Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Sweep representations of two-dimensional area, Sweep Representations  T...

Sweep Representations  The simplest form of sweep is that produced by sweeping a two-dimensional area along an axis perpendicular to its plane. This form of sweep is most usefu

Determine the relative error, a) Determine the relative error if 2/3 is app...

a) Determine the relative error if 2/3 is approximate to 0.667. b) √29 = 5.385 and √Π= 3.317 Correct to 4 significant figures. Determine the relative errors in their sum and dif

Illustrate the future trends in automobile, Short answer Type. a) Writ...

Short answer Type. a) Write the difference Between Dry clutch and Wet ? b) What is difference Between Chasis and Frame? c) Illustrate the Future trends in Automobile

Equilibrium diagram, what do understand by the term equilibrium diagram

what do understand by the term equilibrium diagram

Thermodynamics, how to prove that heat and work is path function?

how to prove that heat and work is path function?

Illustrate the design process and application of cad, Describe the use of c...

Describe the use of computer in : (i) Design (ii) Manufacturing Illustrate the design process and application of CAD.

Make evaluation for the engine efficiency, (a) Differentiate between carnot...

(a) Differentiate between carnot Heat pump and carnot Heat engine. What is the basic cycle for a carnot Heat pump ? Explain it. (b) A reversible heat engine delivers 0.6 K at po

Classification of force - mechanics, Classification of force: Single f...

Classification of force: Single force is of two types that is, Tensile and compressive. Generally in a body several forces are acting. When a number of forces of different mag

Find the magnitude of force, Find the magnitude of force: Q: The two ...

Find the magnitude of force: Q: The two parallel forces are acting at point A and B respectively is equivalent to force of  100 N acting downwards at point C and coupl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd