Process selection and process design, Operation Management

Assignment Help:

Process Selection and Process Design

Having identified alternative process sequences and process span choices, the question then to be answered is which of the configurations should be selected for implementation. The answer to this question may not be straightforward. The simplest case would be where, for all of the process sequences being considered, the various processes entailed are already owned by the company, and there is enough free capacity to meet the forecast demand.

1290_Process Selection and Process Design.png

In this case a simple break-even analysis may help in making the choice. For each of the process sequences to be compared, the fixed and variable costs are determined: the fixed costs are those, such as special tooling costs, which are required to set up the processes and are independent of the volume of output; variable costs are those, such as direct labour and material costs, which vary in direct proportion to the output volume. This figure shows, graphically, how the total costs of three process sequences (A, B and C) change with volume of output, alongside the associated revenue. This shows that, for quantities below V1, none of the process sequences recover their costs; for quantities between V1 and V2, process sequence A is the most economical; for quantities greater than V2, process B becomes the least costly. Notice that, in this illustrative example, process sequence C is uncompetitive at all levels of output.

The question may be more difficult to answer if one or more of the competing process sequences require significant capital expenditure. In this case, in addition to break-even analysis, investment appraisal tests may be applied. For example, a process sequence which is attractive according to break-even analysis may be rejected on the basis that its payback period renders the necessary investment too risky. Further consideration of break-even analysis and investment appraisal techniques are beyond the scope of this unit, but are covered at length in Finance and Financial Management.

 


Related Discussions:- Process selection and process design

Explain what are the values of the slack, For the linear program Max 3A + 2...

For the linear program Max 3A + 2B s.t. A + B ? 4 3A + 4B ? 24 A ? 2 A - B ? 0 A, B ? 0 a. Write the problem in standard form. b. Solve the problem. c. What are the values of the s

Explain what is nominal damage, What is the difference between compensatory...

What is the difference between compensatory damages and consequential damages? Provide at least one relevant example of each that was not included in your textbook. What is nominal

Linear Programming , A paper mill produces two grades of paper viz., X and ...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Explain how often do you think very favourable, How often do you think very...

How often do you think very favourable, intermediate, or very unfavourable situations occur to leaders in real life? Based on Fiedler's theory

Explain collaboration solutions in the face of economic, Why are unions exp...

Why are unions exploring new collaboration solutions in the face of economic/work adversity?

Explain why organizational restructuring is needed, Matrix structures allow...

Matrix structures allow for workers to be shared on multiple projects and at a lower than usual cost. Answer To be shared on multiple projects and at a lower than usual cost

Find gross domestic product is accounted for by logistics, What percent of ...

What percent of North American gross domestic product is accounted for by logistics? Almost 11 percent Almost 22 percent Almost 33 percent Almost 44 percent Flingers

Define activity a can be finished and not delay any activity, Using the dat...

Using the data in Table 13-4, determine the latest time activity A can be finished and not delay any activity? Table 13-4 The following represents a project with known activity tim

Hidden markov models, Hidden Markov Models: We discussed an example of...

Hidden Markov Models: We discussed an example of determining the most probable state path with the Viterbi algorithm. We also discussed in the class how to calculate the margi

Define frame relay is a technology that does noerror control, Frame relay i...

Frame relay is a technology that does no error control. If a frame arrives garbled, it is dropped and frame relay does not inform the transmitter. Is this a reasonable approach?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd