Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Equipment for resistance welding-protection, EQUIPMENT FOR RESISTANCE WELDI...

EQUIPMENT FOR RESISTANCE WELDING-Protection A circuit breaker can be provided (this equipment can be rated for interrupted capacity) which will cater to a number of resistance

Applications of seam welding, Applications of seam welding Lap seam wel...

Applications of seam welding Lap seam welding is used for the manufacture of cans, buckets and water tanks and for welding thin walled large diameter pipes. Mash seam welding

Test the strength of binders, Strength tests : These tests are carried out ...

Strength tests : These tests are carried out to check the holding powers of various binders used in green moulding sand, dry moulding sand and core sand. These tests are performed

Cantilever beam - shear force diagrams, Cantilever beam - shear force diagr...

Cantilever beam - shear force diagrams: Illustrate the shear force & bending moment diagrams for the cantilever beam illustrated in Figure. Figure Solution

Construction of boiler, CONSTRUCTIO N FEATURES : Comprises of a water ...

CONSTRUCTIO N FEATURES : Comprises of a water drum which is connected to two headers at the front and back ends. The headers are connected by large number of water tubes which

Fuel and steam generator, Boiler efficiency and heat losses, heat Balence s...

Boiler efficiency and heat losses, heat Balence sheet, boiler draught, high pressure boiler

Determine the steady state amplitude of vibration, 1. (a) Sketch frequency-...

1. (a) Sketch frequency-response curves for a damped single degree of freedom system subjected to a harmonic excitation under three different damping ratios. The system has a natur

Hinged support, Hinged Support: Hinged (Pin) Support: At hinged end,...

Hinged Support: Hinged (Pin) Support: At hinged end, beam cannot move in any direction support will not develop any resisting moment, but it can develop reaction in any of t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd