Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking?

In segmental tunnelling, jacks are installed at the shield so that itisn't necessary to install thrust wall at the jacking pit. This provides the opportunity for smaller size of pit because of the absence of thrust wall. Also as the jacking operation includes the jacking of small length of segmental liner plates and consequently smaller force would be required for pipe jacking when compared with traditional pipe jacking (jacks at jacking pits) where jacking force is needed  to overcome long lengths of pipe drives. Alternatively, the use of segmental tunnelling provides better control in alignment since the steering operation could be performed at the shield.


Related Discussions:- Potential advantages of segmental tunnelling

Define overloading - deterioration in steel, Define Overloading - Deteriora...

Define Overloading - Deterioration in Steel? Steel structural elements are sensitive to impact damage from moving vessels and other types of accidental overloading. Impact or c

Strength of materials, #questionwhat is the shear force and bending moment....

#questionwhat is the shear force and bending moment..

What is diamond crossing, Q. What is Diamond Crossing? Diamond Crossing...

Q. What is Diamond Crossing? Diamond Crossing is provided when two tracks cross each other either of the same gauge or of different gauges. It consists of two acute crossing (

How can you design side slope of bank, Q. How can you design Side Slope of ...

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

Determine the ultimate bearing capacity of a square footing, Determine the ...

Determine the ultimate bearing capacity of a square footing, 1 m × 1 m, resting on saturated clay of unconfined compression strength of 180 kN/m 3 and a bulk density of 18 kN/m 3

Vibration in structures – resilient bearings, Q. Vibration in structures - ...

Q. Vibration in structures - resilient bearings? When railway tunnels are built close to buildings, ground-borne vibration is transmitted to buildingsthrough compression and sh

Vertical curves - geometric design of roads, Vertical Curves: When tw...

Vertical Curves: When two vertical gradients meet, it is necessary to provide a vertical curve. Two types of vertical curves are used: (a) Summit curve, where the point of

Energy absorbed in heeling during vessel berthing, Q. Energy absorbed in he...

Q. Energy absorbed in heeling during vessel berthing? When a vessel   berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd