Sequence networks , Basic Statistics

Assignment Help:

A group of identical synchronous motors is connected through a transformer to a 4.16-kV bus at a remote location from the generating plants of a power system. The motors are rated (see table 3) and operate at (see table 3) efficiency when carrying full load at unity power factor and rated voltage. The sum of their output ratings is 4476 kW. The reactance in per unit of each motor based on its own input kVA ratings are Xd" = X1= 0.20, X2 =0.20, X0 =0.04 and each is grounded through a reactance of 0.02 per unit. The motors are connected to a 4.16-kV bus through a transformer bank composed of three single-phase units, each of which is rated 2400/600, 2500 kVA. The 500-V windings are connected in D to the motors and the 2400-V windings are connected in Y. The leakage reactance of each transformer is 10%.

The power system which supplies the 4.16-kV bus is represented by a Thevenin's equivalent generator rated at 7500 kVA, 4.16 kV with reactances of Xd" = X2 = 0.10 per unit , X0 = 0.05 per unit, and Xn from neutral to ground equal to 0.05 per unit

Each of the identical motors is supplying an equal share of a total load of 3730 kW and is operating at rated voltage, 85% power factor lag, and 88% efficiency when a single line-to-ground fault occurs on the low-tension side of the transformer bank. Treat the group of motors as a single equivalent motor.

3a. Draw the sequence networks showing values of the impedances

3b. Determine the sub-transient line currents in all parts of the system with pre-fault current neglected

(Note: Each student will be assigned either (1) or (2) parameters in Table 3 for the motor rating.)

Table 3

 

 

 

Rated Voltage

Efficiency

 

 

 

(1)

700

87.5

(2)

550

84.5

(Note: I will be using 550 as the rated voltage and 84.5 as the efficiency in Table 3 for the motor rating.)

 Solution should include:1. Single line diagram of the system described

1. Single line diagram of the system described

2. Sequence network connection diagram with impedances and subtransient currents

3. Detailed calculation of the subtransient current in all parts of the system

a. Calculation of current in the fault

b. Calculation of the prefault current in the lines

c. Current in the fault

d. Current in lines between transformer and fault

e. Current in lines between motor and fault

f. Current in line between bus and transformer

4.. Accuracy of the calculation

5. Analysis of calculation procedure done.


Related Discussions:- Sequence networks

#title.Arithmatic mean., If the mean of first 5 no. is 60 and mean of last ...

If the mean of first 5 no. is 60 and mean of last 5 no. is 55 then what is the 5th no.

Hypotheses- sampling methodology or data collection design, Research Assign...

Research Assignment for Quantitative Methods 2 Purpose: To design, undertake and analyse research on a negotiated project, possible themes could be any one of the following:

Time series, Methods of measuring secular trend

Methods of measuring secular trend

Factor anaylsis statistical method , First of all, thank you very much for ...

First of all, thank you very much for your help. I have a mixes data base, categorial variable, liclekt scale on 5 and 4, and continous variable, and several dummy. I would need h

Books of original entry, Books of original entry Books of original entranc...

Books of original entry Books of original entrance are a record in which the various or many other transactions are initially and formally recorded and serve up as the straight so

Statics process control and improvements, 1. Warm-up Exercise Volumes I,...

1. Warm-up Exercise Volumes I, II, III, and IV of Shakespeare are in sequence next to one another in the library bookcase.  Each volume has 2" of pages and the front and back co

Job order costing, Bedovin company manufactures office tables and chairs us...

Bedovin company manufactures office tables and chairs using job order costing. The data given below were taken from the records as of April 30, the first month of operations. Job

Probability, a survey of grocery revealed 40 percent had a pharmacy, 50 per...

a survey of grocery revealed 40 percent had a pharmacy, 50 percent had a floral shop, and70 percent had a deli. suppose 10 percent of the stores have all three departments, 30 perc

Probebility., what is probebility? and how to solve the sums of this?

what is probebility? and how to solve the sums of this?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd