Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

FEA, Consider the rocket on a test stand as described in Chapter 3 of the l...

Consider the rocket on a test stand as described in Chapter 3 of the lecture notes. The nose of the rocket is fixed. The rocket is of length L, constant EA and constant m, mass per

Find out dimension of the cross section of the beam, Q.  A wooden beam of t...

Q.  A wooden beam of the rectangular cross section is subjected to bending moment of 5KNm. If the depth of section is to be double the breadth and stress in wood is not to exceed 6

Biofluids mechanics, in fontan circulation that is represented as a circuit...

in fontan circulation that is represented as a circuit

Balancing of several masses rotating in different planes, The crank shaft o...

The crank shaft of a high speed pump has a parallel shaft of 2.5 cm diameter and 48 cm in length. It carries three eccentrics each of 6 cm in diameter and uniform thickness of 1.8

Mockup of tube to tubesheet, what are the tests to carried out after mockup...

what are the tests to carried out after mockup preparation

Stress analysis requirements, Q. Stress analysis requirements? All othe...

Q. Stress analysis requirements? All other lines requiring review by the stress group are to be checked for adequate support, stability, excessive movement, etc. Where hand ca

Thermodynamic, what is the difference between intrinsic and extrinsic proce...

what is the difference between intrinsic and extrinsic process?

What is passive fire protection, Q. What is Passive Fire Protection? Pa...

Q. What is Passive Fire Protection? Passive fire protection is defined as any fire protection system that, by its nature, plays an inactive role in protecting personnel and pro

Themodynamic, vacuum gauge indicates that the pressure of air in a closed c...

vacuum gauge indicates that the pressure of air in a closed chamber is 0.2bar(vacuum).The pressure of the surrounding atmosphere is equilent to a 750-mm column of mercury.The densi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd