Segmentally lined and sprayed concrete linings tunnels, Civil Engineering

Assignment Help:

Q. Segmentally lined and Sprayed Concrete Linings tunnels?

The fundamental difference between segmentally lined tunnels and SCL tunnels is that the sprayed concrete in SCL tunnel is employed for temporary linings only. Concrete linings in segmentally lined tunnels are designed with long-term load conditions with adoption of appropriate safety factors. Though the dimension of linings in SCL tunnels is derived from a balance between safety of lining and cost consideration. 

The quality of precast concrete linings can be better controlled in precasting yards. It is obviously better than that of sprayed concrete which depends on site workmanship.


Related Discussions:- Segmentally lined and sprayed concrete linings tunnels

Explain the cross sectional area of flow, Cross-sectional area of flow (ft ...

Cross-sectional area of flow (ft 2 ) (A) For rectangular channels = (w)(d). For trapezoidal channels, divide the flow area into two side triangles and one center rectangle, so

Calculate uniform annual cost for maintenance and repair, A contractor purc...

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Stair, Difinaction of stair

Difinaction of stair

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

REQUIREMENT OF GOOD BUILDING STONE, HOW TO MAKE A GOOD BUILDING .? TELL ABO...

HOW TO MAKE A GOOD BUILDING .? TELL ABOUT SOME TIPS OF REQUIREMENT OF GOOD BUILDING STONE? AND SAY ABOUT CEMENT?

Indicate quality of rock foundation, Question During piling works, norm...

Question During piling works, normally founding levels of bored piles are definite by using total core recovery or rock quality designation (RQD). Are there any problems by

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd