Prototype sand blast method, Mechanical Engineering

Assignment Help:

During the test run of prototype machine we found out a few issue occurred due to blasting room design problem. The blasting room design is too quartet, this design had cause the blast abrasive bounce back and hit on the blade product. This had result a lot of damage on blade cutting edge. Figure below shown clearly on the sand blast flows are all bounce back and hit on the blue block (blade rod). This was incident was out of our consideration scope.

              The prototype's blasting room needed to do modification to divert the sand blast force to another direction instead of bouncing back to product. We had come out an idea to fabricate a curve plate to fix on blasted wall. We are trying to diverting the blast force direction to the side where no part is placed.

              New fabricated plate with a V shape design are try to divert all the blast force into another direction which will not bounce back to the product. This prototype blasting machine will blast the same blade rod for twice. Reason is to double make sure there is no burrs are able to remain at the blade tips. Previous experiment we were using single blast nozzle, but here we are increased the quantity of nozzle to 2. Reason is that we found out this additional nozzle helped to reduce manufacturing takt time and able to produce the expected quality.


Related Discussions:- Prototype sand blast method

Rankine Cycle, In a nuclear power plant saturated steam at 30 bar enters a ...

In a nuclear power plant saturated steam at 30 bar enters a h.p. turbine and expands isentrophically to a pressure at which its quality is 0.841. At this pressure the steam is pass

Concept of continum, in concept of continum what is the meaning of upper cu...

in concept of continum what is the meaning of upper cure

Spring, direct shear and torsional shear of the coil

direct shear and torsional shear of the coil

Calculate the amount sand-aggregate, Calculate the amount of cement, sand,...

Calculate the amount of cement, sand, aggregate, and water needed to create a concrete mix with a 28-day compressive strength of 34 MPa for a 10 m x 10 m x 0.25 m structure given t

Introduction to advance manufacturing, INTRODUCTION In the morning se...

INTRODUCTION In the morning session there was a discussion about what the teachers are going to do in this week. Later the professor has shown power point presentation on int

Boiler, Working, specification construction of Lancashire boiler

Working, specification construction of Lancashire boiler

What are the capabilities of step, What are the capabilities of STEP In...

What are the capabilities of STEP Industry-Developed STEP Capabilities AP-203, Configuration Control for 3D Design of Mechanical Parts and Assemblies, provides a very robust

Explain working of steam drum, Q.Explain working of Steam Drum? Total so...

Q.Explain working of Steam Drum? Total solids concentration in the steam at steam manifold outlet shall not exceed 0.5 ppm during steady operation at MCR.  Fabricator must indic

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd