Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Dynamic Force Analysis, How to determine Forces and Torque of slider crank ...

How to determine Forces and Torque of slider crank mechanism?

Reaction on the beam - mechanics, Reaction on the beam - mechanics: D...

Reaction on the beam - mechanics: Determine algebraically the reaction on the beam loaded as shown in the figure given below. Neglect the thickness and mass of beam.

Spot welding of different metals-low carbon steel, Spot welding of differen...

Spot welding of different metals-Low carbon steel Normally, mild steel can be spot welded from the thinnest gauges to a maximum of two pieces of 12 mm thickness. The restrictio

Mechanism of laser welding, MECHANISM OF LASER WELDING   Laser weldi...

MECHANISM OF LASER WELDING   Laser welding of metals is performed with beams focused to irradiate levels in the range of 106 to 107 W / cm 2 . At such power densities, melti

Usage of special tool, USAGE OF SPECIAL TOOL: The common tools used in rep...

USAGE OF SPECIAL TOOL: The common tools used in repair and maintenance of motorcycles were introduced to you in previous sections. Now, we shall learn about some special tools and

Illustrate the general shear failure in bearing capacity, Illustrate the ge...

Illustrate the general shear failure in bearing capacity. General Shear Failure: In this case of failure, contiguous failure surfaces develop between the edges of the footin

Processes , example on operation sheet?

example on operation sheet?

Determine the convection coefficient associated with airflow, An experiment...

An experiment to determine the convection coefficient associated with airflow over the surface of a thick stainless steel casting involves insertion of thermocouples in the casting

Computer algorithm for on-line scheduling , Computer Algorithm For On-Line ...

Computer Algorithm For On-Line Scheduling For Automated Manufacturing Systems  Introduction Now days  market  is  characterized  via  the  production  of  minute  batch

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd