Production volume of bushings as well bearings are the same, Operation Management

Assignment Help:

1. A powder metal (PM) manufacturing line produces bushing in three steps, compaction, sinter-harden, and rough/O?nish turn, which are accomplished at three single machine stations with average processing times of 12, 10 and 6 minutes, respectively. However, while compaction and sinter-harden are dedicated to the bushing line, the rough/O?nish turn station also processes bearings from another line; the average processing time for bearings are 14 minutes.

1. (a) If the production volume of bushings and bearings are the same, what is the bottleneck of the PM line?

2. (b) If the volume of bearings is 3 times that of the volume of bushings, what is the bottleneck of the PM line?


Related Discussions:- Production volume of bushings as well bearings are the same

Explain formal communication chain effective, Most organizations possess so...

Most organizations possess some formal organizational chart showing the established lines of authority and the division of labour. Generally, formal processes of communication are

Record of operations in an organisation, Record of operations in an organis...

Record of operations in an organisation If the operation to be studied already exists it is important to record its details by direct observation. To help in this, many tools

Explain what recommendations would you make and why, 1. Draw a process flow...

1. Draw a process flow diagram of the process described in the case. Be sure to identify the key resources involved and the task times at each step. 2. What is utilization at ea

Operational Management, I have a take home exam that I need to be solved 10...

I have a take home exam that I need to be solved 100 % correct , please . I need it within 23 hours EXACTLY from now please . Thank you so much and I am really looking forward to s

Explain improve matters and rectify the injustice, What could you or the pe...

What could you or the person who was treated unfairly have done to improve matters and rectify the injustice on the spot?

Kaplan and norton balanced scorecard framework, Kaplan and Norton Balanced ...

Kaplan and Norton Balanced Scorecard Framework Kaplan and Norton (1992, 1993, and 1996) describe the concept of a 'balanced scorecard' that includes four categories of measure

Operation management functions, Operation Management functions Operatio...

Operation Management functions Operations Management has many functions to carry out the transformation procedure efficiently. The function incorporates various roles which are

Explain various elements of strategic leadership, 1. Discuss the various el...

1. Discuss the various elements of strategic leadership. 2. Do you believe that one's propensity to become a leader is an acquired skill or that the ability to be a leader is so

Explain what is the makespan and machine idle time, Sequence the jobs shown...

Sequence the jobs shown below by using the Gantt chart. Assume that the move time between machines in one hour. Sequence the jobs in priority order 1,2,3,4. Job Work Center/Machine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd