Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

What are the capabilities of step, What are the capabilities of STEP In...

What are the capabilities of STEP Industry-Developed STEP Capabilities AP-203, Configuration Control for 3D Design of Mechanical Parts and Assemblies, provides a very robust

Hill roads - road under special conditions, Hill Roads: Alignment ...

Hill Roads: Alignment Selection and Geometric Design Standards Here, you have already learnt how an alignment of a hill road has to be selected. The selection of a g

Horizontal curves - railways, Horizontal Curves - Railways In railwa...

Horizontal Curves - Railways In railway engineering, the horizontal curve is defined by its degree as well as by its radius. The degree is the angle subtended at the centre

Working of a four-stroke engine , Working of a Four-stroke Engine: To unde...

Working of a Four-stroke Engine: To understand the working of a four-stroke motorcycle engine, the whole operation can be divided into four parts, known as strokes. The strokes ar

Compute the deflection and maximum bending stress, For the beam shown in Fi...

For the beam shown in Figure compute the deflection at the element nodes. The modulus of elasticity is psi and the cross section is as shown in the figure. Also compute the maximum

Center of Gravity, Determine the Center of Gravity of a thin hollow right c...

Determine the Center of Gravity of a thin hollow right circular cone of height H and radius of the base circle R.

Explain concept of a corner or angled window, Question 1: Retail design...

Question 1: Retail design tends to be rapid turnover business. Your potential client needs a window display for his retail sports wear shop for the summer sales. The assumed bu

Explain working of steam sampling, Q. Explain working of Steam Sampling? ...

Q. Explain working of Steam Sampling? Sample coolers shall be supplied by the Vendor. A common sample spillage trough shall also be provided by the Vendor, with a cover screen

Causeways, Paved Dips: Paved dips, also known as bed level causeways,...

Paved Dips: Paved dips, also known as bed level causeways, are structures consisting of gentle and shallow depressions in the road where the water is allowed to flow over the

Metallurgy, what is mean by precipitation hardening?

what is mean by precipitation hardening?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd