Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Introduction to tools and equipment , INTRODUCTION: At any point of time, ...

INTRODUCTION: At any point of time, it may be required to disassemble the whole or any part of motorcycle. Whenever a part of motorcycle malfunctions or is damaged then it may be

AOC, The objective of the project is to protect damage of the DC motors. If...

The objective of the project is to protect damage of the DC motors. If the motor is not working it will be shown with red light, if working normally then green and if working at a

Location of safe areas, All equipment that is critical to the plant's safet...

All equipment that is critical to the plant's safety support; should always be located in a Safe Area (e.g. fire pumps, instrument/electrical equipment and an Emergency Assembly Ar

Angle of friction, Angle of friction:   It can be defined as t...

Angle of friction:   It can be defined as the angle made by resultant of normal reaction ( R ) and limiting force of friction ( F ) with normal reaction ( R ). Let,

Determine the axial extension along a load, Determine the axial extension a...

Determine the axial extension along a load: An open coiled helical spring is created having 10 turns of a mean radius of 60 mm. The wire diameter is 10 mm and coils make an an

Explain about active fire protection, Q. Explain about Active Fire Protecti...

Q. Explain about Active Fire Protection? Active Fire Protection - A fire fighting system that is normally dormant and is activated automatically upon detection of a fire hazard

Determine strain using wheatstone bridge, a) Can you explain Discuss LVDI i...

a) Can you explain Discuss LVDI in detail. b) Derive the expression for calculating strain using wheatstone bridge. c) Distinguish between analog and digital transducers.

Merchant force circle diagram, (a) Draw neatly and accurately the Merchant ...

(a) Draw neatly and accurately the Merchant force circle diagram. Mention clearly the forces involved, the constructional steps and the assumptions made [do not derive the forces]

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd