Review of available records - underwater inspection, Civil Engineering

Assignment Help:

Review of available Records - Preparation for Underwater Inspection?

Before taking up the underwater inspection, a detailed review of drawings and past report should be carried out for

- Types of members in the system

- Types of materials to be encountered

- Type and extent of repairs carried out in past

- Results of last underwater inspection

- Accident or damage caused to the structure Based on the above review, the nature and extent of inspection required should be worked out. If necessary, sketches may be prepared for documentation of inspection items and defects.


Related Discussions:- Review of available records - underwater inspection

Why we use air valves, Q. Why we use Air Valves? Air Valves - Air valve...

Q. Why we use Air Valves? Air Valves - Air valves of proper size and pressure rating at summits. Air valves ensure the safety of the pipe line against collapse when at points o

Track design for line speed improvements, The objective of this module is:-...

The objective of this module is:- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibil

What is the role of sunfilter in building, QUESTION (a) Using an illu...

QUESTION (a) Using an illustration, describe what happens to sunrays when it passes through the atmosphere to reach the ground. (b) What is the role of a sunscreen/sunfil

What is diamond crossing, Q. What is Diamond Crossing? Diamond Crossing...

Q. What is Diamond Crossing? Diamond Crossing is provided when two tracks cross each other either of the same gauge or of different gauges. It consists of two acute crossing (

Construction equipments, what is preventive maintenance and state its advan...

what is preventive maintenance and state its advantages

Explain frame members effective lengths, Explain Frame Members Effective Le...

Explain Frame Members Effective Lengths a. Effective length is a product of an effective length factor (k) and the actual length of the column. b. k depends on the rel

Advantages of using top-down approach, Question What are major advantag...

Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru

Cement, Why we mixm pozzolona in cement

Why we mixm pozzolona in cement

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd