problem, Operation Management

Assignment Help:
a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below
year running cost
1 200
2 500
3 800
4 1200
5 1800
6 2500
7 3200
8 4000
when should machine be replaced?


Related Discussions:- problem

Explain the forecasted demand for fudge, The forecasted demand for fudge fo...

The forecasted demand for fudge for the next four months is 140, 160, 90 and 70 pounds. A) What is the recommended production rate if a level strategy is adopted with no back order

Describe three issues that can deter high performance, Discuss three issues...

Discuss three issues that can deter high performance when outsourcing a project. Discuss ways that these issues can be reduced or eliminated ahead of time or during the project dur

MBA-2, What do you understand by line balancing what happens if balance doe...

What do you understand by line balancing what happens if balance doesn''t exist

Explain behavior and performance with the objectives, The effectiveness of ...

The effectiveness of any compensation system to attract, retain and align employee behavior and performance with the objectives of the enterprise is dependent upon management credi

Comparison between method and work measurement, Comparison between method a...

Comparison between method and work measurement: Method  study  is the  principle   technique  for reducing  the work  involved  primarily by eliminating unnecessary  movement

Line Balancing, #What do you understand by “line balancing”? What happens i...

#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Explain computer criminals become more innovative, Identify potential ethic...

Identify potential ethical challenges that may be faced by security professionals as technology advances, applications become more mobile, and computer criminals become more innova

Explain that they receive the training they need, The Chief Projects Office...

The Chief Projects Officer (CPO) is responsible for the individuals working on a project in all of the following way EXCEPT: A. That they perform project activities according to

What role do alter agents play in the execution of a road, What things shou...

What things should be taken into consideration in the creation of a roadmap for a strategic plan? What are examples of external and internal change agents? What role do change agen

Process flow and layouts, process flow and layout flows are at the core of ...

process flow and layout flows are at the core of lean manufacturing, do you agree or disagree?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd