Quantitative Technique for business, Operation Research

Assignment Help:
Davidson construction company is building a luxury lakefront home in batangas coordination of the architech an sub contractors will require a major effort to meet the 44-week (approximately 10-month completion date requested by the owner. the Davidson project manager prepared the following information.

A none 4 8 12
B A 6 7 8
C A 6 12 18
D A 3 5 7

Related Discussions:- Quantitative Technique for business

Line balancing methods - heuristic approach, Line Balancing Methods - Heuri...

Line Balancing Methods - Heuristic Approach  Heuristic mean serving to find i.e. to find out discover things for oneself. Heuristic describes a particular approach to problem so

LLP, A paper mill produces two grades of paper viz., X and Y. Because of ra...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Models, Which model is described as a rule of thumb

Which model is described as a rule of thumb

Steps of research proposal, Steps of Research Proposal Proposal Con...

Steps of Research Proposal Proposal Content  The researcher is always given instructions for preparing a proposal that indicate the format to be followed. Funding agencie

Chi square test as a test of homogeneit, Chi Square Test as a Test of Homog...

Chi Square Test as a Test of Homogeneit The X 2 test of homogeneity is an  extension of the chi square  test of independence of attributes. It is  designed to determine  whet

Innovation.., identify a new technological innovation not yet commercialize...

identify a new technological innovation not yet commercialized (e.g., house cleaning robotic). What are the product''s features? In your paper, explain how that technological innov

Operation research and decision making, Operations Research uses the meth...

Operations Research uses the methods of science to understand and explain the phenomena of operating systems. It devises the theories( models ) to explain these phenomena

Operation Research, A paper mill produces two grades of paper viz., X & Y. ...

A paper mill produces two grades of paper viz., X & Y. Because of raw material restrictions, it cannot produce more 400 tons of grade X paper & 300 tons of grade Y paper in a week.

LPP, A paper mill produces two grades of paper viz., X and Y. Because of r...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Linear programming problem, Solve the following Linear Programming Problem ...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd