Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Resistance spot welding, Resistance Spot Welding In this process, a spo...

Resistance Spot Welding In this process, a spot of weld is made between overlapping sheets by means of two cylindrical copper alloy electrodes, one on top and the other at the

Line of action of force, Line of action of force: Sol.: The directio...

Line of action of force: Sol.: The direction of force along the straight line through its point of application, in which force tends to move body to which it is applied. Thi

Flange facing and surface finish, Q. Flange Facing and Surface Finish? ...

Q. Flange Facing and Surface Finish? Raised face flange facings are preferred. Flat face flanges to be used only when mating with like equipment (fabricated from brittle mat

Airport drainage, Airport Drainage: Rainwater should be quickly taken...

Airport Drainage: Rainwater should be quickly taken away from the runway, taxiway and apron areas. For drainage of runway and taxiway, a cross-slope of 1.5 per cent on either

Gmaw power source, GMAW POWER SOURCE A power source wit h a flat charac...

GMAW POWER SOURCE A power source wit h a flat characteristics is almost universally used for GMAW process as it provides self adjustment and stabilisation of the arc. Also it m

Solids of mechanics, Derive the equation for pure bonding of beam (simply)

Derive the equation for pure bonding of beam (simply)

Stockholm conference, define environment and explain stockholm conference

define environment and explain stockholm conference

#title.scale, actual division 2km is shown as 1 cm in a map.construct a cle...

actual division 2km is shown as 1 cm in a map.construct a clean scale to measure km which can travel a distance upto 30 km.Show measurement of 18 km in the scale

Electrodes- inconel electrodes, Inconel Electrodes These electrodes are u...

Inconel Electrodes These electrodes are used in the industries, like petrochemical, fertiliser, etc. The weld composition contain small percentage of alloying elements like V, Mo

What is squeeze time, Q. What is Squeeze time? It is the time between t...

Q. What is Squeeze time? It is the time between the initial application of the electrode pressure on the work and the initial application of current to make the weld. During th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd