Q. Reasons for blockage in pumping concrete ?
Concrete pumping is normally adopted in highly elevated locations for which access for concrete trucks is difficult. Construction works can be boosted up by using concrete pumping since a larger volume of pours can be achieved within a specified duration when compared with normal concrete placing methods.
Blockage can take place at the time of pumping operation for the subsequent two common reasons:
(i) For saturated concrete mixes, pump pressures can force water out of the concrete leading in bleeding. Flow resistance is then increased and can contribute to blockage of pipelines.
(ii) If cement content (or other components of concrete mixes which increase frictional forces) is high, a higher frictional resistance to pumping can develop and concrete can't be pump able.
Explain the Principle of Working of Shock Transmission Unit? The STU consists of a machined cylinder with a transmission rod that is connected at one end to the structure and a
Ask question #Minexaple of wholeiwhole baring 100 words accepted#
what is couple?
During weight training,an athlete pulls a weight of 500 N with his arms pulling on a handlebar connected to a universal machine by a cable.Find the moment of the force about the sh
Question What is relation of bearing pressure on soil nail head to ratio La/Lb, where La is length of soil nail before potential slip circle as Lb is length of soil nail beyo
Define Diving Operation - Preparation for underwater inspection? Use of experienced divers trained and screened by a reputed commercial diving school is critical for successful
Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?
Calculate the Actual Water Cement Ratio A jobsite delivery ticket is shown below for a grout mix. The actual w/c ratio is most nearly: Solution: Note, althou
Solve the following problems related to Wastewater flow and densities (a) The volume of 896, 000 lb of wastewater is? (b) The weight of 13,000 ft3 of wastewater is? (c) A
The sketch shows a common consumer product called Water Pik. This device uses a motor to drive a piston pump that produces a jet of water (diameter d = 3 mm, temperature T = 10 °C)
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd