Planning stage of the audit, Civil Engineering

Assignment Help:

Materiality is used only at the planning stage of the audit.

Ans: I disagree with the statement because:

When planning the audit, the auditor considers what would make the financial information materially misstated. The auditor's assessment of materiality and audit risk is used not only at audit planning stage rather it is also applied at evaluating the results of the audit procedures.


Related Discussions:- Planning stage of the audit

Topographical survey and preparation of drawings, Topographical Survey and ...

Topographical Survey and Preparation of Drawings: Topographical Survey for a road project consists of three sequential stages: (a) Reconnaissance Survey, including a study

Aggregate crushing test, Aggregate Crushing Test: In which the layer o...

Aggregate Crushing Test: In which the layer of aggregates in a cylindrical measure is subjected to a compressive load of 40 T, and the per cent fines generated are determined,

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

Determine the statements about unit area or borrow pit, Determine the State...

Determine the Statements about Unit Area or Borrow Pit? Ans: I.  Sometimes called Average Depth II. Works well for volumes for building sites and surface mines III. Needs

Define types of seismic isolation bearing - rubber bearings, Define Types o...

Define Types of Seismic Isolation Bearing - Rubber Bearings? Seismic isolation is obtained by two types of isolation bearings. a) Rubber bearings b) Friction pendulum bea

Define collisions - underwater inspection of bridge, Define Collisions - Un...

Define Collisions - Underwater Inspection of Bridge? Structural damage to underwater portions of a bridge can either be collision related or direct result of a collision. Colli

#memory, assign for memory unit

assign for memory unit

How we can check caisson is stable or not, A box caisson, 10 m high, is 18 ...

A box caisson, 10 m high, is 18 m × 9 m at the base. The weight of the caisson is 9 MN and its centre of gravity is 4.2 m above the base. Check whether the Caisson is stable. If

Construction material, 4. Calculate the loose volume of material needed to ...

4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench

Explain about vierendeel girder, Q. Explain about Vierendeel girder? Vi...

Q. Explain about Vierendeel girder? Vierendeel girder design is sometimes adopted in design of footbridges. Traditionally truss design, triangular shape of truss is generally u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd