Raft base of pumping stations, Civil Engineering

Assignment Help:

Question

Why are voids filled with lightweight infilling material in raft base of pumping stations?


Answer


To decrease dead load and therefore to decrease settlement of pumping stations, voids inside raft foundations are overflowing with light material. If in its place concrete is placed in these voids, it poses harsh thermal cracking difficulty and drastically increases loads to pumping stations. Use of general fill is also not desirable since its self-weight is comparable to that of concrete. On contrary, if these voids are left vacant, water might penetrate into these voids during future operation and increases dead load of pumping stations during its standard operation. So, lightweight infill material that is non-water-absorbing and non-biodegradable is intended inside these voids to stay away from ingress of water and to reduce dead load of structure.

 


Related Discussions:- Raft base of pumping stations

Determine the governing effective length of a steel column, Determine the g...

Determine the governing effective length of a steel column? Determine the governing effective length of a W12 x 106 steel column that is 12' high, pinned at each end, and

Rcc, difference between RCC and RBC

difference between RCC and RBC

Elastic curve, elastic curve of a simply supported beam with triangular loa...

elastic curve of a simply supported beam with triangular load

Explain the well drawdown equations - ground water, Explain the Well Drawdo...

Explain the Well Drawdown Equations Watch the units, especially if you use log 10 or ln.    h 1 = aquifer thickness minus the drawdown (ft)  r 1 = distance from well (ft

Define emerging trends in bearings, Define Emerging Trends in Bearings? ...

Define Emerging Trends in Bearings? New innovations have taken place in the area of bridge bearings, notable among them are: (1) Shock Transmission Unit (STU) or Lock Up Dev

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Road location in dune areas, Road Location in Dune Areas: The followi...

Road Location in Dune Areas: The following principle should be observed in locating a road in dune areas : (a) Align a road where sand is covered by vegetation. (b) Sel

Void ratio, a soil sample is 38mm in diameter and 76mm and in its natural c...

a soil sample is 38mm in diameter and 76mm and in its natural condition weighs 168g.when dried completely in an oven weighs 13o.5g.the value of Gs is 2.73.what is the degree of sat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd