Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Corrosion control in oil-treating equipment, Q. Corrosion Control in Oil-Tr...

Q. Corrosion Control in Oil-Treating Equipment? Bitumen provides adequate internal protection for Inlet Slug Catcher, FWKO and Treater. Due to high operating temperature, inter

Aggregate production planning, Aggregate Production Planning: This uni...

Aggregate Production Planning: This unit provides the definition and physical significance of aggregate production planning. Further, this is illustrated that how the internal

Determine the temperature for the engines, (a) Describe heat engine. How is...

(a) Describe heat engine. How is this engine characterized? (b) Describe Perpetual motion machines of first kind and second kind, i.e. PMM1 and PMM2. Are such machines possible

Evaluate boiler efficiency, The following data were obtained in a boiler tr...

The following data were obtained in a boiler trail: Mass and temperature of feed water: 680 kg/hr and 20 0 C, Steam temperature and its pressure : 15bar and 300 0 C, Coal used

D.c circuits, formulae for finding gross torque developed by the armeture

formulae for finding gross torque developed by the armeture

Engineering Mechanics, What are the practical applications of solid cylinde...

What are the practical applications of solid cylinder or shaft under cyclic axial loading

What is fusion bonding, Q. What is Fusion Bonding? Fusion Bonding shall...

Q. What is Fusion Bonding? Fusion Bonding shall refer to the fusion bond coating process which utilizes heat to melt adhere the coating material to the metal surface. Fusion Bo

Cylinder block-basic components of engine , Cylinder Block: This serves a...

Cylinder Block: This serves as an enclosure to the cylinder. The cylinder is an integral part of cylinder block in 100 cc motorcycle. Figure : Cylinder Block

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd