Q. Principle of airlifting for cleaning pile bores?

Airlifting is generally carried out before concreting to remove debris and clean the base of pile bores. It basically acts as an airlift pump by using compressed air. The setup of a typical airlifting operation is as follows: a hollow tube is placed centrally inside pile bore and a side tube is connected to the end of tube near pile bottom for the passage of compressed air inside the tube. Upper end of the tube is linked to a discharge tank for the circulation of pumped fluid from pile base.

Efficiency of airlifting operation is dependent on the performance of air compressor. At the time of airlifting, compressed air is piped down the tube and it returns up to discharge tank carrying it with the fluid. It functions by imparting energy to fluid and forces the fluid to move vertically upwards. Injected air mixes with the fluid, which leads to the formation of lower unit weight of combined mixture when compared with surrounding fluid. This hydrostatic pressure forces the air/fluid mixture up to the discharge tanks.


Related Discussions:- Principle of airlifting for cleaning pile bores

State an expression for zero air-void line, State an expression for 'zero a...

State an expression for 'zero air-void line' and illustrate the line for a specific gravity of 2.65. What are the various factors that affect the compaction of soil in the field

Light and rapid rail transit, Light Rail Transit (LRT) Light Rail Tra...

Light Rail Transit (LRT) Light Rail Transit is also known by the name train. LRT can be run on the surface if road space is available (as in Kolkata) or as elevated, with pil

Explain flow measurement with weirs, Explain Flow Measurement with Weirs ...

Explain Flow Measurement with Weirs Fixed plates positioned vertically in an open channel over which flow is directed through an opening. The opening linear distance is termed

Force system, show the diagram for non coplanar non concurrent force system...

show the diagram for non coplanar non concurrent force system

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

What do you mean by base fixity, Q. What do you mean by Base fixity? B...

Q. What do you mean by Base fixity? Base fixity When structures such as portal frames are associated to the base foundation, engineers have to determine the degree of fix

Calculate the amount put into saving account, Calculate the Amount put into...

Calculate the Amount put into Saving Account If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is m

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd