Precast concrete jacking pipes, Civil Engineering

Assignment Help:

Question

While precast concrete jacking pipes, from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons?


Answer


Grout holes are there in precast jacking pipes for following reasons-

(i) They serve as locations for inoculation of bentonite or other lubricant. Lubricant is used for together granular top soils and cohesive soils to trim down frictional resistance. For cohesive soils, soils cannot get onto pipes by presence of lubricant and the shearing plane lies within lubricant. On other hand, for granular soils, lubricant mixes with soils with a considerably reduced friction. With use of lubricant, longer pipe lengths are able to be jacked without use of intermediate jacking station.

(ii) They give inlet locations for subsequent grouting works after completion of pipe jacking to fill totally the void space b/w pipes and surrounding soils.

(iii)They are used as lifting holes while placing precast jacking pipes into rails within jacking pits.

 

 


Related Discussions:- Precast concrete jacking pipes

Distinguish among active and passive earth pressure, Distinguish among  'ac...

Distinguish among  'active' and 'passive' earth pressure. Describe clearly Rebhann's graphical construction method to evaluate the earth pressure on a retaining wall. What are t

Plants aeration period, Plants aeration period: Problem: What i...

Plants aeration period: Problem: What is the plant's aeration period? Solution The plant's aeration period is the number of hours that the wastewater is aerated

Scale., how many scale are there and what are they use

how many scale are there and what are they use

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

What do you mean by manhole loss, Q. What do you mean by Manhole loss? ...

Q. What do you mean by Manhole loss? Manholes are provided in locations where there are changes in direction, size and gradient of gravity pipelines. Generally practice for str

Calculate the amount of concrete - construction management, An electrical c...

An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd