Shear slump and collapse slump in slump tests, Civil Engineering

Assignment Help:

Question
What is sign of shear slump and collapse slump in slump tests?

Answer
There are three varieties of slump that might occur in slumps test, specifically, slump, shear slump and collapse slump.

True slump refers to general drop of concrete mass regularly all around without disintegration.

Shear slump implies that concrete mix is lacking in cohesion. Accordingly, it might undergo segregation and bleeding and thus is adverse for durability of concrete.

Collapse slump point out that concrete mix is as well wet and mix is deemed to be harsh and lean.

 


Related Discussions:- Shear slump and collapse slump in slump tests

Pressure distribution under rigid and flexible footings, Pressure distribut...

Pressure distribution under rigid and flexible footings For rigid and thick footings, pressure distribution under the footings is generally presumed to be linear. If symmetric

Calculate uniform annual cost for maintenance and repair, A contractor purc...

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest

Advantageous to use concrete of very high power, Question Will it advantag...

Question Will it advantageous to use concrete of very high power for example exceeding 60MPa? What are potential problems connected with high strength concrete ? Answer To in

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Cantilever beam, The problem in the link below. ">http://www.expertsmind....

The problem in the link below. ">http://www.expertsmind.com/questions/plot-vertical-displacement-cantilever-beam-30134382.aspx#

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

Fire resistance of steelwork, Q. Fire resistance of steelwork Because ...

Q. Fire resistance of steelwork Because of the high thermal conductivity of steel, temperature of unprotected steel is almost the same as temperature of fire. Because the yiel

Dielectric materials are what kind of materials, Dielectric materials are w...

Dielectric materials are what kind of materials ? Answer: It is  insulating materials.

Surveying, A pre- engineering base line was run down a very steep hill.rath...

A pre- engineering base line was run down a very steep hill.rather than measure horizontaily down hill with steel tape: surveyor measured the vertical angle with the theodolite and

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd