Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Welding, what is blow hole defect ?

what is blow hole defect ?

Define the gear hobbing, Define the Gear Hobbing This is the most produ...

Define the Gear Hobbing This is the most productive of all the gear production processes. However, it can only be used for producing spur gears and worn gears. It cannot be use

Determine standard for the specific standard technical areas, Standard for ...

Standard for the specific standard technical areas These norms are based on previously described models. Typical categories of these norms are: (a)  drafting, which describe

Determine forces in members of cantilever truss, Determine  forces in memb...

Determine  forces in members of cantilever truss: Determine  forces  in  members   B C   and  BD   of   cantilever truss  shown  in  the figure in the figure given below.

Define the term linear non-uniform soil pressure, Define the term linear no...

Define the term linear non-uniform soil pressure. See that the eccentric load on a column as in demonstrated figure also produces a similar effect. The linear non-uniform soil

Mechanics, definition of open and cross belt drive

definition of open and cross belt drive

What do you mean by line designation tables, Q. What do you mean by Line De...

Q. What do you mean by Line Designation Tables? Development of the Line Designation Tables (LDT's) is carried out in conjunction with the evolution of the P&ID's. Engineering

Evaluate the power output of turbine, Evaluate the power output of turbine:...

Evaluate the power output of turbine: Q: A turbine in steam power plant operating under steady state conditions receives the superheated steam at 3MPa and 350ºC at the rate o

Engfine, how we made parts of engine

how we made parts of engine

Control, hey i really need someone to help doing my control course work asa...

hey i really need someone to help doing my control course work asap cuse it is due sunday it is about Control of water level in a nonlinear ‘V’ shaped tank

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd