Rolling - Binder:
The layer thickness is 40-50 mm. Rolling is done in three stages :
Initial Rolling
By 80-100 kN smooth wheeled roller.
Intermediate Rolling
By 80-100 kN vibratory roller or by pneumatic tyred roller.
Final Rolling
60-80 kN tandem roller.
Rolling is done till the laboratory density is achieved.
Q. Explain Census of Traffic at Level Crossings? Periodical census of traffic at all level crossings, unmanned/manned should be taken at least once in five years to review the
Project specifications require a relative compaction of 95% (modified Proctor). Construction of a highway embankment requires 10,000-yd 3 of fill. The borrow soil has an in-situ
hi
whatis difference between premix asphalt carpeting and asphalt concrete pavement
Solve the following three questions of the beam ABCD. Note that A is a fixed end; B is apin connection; C is a roller support; and D is a free end. 1) Sketch the quantitative
spiral curves?
short note
Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with div
applying quadratics in civil engineering
precaution to be taken for roads construction in marshy land
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd