Preparing the research design, Operation Management

Assignment Help:

Preparing the Research Design:

Research design is the conceptual structure within which research should be conducted. A research design specifies the methods and procedure for conducting a particular study. The researcher should specify the approach he intends to use with respect to the proposed study. The function of research design is to provide for the collection of relevant evidence with minimal expenditure of effort time and money. Research design can be grouped into three categories exploratory research descriptive research and causal research.

a. Exploratory Research: An exploratory research focuses on the discovery of ideas and is generally based on secondary data. It is preliminary investigation which does not have a rigid design.

b. Descriptive Research: A descriptive study is undertaken when the researcher wants to know the characteristics of certain groups such as age sex educational level income occupation etc. In contract to exploratory studies descriptive studies are well structured.

c. Casual research: A casual research is undertaken when the researcher is interested in knowing the cause and effect relationship between two or more variables. Such studies are based on reasoning along well tested lines .

The preparation of the research design appropriate for a particular research problem involves usually the consideration of the followings.

a.The means of obtaining the information.

b. The availability and skills of the researcher and his staff ( if any) :

c. Explanation of the way in which selected means of obtaining information will be organized and the reasoning leading to the selection.

d.The time available for research and

e.The cost factors relating to research i e, the finance available for the purpose.


Related Discussions:- Preparing the research design

What are some instances that would explain strategic groups, What are some ...

What are some examples that would explain strategic groups?

Forward scheduling - scheduling techniques, Forward Scheduling - Scheduling...

Forward Scheduling - Scheduling Techniques Forward scheduling means assigning customers orders or job to various work centers based on the as early as possible approach. Thus

Explain the precedence relationships and the estimated times, A project con...

A project consists of activities A, B, C, D, E, F, and G. The precedence relationships and the estimated times to complete each activity are given below: Activity Preceding Activit

Share the data and understanding of the data, •Using the Internet, research...

•Using the Internet, research statistics using PollingReport.com. •Select a topic from either the "In the News" section or the "Issues" section. •Study the data that the Website pr

Define activity a can be finished and not delay any activity, Using the dat...

Using the data in Table 13-4, determine the latest time activity A can be finished and not delay any activity? Table 13-4 The following represents a project with known activity tim

Gaining Trust with Culture Disparties, Ask quFor this assignment, you will ...

Ask quFor this assignment, you will apply critical thinking to what you have learned up to this point in this course regarding the successes and failures of the U.S. health care sy

Internal business perspective - performance and productivity, Internal Busi...

Internal Business Perspective - Performance Measures Although customer based measures are important, they must be translated into internal performance measures that can be ach

Describe how this affect the subsequent bid, Lamda Computer Products compet...

Lamda Computer Products competed for and won a contract to produce tow prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits

Point rating method, Point  Rating Method In  selecting  a site  of l...

Point  Rating Method In  selecting  a site  of location companies  have several  objectives, but  not  all are  of equal  importance. The relative weight a company assigns to

Explain what is the expected growth rate, Sidman Products' common stock cur...

Sidman Products' common stock currently sells for $51 a share. The firm is expected to earn $6.10 per share this year and to pay a year-end dividend of $2.40, and it finances only

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd