The life of a road depends upon how well and quickly the water is drained away from its various components. Similarly, regular and periodic inspection and maintenance of a road ensures that the facility lasts over a period it is designed for.

Objectives

After studying this unit, you should be able to :

  • understand the importance of drainage of roads,
  • know surface and subsurface drainage is achieved through side drains, intercepting drains, the subsurface pipe drains and cross-drainage structures, and
  • discuss the road maintenance, how the maintenance needs are assessed and how the maintenance of various types of roads is achieved.

 


Related Discussions:- Road drainage and maintenance

Calculate the parameters for setting out curve, Q For a curve of 50, apex ...

Q For a curve of 50, apex angle of 900 and transition length of 60m, calculate the parameters for setting out curve by a Theodolite for TTP, mid point of transition, CTP and a p

BOLTED CONNECTIONS, compare riveted joints with welded joints

compare riveted joints with welded joints

Define the pressure on a vertical plane, Define the Pressure on a vertical ...

Define the Pressure on a vertical plane Fluid pressure increases linearly with increasing depth. The average pressure on a vertical plane occurs at the average vertical depth.

Pulverized fly ash as cement replacement, Q. Pulverized fly ash as cement r...

Q. Pulverized fly ash as cement replacement? Pulverized fly ash is a type of pozzolans. It is analuminous or siliceous material that possesses no binding ability by itself. Whe

Define project schedule financial analysis, The 6 monthly payment applicati...

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14

Concrete technology, what is the actual quantity of water to be mixed in va...

what is the actual quantity of water to be mixed in various grade of concrete and also the size of gravel to be mixed with in RCC work. Also I want to know the difference between a

Engineering Science, 1(a)Explain the difference between a concurrent and a ...

1(a)Explain the difference between a concurrent and a non concurrent force system . (b)If a non coplanar force system is acted upon by equal and opposite forces,it must be in equil

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd