Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Ionization of inert gases, inert gas is ionizing in tig and mig,plasma arc ...

inert gas is ionizing in tig and mig,plasma arc welding processe.but it is impossible to react with inert gas

Determine the maximum bending stresses, Determine the maximum bending stres...

Determine the maximum bending stresses: A rectangular beam of breadth 100 mm & depth 200 mm is simply supported over a span of 4 m. The beam is loaded with a uniformly distrib

MRP 1, Advantages and disadvantages

Advantages and disadvantages

Erosion-corrosion in sand slurry line, Q. Erosion-Corrosion In Sand Slurry ...

Q. Erosion-Corrosion In Sand Slurry Line? All sands are collected in the Inlet Slug Catcher and routed to the Desand Tank for separation. Sand Slurry lines are subject to erosi

Clutch cable routing- gear complaints, Clutch cable routing :Ensure that t...

Clutch cable routing :Ensure that the cable is routed as per standard routing, through the brackets provided.

#title.scale, actual division 2km is shown as 1 cm in a map.construct a cle...

actual division 2km is shown as 1 cm in a map.construct a clean scale to measure km which can travel a distance upto 30 km.Show measurement of 18 km in the scale

WELDING, WHAT IS DIFFERENCE BETWEEN POROSITY AND BLOW HOLE

WHAT IS DIFFERENCE BETWEEN POROSITY AND BLOW HOLE

Explain the use of bare electrode, Q. Explain the use of bare electrode? ...

Q. Explain the use of bare electrode? This type of electrode is also known as plain electrode. No flux covers on this electrode. These types of electrodes are used for D.C. sup

Control of the guide vanes, Control of the guide vanes shall be by means of...

Control of the guide vanes shall be by means of an external linkage connected to the internal control ring Steam Generator piping. Inlet guide vanes shall be furnished with the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd