Production volume of bushings as well bearings are the same, Operation Management

Assignment Help:

1. A powder metal (PM) manufacturing line produces bushing in three steps, compaction, sinter-harden, and rough/O?nish turn, which are accomplished at three single machine stations with average processing times of 12, 10 and 6 minutes, respectively. However, while compaction and sinter-harden are dedicated to the bushing line, the rough/O?nish turn station also processes bearings from another line; the average processing time for bearings are 14 minutes.

1. (a) If the production volume of bushings and bearings are the same, what is the bottleneck of the PM line?

2. (b) If the volume of bearings is 3 times that of the volume of bushings, what is the bottleneck of the PM line?


Related Discussions:- Production volume of bushings as well bearings are the same

Explain travel time of a community, A bank is planning to serve the rural c...

A bank is planning to serve the rural communities shown in figure 10.8 with automated teller machines (ATMs). The travel time in minutes between communities in the service area is

Explain what is the current multifactor productivity, Question 1 of 6. Ambe...

Question 1 of 6. Amber Patel operates a delicatessen store in South Lambert, Nevada. Currently, the store has 4 employees, each one working 160 hours per month. Because of its exce

Drawbacks and challenges designing this job for efficiency, Consider the jo...

Consider the job of a customer service representative who fields telephone calls from customers of a retailer that sells online and through catalogs. What measures can an employer

Explain what is an ethics audit, • What is an ethics audit and why is it i...

• What is an ethics audit and why is it important to an organization? Explain the benefits and challenges of conducting one. • Why is it important to link the ethics audit bac

LINE BALANCING, What do you understand by “line balancing”? What happens if...

What do you understand by “line balancing”? What happens if balance doesn’t exist?

Describe presence of an outside threat correlates, Some people argue that t...

Some people argue that the presence of an outside threat correlates with high degree of team cohesion. Would you agree or disagree?

MBA, Q3. What do you understand by “line balancing”? What happens if balanc...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Production control function, Production control Function 1. Dispatchi...

Production control Function 1. Dispatching : Dispatching may be  defined as setting  production activities in motion through  the  release  of orders ( work order shop order)

Explain team prior to raising a follow-on fund, How should foster position ...

How should foster position herself and her team prior to raising a follow-on fund?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd