Projects at times get delayed due to various factors, Project Management

Assignment Help:

QUESTION

a) Project management activities are carried out in a planned manner. List the distinguishing characteristics of a project?

b) During project management meetings, there are two common terms, among others, that are used frequently namely (1) gates and (2) milestones. Explain what you understand by the term (1) gates and (2) milestones

c) A project plan aims to ensure that the project objectives are achieved within the constraints of quality, cost and time. Explain the importance of a project plan

d) In this IT era managing huge projects is greatly facilitated by the use of appropriate tools, such as the planning and control of the project will be assisted through the use of appropriate software Explain the steps that you would follow to choose aproject management software

e) Projects at times get delayed due to various factors. What are possible corrective actions that can be taken to bring the project back on track?


Related Discussions:- Projects at times get delayed due to various factors

Human resource function perform its role effectively, Describe the ways in ...

Describe the ways in which IS and IT might help an organisation's human resource function perform its role effectively. Assisting HR planning. In order to construct robust HR s

Explain how using a project management methodology, DG Company has made a s...

DG Company has made a significant investment in a project to develop a new client management IT system, which when implemented should help give the company a competitive edge.  How

Describe the organisational culture, 1. Briefly trace the development and g...

1. Briefly trace the development and growth of Walmart from 1969 to the present through the application of corporate strategies - what types of strategies have these been? 2. Th

Identify the characteristics of the organisation, M is a business that sell...

M is a business that sells custom made computer-based information systems. Every customer order is for a unique system, which will contain experts from many functional areas within

Determine elapsed time of critical path, Determine elapsed time of critical...

Determine elapsed time of critical path when The critical path is given by points BCFG and the elapsed time 17 weeks. There D can over running by up to 3 weeks without

MSc PM, Hi I would like to know if you assist on the dissertation or what s...

Hi I would like to know if you assist on the dissertation or what services you can provide. Thanks,

Explain the utility of base costs, Question 1: (a) ‘One of the most pow...

Question 1: (a) ‘One of the most powerful concept as advocated by Total Quality Management is that of the internal customer and supplier.' With reference to examples you ar

Factors affecting process design - degree of automation, Factors affecting ...

Factors affecting Process Design - Degree of Automation The degree of automation  to be  adopted and  integrated into the  production  system is a key issue in process design,

What do you mean by gates and milestones, What do you mean by Gates and Mil...

What do you mean by Gates and Milestones? Gates and milestones: Milestones are a completion of main interim objectives for a project for example the key stages of a pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd