Physical tests on cement, Civil Engineering

Assignment Help:

Physical Tests on Cement

(a) Soundness Test: by sieve analysis, it is conducted. 100 gms of cement is taken and sieved throughout IS sieve No. 9 for fifteen minutes. Residue on the sieve is weighed. It should not exceed 10 %by weight of sample taken.

(b) Setting Time: Initial setting time and final setting time are 2 important physical properties of cement. Initial setting time is the time taken by the cement from adding of water to the beginning of losing its plasticity.  the time lapsed from adding of the water to full loss of plasticity is called Final setting time. Vicat apparatus is utilized for finding the setting times .Vicat apparatus consists of a movable rod to which any one of the three needles indicate in figure can be attached. An indicator is attaching to the movable rod. A vicat mould is linked with this apparatus which is in the form of split cylinder.

1365_vicat apppratus.png

                 Vicat apparatus

It is necessary to determine water to be added to get standard consistency before finding initial and final setting time. For this 300 gms of cement is mixed with approximate 30% water and cement paste prepared is filled in the mould which rests on non porous plate. The plunger is associated to the movable rod of vicat apparatus and gently lowered to touch the paste in the mould. Then the plunger is permitted to move freely. If the penetration is 5 mm to 7 mm from the bottom of the mould, then cement have standard consistency. If not, experiment will repeat with different proportion of water fill water needed for standard consistency is found. Then the tests for initial and final setting times may be carried out as described below:

Initial Setting Time: 300 gms of cement is comprehensively mixed with 0.85 times the water for standard consistency and vicat mould is fully filled and top surface is leveled. 1 mm square needle is fixed to the rod and gently placed over the paste. Then it is freely permitted to penetrate. In the starting the needle penetrates the paste fully. As time lapses the paste start losing its plasticity and offers resistance to penetration. When needle may penetrate up to 5 to 7 mm above bottom of the paste experiment is stopped and time elapsed between the addition of water and end I f the experiment is noted down as initial setting time.

Final Setting Time. The square needle is replaced with annular collar. Experiment is continued by permitting this needle to freely move after gently touching the surface of the paste. Time elapsed among the addition of water and the mark of needle but not of annular ring is found on the paste. This time is noted down as final setting time.

(c) Soundness Test: This test is conducted to find free lime in cement, which is not wanted. Le Chatelier apparatus shown in given figure is used for conducting this test. It consists of a split brass mould of height 30 mm and diameter 30 mm. On either side of the split, there are 2 indicators, with pointed ends. The ends of indicators are 165 mm from the centre of the mould.

562_le chatelier appratus.png

                                      Le Chatelier's apparatus

Correctly oiled Le Chatelier mould is placed on a glass plate and is filled fully with a cement paste with 0.78 times the water needed for standard consistency. It is then covered with another glass plate and a small weight is placed over it. Then the entire assembly is kept under water for 24 hours. The temperature of water should be between 24°C and 50°C. Note down the distance between the indicators. Then place the mould again in the water and heat the assembly like that water reaches the boiling point in 30 minutes. Boil the water for 1 hour. The mould is removed from water and permitted to cool. The distance between the 2 pointers is measured. The difference among the two readings indicates the expansion of the cement due to the presence of unburnt lime. This value should not exceed from 10 mm.

(d) Crushing Strength Test: For this 200 gm of cement is mixed with 600 gm of standard sand by confirming to IS 650-1966. After mixing comprehensively in dry condition for a minute distilled potable P/4 +3 percentage is added where P is the water needed for the standard consistency. They are mixed along with trowel for 3 to 4 minutes to get regular mixture. The mix is placed in a cube mould of 70.6 mm size (Area 5000 mm2) reserved on a steel plate and prodded with 25 mm standard steel rod 20 times within 8 seconds. Then the mould is placed on a standard vibrating table that vibrates at a speed of 12000 ± 400 vibration per minute. A hopper is safe at the top and the remaining mortar is filled. The mould is vibrated for 2 minutes and hopper removed. The top is over with a knife or with a trowel and leveled. After 24 ± 1 hour mould is removed and cube is placed under clean water for curing.

After particular period cubes are tested in compression testing machine, keeping the specimen on its level edges. Average of 3 cubes is reported as crushing strength. The compressive strength at the end of 3 days shall not be less than 11.5 N/mm2 and that at the end of 7 days not less than 17.5 N/mm2.


Related Discussions:- Physical tests on cement

Explain plate jig, Explain Plate jig 1) The major parts of this jig is ...

Explain Plate jig 1) The major parts of this jig is plate from which it takes its name other necessary parts and drill bush and locating pins. 2) Plate jigs are general for

Structure, what is the cutelment length

what is the cutelment length

Borrow pits - embankment construction, Borrow Pits Borrow pits are th...

Borrow Pits Borrow pits are the locations from where the embankment soil is obtained. The following guidelines govern the location of borrow pits : (a) They should be pref

What is bonded post-tensioning, What is Bonded Post-tensioning In post...

What is Bonded Post-tensioning In post-tensioned construction, ducts, in which tendons are provided, are sometimes grouted after the stressing operation. Though the mechanism

Show the benefits of adopting marine fill, In reclamation involving large v...

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?  There are two

What is the dry density, Q. The field density of a compacted fill is deter...

Q. The field density of a compacted fill is determined by means of a core cutter whose empty weight is 1000 g and volume is 1000 cm 3 . The cutter full of soil weights 2890 g. If

Determine the in-situ dry unit weight, Q. The following observations were r...

Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We

Test on specially moulded test piece, Test on specially moulded test piece ...

Test on specially moulded test piece The test piece shall be moulded by the manufacturer with identical compound and under identical vulcanizing conditions as used in manufact

Explain the inventory inspections - inspection of bridge, Explain the Inven...

Explain the Inventory inspections - Inspection of Bridge? These inspections are normally performed following new construction, modifications, or repair to establish as-built or

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd