During the analysis of a process that was evaluated, a situation arose where it was seen that the variability of the data points collected was non-random on several occasions, i.e, it did not meet acceptable quality standards. However, when an investigation was done to find the cause of the problem, assignable causes were not revealed and the quality team felt that they were “hitting a wall”
(i) What are some of the possible explanations for not finding any assignable causes?
(ii) If you were a quality manager working on this project, what recommendations would you make to proceed from this situation?

Related Discussions:- quality management

Factors affecting organisational structure , Factors Affecting Organisation...

Factors Affecting Organisational Structure-process of structuring-LIBRARAY MANAGEMENT A manager has to design a structure that will best suit the specific requirements of his

Challenges in quality improvement, C hallenges Quality improvement can...

C hallenges Quality improvement can create conflicting situations and could result in complications. Project team members may be disillusioned by the past failures. The past e

Rung process, RUNG PROCESS   In a library we classify and catalogue a b...

RUNG PROCESS   In a library we classify and catalogue a book after it is acquired and entered in the Accession Register. After cataloguing the book, the entries will be filed i

Classification and cataloguing policy, Classification and Cataloguing Polic...

Classification and Cataloguing Policy: Whatever may  be the scheme of classification or catalogue code chosen, a policy should  be formulated for their application. Some  of t

Outline the major functions of the national assembly, QUESTION 1 What w...

QUESTION 1 What were the main arguments for and against the Independence of Mauritius in the 1960s? QUESTION 2 "The President of the Republic of Mauritius is a constitu

History of quality and project management, Brief History of Quality and Pro...

Brief History of Quality and Project Management It would be interesting to track down how the quality movement and the project management approach began and how today they stan

Answers Please, Question 1 of 16 4.0 Points Six (6) samples of size five ...

Question 1 of 16 4.0 Points Six (6) samples of size five (5) were used to collect the data presented below: sample number 1 2 3 4 5 6 sample mean (x-bar) 8.0 8.1

Cumulative index work and loose issue shelving work, Cumulative Index Work:...

Cumulative Index Work: As the name suggests, it pertains to noting by entering down the announcement of cumulative index followed by entering  the receipt of cumulative index

Internal techniques of exposure management, Question 1: i) What are eu...

Question 1: i) What are eurosecurities? ii) Assess the reasons for the growth in eurosecurities markets and discuss the implications of these markets for international ban

Assessment of project quality, A ssessment of Project Quality Quality ...

A ssessment of Project Quality Quality management can be measured by having three main components: Quality control. Quality assurance. Quality improvement.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd