Problem type-aspects of scheduling , Mechanical Engineering

Assignment Help:

Problem Type

Aforementioned illustration relates to the class of non-cyclic scheduling problems characterized via the subsequent features.

(a) The Flexible Manufacturing System consists of M stations (workplaces, machines) all of that can process at mainly one operation at a time,

(b) The inventory that may change at some time contains N jobs along with termed earliest possible beginning times and due dates,

(c) A job is a sequence of operations along with precedence constraints that is most operations can only be begun if one or some preceding operations have been finished.

                            Table no.2 (b): Due Dates Distributions for Situation E-H

Situation A : Case 2, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            5

 

480                            5

 

720                            5

 

960                            35

 

1200                          50

 

Average Throughput Time: 1008 min

 

Demanded/achieved flow factor: 1.20

 

Situation A : Case 2, 50% late jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

 

240                            5

 

480                            10

 

720                            35

 

960                            27

 

1200                          23

 

Average Throughput Time: 847 min

 

Demanded/achieved flow factor: 1.00

 

Situation A : Case 2, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            19

 

480                            25

 

720                            31

 

960                            15

 

1200                          10

 

Average Throughput Time: 653 min

 

Demanded/achieved flow factor: 0.78

 

Situation A : Case 2, 85% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

 

240                            30

 

480                            45

 

720                            15

 

960                            5

 

1200                          5

 

Average Throughput Time: 504 min

 

Demanded/achieved flow factor: 0.60

 

(d) For all operation, this is identify that on which stations (one or more) this can be represented and how long this acquires (containing transportation times); these durations  are  supposed  to  be  independent of  the  scheduling deterministic and policy  ,

(e) Operations which have been begun but cannot be interrupted (non-preemptive scheduling), and

(f) The idle times among the operations are not limited, neither are the buffers opposite the stations or at the output.

Consequently the major restriction is the capability of the stations. Another limitation is assumed to be of secondary significance. They may be shown via the earliest possible starting times of the operations or contained in the operation times, for instants: via adding a constant average transportation delay. Obviously, the transportation system can be integrated via adding transport operations to the work plans and explaining one or more resources that provide transport and have to be assigned as well. The only limit implied through the  assumptions made  is  that  the  resource  uses  times  are  independent of  the processing sequences.

In the test difficulty, the options on which station an operation is presented are only amongst identical stations.  Hence,  for  each  operation  there  is  merely  one  value  for  its (nominal)  net  operation  time.  However, this assumption is not essential for the algorithms discussed afterward.


Related Discussions:- Problem type-aspects of scheduling

What are the disadvantages of not washing a motorcycle?, (a) What are the d...

(a) What are the disadvantages of not washing a motorcycle before servicing it? (b) List the parts on which water should not fall directly. (c) Write down the steps for washing and

Explain how the rankine cycle efficiency is improved, Illustrate how the Ra...

Illustrate how the Rankine cycle efficiency is improved by the following : a. Lowering the condenser pressure. b. Increasing the pressure of steam. c. Superheating the ste

Illustrates the concept of bearing capacity of soil, Illustrates the concep...

Illustrates the concept of bearing capacity of soil? The concept of bearing capacity of soil is the very essence of design and analysis of shallow foundations. In order to inve

Deadlock states, Deadlock States Deadlock is a detrimental phenomenon i...

Deadlock States Deadlock is a detrimental phenomenon in the shop floor; here part flow is inhibited because of unsuitable scheduling decisions made via the computer controller.

Explain arc-welding processes, Arc-Welding Processes Arc-welding incl...

Arc-Welding Processes Arc-welding includes those welding processes wherein heat required for welding is derived from an arc powered by electrical energy, may be AC of DC as s

What is product definition data interface, Product Definition Data Interfa...

Product Definition Data Interface (PDDI) IGES provided a very practical first solution for CAD data exchange, complete with an exchange file format. It was remarkable in the sp

Belt Drives, In conveyor belts calculations, if it is required of me to cal...

In conveyor belts calculations, if it is required of me to calculate "The Power transmitted by the drive,at the specific efficiency" Which power are they reffering to?

Torsion equation for solid circular shaft, Prove the torsion equation T/J=τ...

Prove the torsion equation T/J=τ/R=C. θ/L for the solid circular shaft. State the various assumptions used on above said equation.

Find out the reactions at point, Find out the reactions at point: A be...

Find out the reactions at point: A beam AB is hinged at A and is supported at C. It is loaded as revealed in Figure. Find out the reactions at A and C. Solution L

Working of steam engine , Working of stream engine: The high pressure ...

Working of stream engine: The high pressure steam from boiler is supplied to the steam chest. The high pressure steam enters cylinder through inlet port and exerts pressure on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd