Potential advantages of segmental tunnelling, Civil Engineering

Assignment Help:

Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking?

In segmental tunnelling, jacks are installed at the shield so that itisn't necessary to install thrust wall at the jacking pit. This provides the opportunity for smaller size of pit because of the absence of thrust wall. Also as the jacking operation includes the jacking of small length of segmental liner plates and consequently smaller force would be required for pipe jacking when compared with traditional pipe jacking (jacks at jacking pits) where jacking force is needed  to overcome long lengths of pipe drives. Alternatively, the use of segmental tunnelling provides better control in alignment since the steering operation could be performed at the shield.


Related Discussions:- Potential advantages of segmental tunnelling

Thermal stresses, Thermal stresses: In Thermal stresses, you have stud...

Thermal stresses: In Thermal stresses, you have studied (a) The effect of temperature on bodies and materials, (b) The concept of thermal stresses, and (c) The techni

Rock reinforcement – how it works, Rock reinforcement - how it works? ...

Rock reinforcement - how it works? For rocks with widespread fractures, individual blocks resulting from these fractures can fall out and as a result slope failure can take pl

Horizontal capability of pile bents, Question For classic pile bents in...

Question For classic pile bents in marine piers, how can vertical loads related to horizontal capability of pile bents? Answer At first consider a pile bent with a top

Strength of materials, An I-section beam 350*200mm2 has a web thickness of ...

An I-section beam 350*200mm2 has a web thickness of 12.5mm & a flange thickness of 25mm. It carries a shearing force of 200KN at a section. Sketch the shear stress distribution acr

Solis mensuration, the two side are 17 cm and 28 cm long. and the lenght of...

the two side are 17 cm and 28 cm long. and the lenght of the drawn to the third side is equal to 19.5cm. find tghe distance from an endpoint of this medianto the longest s8ide

IRC Class AA loading in existing industrial areas, For IRC Class AA loading...

For IRC Class AA loading in existing industrial areas, what is load (kN/m) has to applied base don the wheel loads. especially raft foundation & roads are at same level.

Equllibrium, how to know about he sign convention for equllibrium forces

how to know about he sign convention for equllibrium forces

Surveying, length of the line measured with 20m chain found to be 250m.calc...

length of the line measured with 20m chain found to be 250m.calculate true length if the chain was 10cm long

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd