Sequence networks , Basic Statistics

Assignment Help:

A group of identical synchronous motors is connected through a transformer to a 4.16-kV bus at a remote location from the generating plants of a power system. The motors are rated (see table 3) and operate at (see table 3) efficiency when carrying full load at unity power factor and rated voltage. The sum of their output ratings is 4476 kW. The reactance in per unit of each motor based on its own input kVA ratings are Xd" = X1= 0.20, X2 =0.20, X0 =0.04 and each is grounded through a reactance of 0.02 per unit. The motors are connected to a 4.16-kV bus through a transformer bank composed of three single-phase units, each of which is rated 2400/600, 2500 kVA. The 500-V windings are connected in D to the motors and the 2400-V windings are connected in Y. The leakage reactance of each transformer is 10%.

The power system which supplies the 4.16-kV bus is represented by a Thevenin's equivalent generator rated at 7500 kVA, 4.16 kV with reactances of Xd" = X2 = 0.10 per unit , X0 = 0.05 per unit, and Xn from neutral to ground equal to 0.05 per unit

Each of the identical motors is supplying an equal share of a total load of 3730 kW and is operating at rated voltage, 85% power factor lag, and 88% efficiency when a single line-to-ground fault occurs on the low-tension side of the transformer bank. Treat the group of motors as a single equivalent motor.

3a. Draw the sequence networks showing values of the impedances

3b. Determine the sub-transient line currents in all parts of the system with pre-fault current neglected

(Note: Each student will be assigned either (1) or (2) parameters in Table 3 for the motor rating.)

Table 3

 

 

 

Rated Voltage

Efficiency

 

 

 

(1)

700

87.5

(2)

550

84.5

(Note: I will be using 550 as the rated voltage and 84.5 as the efficiency in Table 3 for the motor rating.)

 Solution should include:1. Single line diagram of the system described

1. Single line diagram of the system described

2. Sequence network connection diagram with impedances and subtransient currents

3. Detailed calculation of the subtransient current in all parts of the system

a. Calculation of current in the fault

b. Calculation of the prefault current in the lines

c. Current in the fault

d. Current in lines between transformer and fault

e. Current in lines between motor and fault

f. Current in line between bus and transformer

4.. Accuracy of the calculation

5. Analysis of calculation procedure done.


Related Discussions:- Sequence networks

Opertions research, meaning and definition of operations rsearch

meaning and definition of operations rsearch

What is Accrued expenditures or expenses, Costs or expenses that connect wi...

Costs or expenses that connect with the appropriate identification requirements of the finance type engaged but have not been compensated. Acquired expenses are required to be comp

Student, Design an activity based cost system requires that: a) the job bid...

Design an activity based cost system requires that: a) the job bid process redesigned b) resource costs be linked to the activities performed c)the cost of activities be linked to

Determine the price rate-demand , SkyyMarley Airlines has determined that t...

SkyyMarley Airlines has determined that the price elasticity of demand for two customer segments (Coach and Business Class) is -1.35 and -2.50.  Based on their expectations of prof

Dist4ibution, I want support about statistical distributions

I want support about statistical distributions

Quota sampling, what the advantages of quota sampling

what the advantages of quota sampling

How long it takes a ball to fall to the bottom of a cone, A game that frien...

A game that friends and I try to play to guess how long it takes a ball to fall to the bottom of a cone and how many revolutions around the cone it will take. I do not have a lot

Probability, Consider the two events A and B with P(A) = 0.4 and P(B) = 0.3...

Consider the two events A and B with P(A) = 0.4 and P(B) = 0.3. (a) If A and B are independent then compute the probability that Both A and B happen

Determine the probability - probability example, 1. This question has multi...

1. This question has multiple parts. For a distribution of scores with = 82 and standard deviation = 2.5, find the following: (Don't forget to sketch the normal curve to help

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd