Process selection and process design, Operation Management

Assignment Help:

Process Selection and Process Design

Having identified alternative process sequences and process span choices, the question then to be answered is which of the configurations should be selected for implementation. The answer to this question may not be straightforward. The simplest case would be where, for all of the process sequences being considered, the various processes entailed are already owned by the company, and there is enough free capacity to meet the forecast demand.

1290_Process Selection and Process Design.png

In this case a simple break-even analysis may help in making the choice. For each of the process sequences to be compared, the fixed and variable costs are determined: the fixed costs are those, such as special tooling costs, which are required to set up the processes and are independent of the volume of output; variable costs are those, such as direct labour and material costs, which vary in direct proportion to the output volume. This figure shows, graphically, how the total costs of three process sequences (A, B and C) change with volume of output, alongside the associated revenue. This shows that, for quantities below V1, none of the process sequences recover their costs; for quantities between V1 and V2, process sequence A is the most economical; for quantities greater than V2, process B becomes the least costly. Notice that, in this illustrative example, process sequence C is uncompetitive at all levels of output.

The question may be more difficult to answer if one or more of the competing process sequences require significant capital expenditure. In this case, in addition to break-even analysis, investment appraisal tests may be applied. For example, a process sequence which is attractive according to break-even analysis may be rejected on the basis that its payback period renders the necessary investment too risky. Further consideration of break-even analysis and investment appraisal techniques are beyond the scope of this unit, but are covered at length in Finance and Financial Management.

 


Related Discussions:- Process selection and process design

Determine the wbs shown below, Consider the WBS shown below: 1.00.00 1.1...

Consider the WBS shown below: 1.00.00 1.1.0 1.1.1 1.1.2 1.2.0 1.2.1 1.2.2 If the total program costs $100,000 and 1.2.1 and 1.2.2 are each $20 K, then the cost of 1.1.0 is:

Explain use debt financing, If you decide to use debt financing, which kind...

If you decide to use debt financing, which kind of loan, fixed-rate or variable-rate, would you prefer? Why? If you decide to use equity financing, where would you find equity f

Blockbuster offer potential partners to improve its position, Looking to th...

Looking to the future, what value-added components could Blockbuster offer potential partners to enhance its position in the environment?

Explain step of the risk identification process in a project, Describe the ...

Describe the outputs and subsequent steps of the risk identification process in a project.

Operations management and globlization, Briefly explain operation managemen...

Briefly explain operation management and globalization

Which depreciation method is preferable and why, 1. Your firm is considerin...

1. Your firm is considering an investment in a wind farm. Assume that the farm will cost $1 million per MW of installed capacity. The plan under consideration would deploy 10 GE 1.

#title=OEF., TWO HANDED CHART WITH 10 OPERATIONS

TWO HANDED CHART WITH 10 OPERATIONS

What is operations strategy, What is operations strategy? Operations ...

What is operations strategy? Operations strategy: According to Slack and Lewis the definition operations strategy: The total pattern of decisions that shape the long

Demerits of continuous or flow production, Demerits of Continuous or Flow P...

Demerits of Continuous or Flow Production The production problem which may arise particularly in high volume flow is that the constant repetition of a short time cycle task may

Gantt chart, Gantt Chart The Gantt chart were made by Henry L. Gantt ...

Gantt Chart The Gantt chart were made by Henry L. Gantt approximately a century ago. Their aim is to provide an immediate comparison between schedule and realty( i.e. among p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd