Purpose of setting minimum amount of longitudinal steel area, Civil Engineering

Assignment Help:

Q. Purpose of setting minimum amount of longitudinal steel areas for columns?

In some design codes it specifies that area of longitudinal steel reinforcement must be not less than a specific percentage of sectional area of column. Initially the limitation of steel ratio for columns helps to guard against potential failure in tension. Tension can be induced in columns during design life of concrete structures. For example tension is induced in columns in case there is uneven settlement of building foundation or upper floors above the column are completely unloaded whereas the floors below column are strictly loaded. Secondly because of the effect of creep and shrinkage, there would be a redistribution of loads between steel and concrete reinforcement. So steel reinforcement can yield easily in case a lower limit of steel area isn't established.

Additionally, test results indicated that columns with too low a steel ratio will render the equation below inapplicable that is used for design of columns:

N=0.67fcuAc+fyAs


Related Discussions:- Purpose of setting minimum amount of longitudinal steel area

Explain template jig, Explain Template Jig? 1) Template jig is the simp...

Explain Template Jig? 1) Template jig is the simplest type of jig, employed for accuracy than speed. 2) This jig fits over, on, or, into the work and is not generally clampe

Beams of uniform strength, determine the cross section of a rectangular bea...

determine the cross section of a rectangular beam of uniformly strength for a simply supported beam of 6m span subjected to central concentrated load of 20kN a)by keeping depth of

Cycle, what is motor cycle. please explain.

what is motor cycle. please explain.

State the procedure of prestressing, State the procedure of prestressing ...

State the procedure of prestressing When these wires cool down, concrete is poured in the moulds in which these tendons are provided in a stretched condition. Using this proces

Explain the clearance interval - signalized intersections, Explain the Clea...

Explain the Clearance Interval - Signalized Intersections  Also known as "Red Clearance Interval" and "All Red"        r = (w+L) / V - If there is no pedestrian traffic r

Purpose of the gap in the road on this bridge, What is the purpose of the g...

What is the purpose of the gap in the road on this bridge? Ans) Purpose of the gap in the road is to permit the road to expand and contract with temperature alters without causi

Ballast and sub-ballast aggregates, I want to check the grammer of report a...

I want to check the grammer of report and edit it in better sentances , reduce the Plagiarism & edit the reference to havaerd style

Flow, what is maximum flood level

what is maximum flood level

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd