problem, Operation Management

Assignment Help:
a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

Explain market presence to multiple international venues, Before you answer...

Before you answer this discussion question do a little Internet research. Identify and discuss a company that has had great success in expanding its market presence to multiple int

Define the upper and lower control limits, The overall average on a process...

The overall average on a process you are attempting to monitor is 50 units. the process standard deviation is 1.72. Determine the upper and lower control limits for a mean chart, i

Explain a set of circumstances consider disciplinary action, Describe a set...

Describe a set of circumstances under which you might legitimately consider disciplinary action for a chronic complainer.

Explain the united states constitution, The United States Constitution: Ans...

The United States Constitution: Answer is the oldest written constitution in force in a major nation created the four branches of government established the common law created the

Explain what are the hr maturity levels, Provide a broad description of the...

Provide a broad description of the value of understanding the strategic challenges and opportunities facing the business organization today What are the elements for Developing

Explain what kind of data would be considered a nod, What kind of data woul...

What kind of data would be considered a NOD?/ REFERENCE WHERE THE INFO CAME FROM

Flow process chart - process design, 1. Examine the flow process chart in t...

1. Examine the flow process chart in the figure and try to develop an improved method for the future, taking advantage of the technologies becoming available. Answer: There are

Resources planning and execution., Explain why it is important to carry out...

Explain why it is important to carry out a rough-cut capacity planning check on critical resources before proceeding with the development of the final master production schedule

Explain supply chain risk management tools, Of the barriers to supplier dev...

Of the barriers to supplier development mentioned in this chapter, which ones, in your opinion, are the most difficult to overcome? 2. Describe the major sources of supply base ris

Compute the breakeven volume, The following table shows the critical factor...

The following table shows the critical factors in a company's decision on choosing a new piece of equipment. Calculate the breakeven volume and utilization for each option and then

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd