a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

MBA 2ND SEM, Q3. What do you understand by “line balancing”? What happens i...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Explain elements of the integrated model of motivation, Analyze the four el...

Analyze the four elements of the integrated model of motivation to determine which element is the most essential to get right when motivating employees. Explain your rationale. •As

Explain what should they do in the internal organization, Disney entered Eu...

Disney entered Europe with several incorrect assumptions and poor research. Identify the problems that arose and how Disney should adjust for the immediate situation and what shoul

Define the order quantity and expected profits, suppose the manufacturer ha...

suppose the manufacturer has an inflated demand forecast as follows: Quantity Probability 2,200 5% 2,300 6% 2,400 10% 2,500 17% 2,600 30% 2,700 17% 2,800 12% 2,900 3% (a) Suppose t

Explain supply chain risk management tools, Of the barriers to supplier dev...

Of the barriers to supplier development mentioned in this chapter, which ones, in your opinion, are the most difficult to overcome? 2. Describe the major sources of supply base ris

Calculate seasonal indices using all of the data, Attendance at Los Angeles...

Attendance at Los Angeles's newest Disneylike attraction, Vacation World, has been as follows- Quarter Guest in Thousands Quarter Guest in Thousands Winter 07 73 Summer 08 12

Intermittent and continuous operations, Explain intermittent and continuous...

Explain intermittent and continuous operations. Under what type of situation it would be used in automobile industry?

Explain procurement management, Which of the nine knowledge areas defined i...

Which of the nine knowledge areas defined in the Project Management Body of Knowledge includes the activities of generating, collecting, distributing, storing, retrieving and dispo

Explain production system that consists of a single station, Consider a pro...

Consider a production system that consists of a single station with a production rate of 1 part per minute and a process variability given by Ce=1.

Explain what types of risks are inherent in a project, 1. What do each of t...

1. What do each of the letters in the SMART acronym stand for? 2. In your own words, describe what each piece of the SMART acronym means? 3. Why is the SMART acronym an impor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd