Rolling - binder, Civil Engineering

Assignment Help:

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.


Related Discussions:- Rolling - binder

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Conics, what is the eccentricity of ellipse

what is the eccentricity of ellipse

Define air chamber and surge tank, Q. Air chamber vs. surge tank in pressur...

Q. Air chamber vs. surge tank in pressurized pipelines? Air chambers and surge tanks are generally installed in water main to ease the stress on the system when valves or pumps

Mechanical, Define varigions principle of moments and write about system of...

Define varigions principle of moments and write about system of forces?

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

Testing of aggregates, Testing of Aggregates: For use in pavement, ro...

Testing of Aggregates: For use in pavement, road aggregates have to be strong, durable and of good shape. A well-graded aggregates adds to the stability of the layer. The fol

Paints., contituents of paints

contituents of paints

What is long welded rail, Q. What is Long Welded Rail? Long Welded Rail...

Q. What is Long Welded Rail? Long Welded Rail is a welded rail the central part of which dose not under go any longitudinal movement due to temperature variation, normally a le

Show the benefits of adopting marine fill, In reclamation involving large v...

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?  There are two

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd