Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

Battery is not charging motorcycle problem, If Battery is Not Charging ...

If Battery is Not Charging Causes of Problem Remedy Electrolyte specific gravity NG Charging not done fully

Open and closed thermodynamic system, Steam flowing at a rate of 3200 lbm/h...

Steam flowing at a rate of 3200 lbm/hr enters an adiabatic nozzle. The initial condition of steam is: P1 = 250 psi, v1=620 ft/min, v1 = 2.4 ft3/lbm and u1 = 1125.5 Btu/lbm. The ste

Injection molding, finishing operation of telephone outer body after inject...

finishing operation of telephone outer body after injection molding

Cam profile, sketch and discuss the uses and application of the following t...

sketch and discuss the uses and application of the following types of cam follower;knife edge,roller and flat ended.

Evaluate the reaction at support, Evaluate the reaction at support: Q...

Evaluate the reaction at support: Q: Find out the reaction at support as shown in figure given below     First draw FBD of the system as shown in the given figur

Calculate the support reactions of beam, Calculate the support reactions of...

Calculate the support reactions of beam: Q: Bending moment diagram (BMD) of the simple supported beam can be given as shown in figure given below. Calculate the support reac

Explain different types of frames, (a) Explain different types of frames. C...

(a) Explain different types of frames. Compare their merits and demerits. Diagram and illustrate a frameless construction. (b) Illustration briefly the constructional features o

What is, what is soundness of casting.

what is soundness of casting.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd