Process selection and process design, Operation Management

Assignment Help:

Process Selection and Process Design

Having identified alternative process sequences and process span choices, the question then to be answered is which of the configurations should be selected for implementation. The answer to this question may not be straightforward. The simplest case would be where, for all of the process sequences being considered, the various processes entailed are already owned by the company, and there is enough free capacity to meet the forecast demand.

1290_Process Selection and Process Design.png

In this case a simple break-even analysis may help in making the choice. For each of the process sequences to be compared, the fixed and variable costs are determined: the fixed costs are those, such as special tooling costs, which are required to set up the processes and are independent of the volume of output; variable costs are those, such as direct labour and material costs, which vary in direct proportion to the output volume. This figure shows, graphically, how the total costs of three process sequences (A, B and C) change with volume of output, alongside the associated revenue. This shows that, for quantities below V1, none of the process sequences recover their costs; for quantities between V1 and V2, process sequence A is the most economical; for quantities greater than V2, process B becomes the least costly. Notice that, in this illustrative example, process sequence C is uncompetitive at all levels of output.

The question may be more difficult to answer if one or more of the competing process sequences require significant capital expenditure. In this case, in addition to break-even analysis, investment appraisal tests may be applied. For example, a process sequence which is attractive according to break-even analysis may be rejected on the basis that its payback period renders the necessary investment too risky. Further consideration of break-even analysis and investment appraisal techniques are beyond the scope of this unit, but are covered at length in Finance and Financial Management.

 


Related Discussions:- Process selection and process design

Explain disadvantages of financing via the internet, What are the advantage...

What are the advantages and disadvantages of financing via the internet?

Describe delaying completion of the project, Using the data in Table 13-1, ...

Using the data in Table 13-1, what is the latest possible time that C may be started without delaying completion of the project? Table 13-1 The following represents a project with

Explain city water supply system, The network in figure below shows the pip...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant (node 1) to a city water supply system (node 14). The arc capacities

Define as a labour relations specialist in the hr department, The committee...

The committee is asking you, as a labour relations specialist in the HR department, whether this wording is likely to be acceptable

Explain steps are critical to sustaining change, Which of Kotter's 8 steps ...

Which of Kotter's 8 steps are critical to sustaining change? (You can list multiple steps.) Why do some change leaders fail to properly address sustaining change?

Explain level of threshold service of a least-cost system, What is meant by...

What is meant by the level of threshold service of a least-cost system

Explain the factors that are driving change in the industry, Prepare a brie...

Prepare a brief analysis of the vacation cruise industry using Porters Five Force Analysis. Briefly discuss the nature and strength of each of the five competitive forces. Identify

Product layout - process design, Product Layout - process design Where...

Product Layout - process design Where the volume of output is high, as in large-batch and continuous operations, it becomes economically viable to lay out the processes conti

Define the term management, Define the term Management.  Ans:  "Mana...

Define the term Management.  Ans:  "Management is the accomplishment of results by the efforts of many people"  - LAWRENCE APPLEY   "Management is the art of getting

Explain evaluation or rewards systems a source of conflict, How are differe...

How are different evaluation or rewards systems a source of conflict?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd