Why are voids filled with lightweight infilling material in raft base of pumping stations?


Answer


To decrease dead load and therefore to decrease settlement of pumping stations, voids inside raft foundations are overflowing with light material. If in its place concrete is placed in these voids, it poses harsh thermal cracking difficulty and drastically increases loads to pumping stations. Use of general fill is also not desirable since its self-weight is comparable to that of concrete. On contrary, if these voids are left vacant, water might penetrate into these voids during future operation and increases dead load of pumping stations during its standard operation. So, lightweight infill material that is non-water-absorbing and non-biodegradable is intended inside these voids to stay away from ingress of water and to reduce dead load of structure.

 


Related Discussions:- Raft base of pumping stations

Find the maximum stress, Find the maximum stress: A circular bar rigid...

Find the maximum stress: A circular bar rigidly fixed at both ends is 1 m long and tapers uniformly from 20 cm diameter at one end to 10 cm diameter at the other end. Find the

Advantages of unbonded post-tensioning systems, Advantages of unbonded post...

Advantages of unbonded post-tensioning systems Similarly, some advantages of unbonded post-tensioning systems over bonded post-tensioning ones may be written as under :  (a)

Explain flow measurement with weirs, Explain Flow Measurement with Weirs ...

Explain Flow Measurement with Weirs Fixed plates positioned vertically in an open channel over which flow is directed through an opening. The opening linear distance is termed

Primavera, hi contactme 9902142308

hi contactme 9902142308

Engineering Graphics, Draw a parabola , height 40mm and bass 120mm using of...

Draw a parabola , height 40mm and bass 120mm using offset method

Butt weld – from one side vs from both sides, Q. Butt weld – from one side ...

Q. Butt weld – from one side vs from both sides? In the design of butt weld strength, it's normally presumed that its strength is at least equivalent to parent metal. To improv

Calculate the poissons ratio, Calculate the Poissons Ratio: In separat...

Calculate the Poissons Ratio: In separate experiments, Young's Modulus and Rigidity Modulus of a material have been determined as 120 GPa and 50 GPa respectively. Calculate th

What is the meaning of elastic shortening of concrete, What is the meaning ...

What is the meaning of Elastic Shortening of Concrete At the transfer stage, compressive prestressing force is transferred to the concrete. Due to this compressive force, concr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd