Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Washing and drying a motorcycle, Washing and Drying a Motorcycle :  It is ...

Washing and Drying a Motorcycle :  It is important to wash and dry the motorcycle before servicing. It would ensure cleanliness during the service and would not allow any dust ent

Create a pay - off table, Bhasker operates a retail shop and sells the high...

Bhasker operates a retail shop and sells the high priced "Hot Food" thermoware. Each unit I priced at Rs.250. Experience has shown that the weekly demand schedule for items is as f

Explain moulding sand for non-ferrous casting, Q. Explain Moulding Sand for...

Q. Explain Moulding Sand for Non-ferrous Casting? The melting point of non- ferrous metal is much lower than that of ferrous metals. Therefore, the moulding sands for non-ferr

Construct the load displacement diagram, A suspended walkway in an undergr...

A suspended walkway in an underground cavern consists of a deck supported by three tie rods placed symmetrically about the centre as shown below: The rods are each of

Objectives registration scheme entrepreneurship development, Objectives of ...

Objectives of the Registration Scheme They are summarized as follows: To enumerate and maintain a roll of small industries to which the package of incentives and suppor

Batteries and alternative sources of energy, Illustrate six typical applica...

Illustrate six typical application of primary cells. (b) Illustrate six typical applications of secondary cells. (c) Illustrate the advantages of a fuel cell over a conventional

Determine the angular acceleration of the motion, Determine the angular acc...

Determine the angular acceleration of the motion: A flywheel of mass 15 kg and radius 20 cm is wound by a rope that carries a weight A of mass 5 kg at its free end as illustra

How are the refrigerants classified, How are the refrigerants classified? D...

How are the refrigerants classified? Describe the desirable property of a good refrigerant. Explain in brief the thermodynamics, safe and physical working property of an ideal r

Explain the principle of screw conveyer, Explain the Principle of screw con...

Explain the Principle of screw conveyer When materials are feed into the fixed chutes, due to action of gravity of materials and the friction force between material and chute t

Physics, difference brtween parallel and unlike parallel forces

difference brtween parallel and unlike parallel forces

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd