Road location in dune areas, Civil Engineering

Assignment Help:

Road Location in Dune Areas:

The following principle should be observed in locating a road in dune areas :

(a) Align a road where sand is covered by vegetation.

(b) Select a location where the sand is coarse and cannot be blown by wind.

(c) If a road has to be aligned parallel to a sand ridge, avoid locating the road on the slopes. Locate the road either at the top of the ridge or in the inter-dunal space.

(d) If possible locate the road away from the dune at a minimum distance of twice the dune height.

The details of the location of roads placed in dune areas are given in Figure.

2357_Road Location in Dune Areas.png

Figure : Possible Locations of Road in Sand Ridge

The following guidelines may be observed in design :

(a) Avoid sections with partial cut and partial fill.

(b) Avoid cut sections as far as possible.

(c) Avoid high road embankments.

(d) When cutting is done in dunes, provide benchings 5-8 m wide.

(e) It is preferable to black-top the road, since unsurfaced pavements can get dislodged when the sand deposit is cleared by a grader.

(f) Precast concrete blocks are also be good surfacing specification since the cost of maintenance is minimised.


Related Discussions:- Road location in dune areas

SURVEYING, TYPES OF OBSTACLES IN CHAIN SURVEYING

TYPES OF OBSTACLES IN CHAIN SURVEYING

Sand layer underlying paving slab or interlocking blocks, Question What...

Question What is function of a sand layer underlying paving slab or interlocking blocks? Answer Normally after laying of sub-base layer of paving slab or interlocking

Light-weight aggregate prestressed concrete, Light-weight Aggregate Prestre...

Light-weight Aggregate Prestressed Concrete The use of  light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of  light-

Explain the angle of wall friction, A retaining wall 4.5 m high with vertic...

A retaining wall 4.5 m high with vertical back supports a backfill with horizontal surface. The unit weight of the fill is 18 kN/m 3 and the angle of internal friction is 36°. The

Construction Planning, A contractor has both a 3-cy and a 5-cy shovel in th...

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Overhanging beams, Do we take the whole length (including the over hanging ...

Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd