Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Why is stress relieving in post-weld treatment necesaary, In case of welded...

In case of welded vessels why is stress relieving in the form of post-weld treatment necessary? When a metal is welded together the point at which two surfaces are joined are s

Illustrate about the strap footing, Illustrate about the strap footing? ...

Illustrate about the strap footing? In given demonstrates figure the exterior footing placed eccentrically under the exterior column so that property line limitations are not v

Loads analysis, Complete the following problem from the text by Megson.  No...

Complete the following problem from the text by Megson.  Note that since the answers are given, it is essential that you show and justify all work to receive full credit.  Required

What is passive fire protection, Q. What is Passive Fire Protection? Pa...

Q. What is Passive Fire Protection? Passive fire protection is defined as any fire protection system that, by its nature, plays an inactive role in protecting personnel and pro

High temperature materials in boilers, Q. High temperature materials in Boi...

Q. High temperature materials in Boilers? A thin refractory layer between the shield and boiler tube is recommended in areas subject to moderate temperatures and levels of corr

What is the basic working principle of capacitive transducer, Answer any fi...

Answer any five questions. a) Describe calibration and state its types. b) Which are the kinds of test signals? c) What is the basic working principle of piezo-electric tr

Manufacturing methods of ceramics, Manufacturing Methods Of Ceramics Th...

Manufacturing Methods Of Ceramics The ceramics manufacturing consists in shaping along with or without pressure and firing to consolidate. The simplest and cheapest process of

Assignment help, i need help in my assignment it''s due few days

i need help in my assignment it''s due few days

Loop transfer function, Obtain the closed loop transfer function of the sys...

Obtain the closed loop transfer function of the system shown:

Discover the maximum safe air pressure, Discover the maximum safe air press...

Discover the maximum safe air pressure: A cylindrical compressed air drum is equal to 2 m in diameter along plates 12.5 mm thick. The efficiencies of the longitudinal (η l ) a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd