1. A powder metal (PM) manufacturing line produces bushing in three steps, compaction, sinter-harden, and rough/O?nish turn, which are accomplished at three single machine stations with average processing times of 12, 10 and 6 minutes, respectively. However, while compaction and sinter-harden are dedicated to the bushing line, the rough/O?nish turn station also processes bearings from another line; the average processing time for bearings are 14 minutes.

1. (a) If the production volume of bushings and bearings are the same, what is the bottleneck of the PM line?

2. (b) If the volume of bearings is 3 times that of the volume of bushings, what is the bottleneck of the PM line?


Related Discussions:- Production volume of bushings as well bearings are the same

Trigger changes in aspects of practice, What is a critique? Simply stated, ...

What is a critique? Simply stated, a critique is a critical analysis undertaken for some purpose. Nurses critique research for three main reasons: to improve their practice, to bro

Column minima method, Column Minima Method: Step 1: Determine  the  ...

Column Minima Method: Step 1: Determine  the  smallest cost in  the first  column  of the  transportation  table. Let it be  C1j  . allocate  Xi1= min ( ai bi ) in the cell

Explain value differences among national cultures, What are some managerial...

What are some managerial styles you would employ in managing an emloyee who is considered baby boomer List and explain hofstedes five dimensions of value differences among natio

Explain same day delivery manufacturing process, Describe FedEx Office and ...

Describe FedEx Office and Same Day delivery manufacturing process and scheduling approach

Limitations of e-business, Limitations of E-Business 1.      Problems ...

Limitations of E-Business 1.      Problems relating to the security of the data  2.      Limitations of bandwidth (speed of data transmission)  3.      Standardisation o

Explain what should johnson estimate time and parts costs, Johnson Industri...

Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labour hours, and

Explain instituting formal performance appraisal, What are some prerequisit...

What are some prerequisite conditions that must exist before instituting formal performance appraisal?

Define current inventory control system for football helmets, Tune Football...

Tune Football Helmets Company is considering changing its current inventory control system for football helmets. The information regarding the helmets is given below. Demand = 2

Describe set up more responsible governance, You are consulting with a comp...

You are consulting with a company that is failing. It seems the CEO (recently fired) paid no attention to the board of directors. He was also heard to say, "I don't serve stockhold

Define what should hr do about the older workers, What do companies have to...

What do companies have to do about their workforce force that has gotten older and there are not of younger to replace the aging workers? What will be the company best course of ac

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd