Retardation of fresh concrete, Civil Engineering

Assignment Help:

Retardation of fresh concrete has numerous benefits as below:

(i)  A rapid hydration process leads to loss in concrete strength since concrete will have a poorer structure with a higher gel/space ratio compared with concrete with a lower hydration rate. 

(ii) At the time of the hydration process, a substantial heat of hydration would be produced. If the hydration process is performed too swiftly, it will cause a rapid increase in temperature and leads in considerable early thermal movement in concrete.

(iii) In hot weather concreting, loss of workability is considerable. So as to ensure sufficient compaction of fresh concrete, it is essential to extend the time for fresh concrete to remain plastic.


Related Discussions:- Retardation of fresh concrete

Explain remote sensing technique, Q. Explain Remote sensing technique? ...

Q. Explain Remote sensing technique? Remote sensing is a science or an art of obtaining the information about an object, area or a phenomenon through analysis of data acquired

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Edge piles take up more loads than central piles, Edge piles take up more l...

Edge piles take up more loads than central piles in rigid cap Because of the effect of interaction of individual piles, central piles tend to settle more than the edge piles w

Write important factors that affect permeability of a soil, Determine the i...

Determine the important factors that affect the permeability of a soil. A permeameter of 8.2 cm diameter having a sample of soil of length 35 cm. It can be used either for const

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

Differentiate, differentiate between components and resolved parts

differentiate between components and resolved parts

Project management, Project Management: This unit starts with the gene...

Project Management: This unit starts with the general definition of Project management. Several phases involved in project management are also desribed. Further, the technique

Precast concrete jacking pipes, Question While precast concrete jackin...

Question While precast concrete jacking pipes , from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons? Answer Grout h

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd