Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

What do you understand by straight line mechanism, What do you understand b...

What do you understand by straight line mechanism ? Describe with a neat sketch the working and construction of any three types of straight line mechanism. Derive a mathematical

Design the drainage area, Q. Design the drainage area? Areas beneath eq...

Q. Design the drainage area? Areas beneath equipment or vessels subject to spills or leaks shall have slope drainage area. Every skid shall be provided with floor drains. S

Principle of energy conversion, Q.   Describe the principle of energy conve...

Q.   Describe the principle of energy conversion. Show that the reaction of coupling magnetic field on the electrical or mechanical system is essential for the electro - mechanical

Level of safety organization, Level of Safety Organization This level ...

Level of Safety Organization This level comprises representatives of safety departments working at shop floor level or along with workers. The personnel will in fact implement

Mechanical, mostly what aspects trouble mechanical engineers?

mostly what aspects trouble mechanical engineers?

Typical joint designs used in electron beam welding, TYPICAL JOINT DESIGNS ...

TYPICAL JOINT DESIGNS THAT ARE USED IN ELECTRON BEAM WELDING Butt joint : Butt joint is the preferred joint as it involves only a small amount of machining prior to wel

Lifting machines, Lifting machines: Basic definitions of the lifting m...

Lifting machines: Basic definitions of the lifting machines and some lifting machines have been described. For each of these machines, derivation of the formulae for mechanica

Composite materials, Composite Materials While two various materials w...

Composite Materials While two various materials which neither react chemically nor dissolve in every other are combined together so they form a composite materials. Individual

Forces working on dam, Forces working on dam: Let a dam retaining wate...

Forces working on dam: Let a dam retaining water as illustrated in Figure (a). What are the forces working on it? Solution The forces working on dam are as follows:

Strength of material, What us the duff between direct stress and bending s...

What us the duff between direct stress and bending stress

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd