Precast concrete jacking pipes, Civil Engineering

Assignment Help:

Question

While precast concrete jacking pipes, from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons?


Answer


Grout holes are there in precast jacking pipes for following reasons-

(i) They serve as locations for inoculation of bentonite or other lubricant. Lubricant is used for together granular top soils and cohesive soils to trim down frictional resistance. For cohesive soils, soils cannot get onto pipes by presence of lubricant and the shearing plane lies within lubricant. On other hand, for granular soils, lubricant mixes with soils with a considerably reduced friction. With use of lubricant, longer pipe lengths are able to be jacked without use of intermediate jacking station.

(ii) They give inlet locations for subsequent grouting works after completion of pipe jacking to fill totally the void space b/w pipes and surrounding soils.

(iii)They are used as lifting holes while placing precast jacking pipes into rails within jacking pits.

 

 


Related Discussions:- Precast concrete jacking pipes

Vectors, how are vectors used in civil engineering

how are vectors used in civil engineering

Determine the factor of safety against overturning, A trapezoidal masonry r...

A trapezoidal masonry retaining wall 1 m wide at top and 3 m wide at its bottom is 4 m high. The vertical face is retaining soil (φ = 30°) at a surcharge angle of 20° with the hori

Determine the weight of one gallon of ferric chloride, The specific gravity...

The specific gravity of ferric chloride solution equals 1.3.  How much does one gallon of ferric chloride weigh?  Solution:  ρ ferric chloride /ρ water = 1.3       Conver

Tension members, Tension Members: You have learnt about the Standard s...

Tension Members: You have learnt about the Standard specification for structural steel and various types of structural steel rolled sections. Different types of loads, stresse

Door, types of door with sketches

types of door with sketches

How are freeway bridges built, After measuring the anticipated traffic for ...

After measuring the anticipated traffic for the bridge, cement/reinforced- with- rebar stanchions are spaced over the freeway to accommodate the bridge. An 'off-ramp' from the free

Reinforced Concrete Design, design a 3-meter cantilever slab to carry a uni...

design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.

Calculate the total board feet, A project engineer has ordered 100 hardwood...

A project engineer has ordered 100 hardwood boards, 1-1/4-in thick by 8-in wide and 8-ft long.  The total board feet ordered is most nearly:  Solution: 1.25" x 8" x 8' x 100

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd