Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Refrigeration, In a steam jet refrigeration system, the ejector extracts 3....

In a steam jet refrigeration system, the ejector extracts 3.3 m3/s of saturated water vapor at a temperature of 7.2 °C from the flash chamber. The return water from the cooling coi

Calculate diameter of runner, A radically inward flow turbine working under...

A radically inward flow turbine working under a head of 10 m and running at 250 rpm develops 185 KW at the turbine shaft. At inlet tip of the runner vane, the peripheral velocity o

Maximum elastic torque - rectangular section, Maximum elastic torque: ...

Maximum elastic torque: A rectangular section torsion member had dimension of 100mm by 200 mm and is built of a steel for which the shear yield point is τ y = 100 MPa. Find o

Spot welding of different metals-stainless steel, Spot welding of different...

Spot welding of different metals-Stainless steel Stainless steel is having lower thermal conductivity compared to mild steel. Therefore, it requires less heat input. But, stain

Calculate the magnitude and position of the balance mass, The four masses m...

The four masses m1, m2, m3 and m4 having their radii of rotation as 200mm, 250mm, 150mm, 250mm and 300mm are 200kg, 300kg,240kg and 260kg in magnitude respectively. The angles betw

What are the elements of theory of vibrations, What are the Elements of The...

What are the Elements of Theory of Vibrations All bodies possessing mass and elasticity can vibrate or undergo vibratory motion. Let us understand a few basic definitions used

Comparison of disc and drum type brakes drum brake , Comparison of Disc and...

Comparison of Disc and Drum type Brakes Drum Brake Disc Brake Drum brakes have cooling problem because the friction occurs at internal surfaces,

Calculate the length of plastic deformation, Calculate the length of plasti...

Calculate the length of plastic deformation: Calculate the length of plastic deformation along 45o in case the applied stress is 63.25% of yield stress in the plate of abov

Thermal reservoir - thermodynamics, Thermal Reservoir - Thermodynamics: ...

Thermal Reservoir - Thermodynamics: Thermal Reservoir. A thermal reservoir is the part of environment that can exchange heat energy with system. It has adequately large capa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd