Plants aeration period, Civil Engineering

Assignment Help:

Plants aeration period:

Problem:

What is the plant's aeration period?

Solution

The plant's aeration period is the number of hours that the wastewater is aerated during the activated sludge process. These equivalents the hydraulic detention time of the biological reactor

θ= V/Q = 5, 000, 000 l/33.75 × 106 l / day = 0.15 day = 3.6 hours.


Related Discussions:- Plants aeration period

Settlement due to lowering of water table, Q. Settlement due to Lowering of...

Q. Settlement due to Lowering of Water Table? Water table is encountered with, whenever any excavations are made for foundations. The water is to be out for working conditions.

Flooring, construction detail of all types of flooring

construction detail of all types of flooring

Foundation, why is the foundation failure?

why is the foundation failure?

True or false, an increase in consumer income will affect the supply of any...

an increase in consumer income will affect the supply of any given product

Acetylene gas cylinder for gas welding, Q. Acetylene gas cylinder for gas w...

Q. Acetylene gas cylinder for gas welding to be erected in upright position Acetylene gas is normally used for gas welding due to its simplicity in production and transportati

Effect of pile installation method, Effect of pile installation method to l...

Effect of pile installation method to load carrying capacity of piles The construction of piles by driving method causes an increase in density of surrounding soils. Therefore

Explain the installation of shock transmission unit, Explain the Installati...

Explain the Installation of Shock Transmission Unit? It is not always necessary to install STUs while a structure is under construction but the holding down anchor bolts and th

Importance of racking load for a pre-stressed concrete beam, Importance of ...

Importance of racking load for a pre-stressed concrete beam Evaluation of cracking load for a pre-stressed concrete beam member is important for the following cases/reasons.

Explain foundation design discharge for a bridge, Q. Explain Foundation des...

Q. Explain Foundation design discharge for a bridge? To provide for an adequate margin of safety against any abnormal flood exceeding the design discharge (Q), the foundations,

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd