Packing resources in joint of concrete pipes in pipe jacking, Civil Engineering

Assignment Help:

Question

What is key function of packing resources in joint of concrete pipes in pipe jacking?

Answer

Packing resources are about 10 to 20mm broad and are usually made of plywood, fibreboard or previous materials. In case the packing materials are absent in pipe joints for pipe jacking, after that any deflection in joints reduces contact area of concrete and it leads to spalling of joints due to high pressures induced. With insertion of packing fabric inside pipe joints, the acceptable deflection without damaging joint throughout pipe jacking process is able to be increased.

 

 


Related Discussions:- Packing resources in joint of concrete pipes in pipe jacking

LOADS, what are the difference between UDL and UVL?

what are the difference between UDL and UVL?

Determine the loss of fluid energy, Determine the loss of fluid energy as 3...

Determine the loss of fluid energy as 310 gallons per minute (gpm) of water flows through 1,000 ft of 4 inch, schedule-40 welded and seamless steel pipe. The fluid temperature is 5

Hiley formula in designing of h-piles, Question Is it resourceful that ...

Question Is it resourceful that engineers rely solely on Hiley's formula in designing of H-piles? Answer About 90 percent of H-piles accept Hiley's formula for desig

Define types of deterioration in steel substructure, Define Types of Deteri...

Define Types of Deterioration in Steel Substructure There are 5 major types of deterioration in steel substructure in the marine environment: - Corrosion - Abrasion - Loo

Civil, vcdjvoidj pirioi oique

vcdjvoidj pirioi oique

Gas welding be erected in upright position, Question Explain some reaso...

Question Explain some reasons why should acetylene gas cylinders used for gas welding be erected in upright position? Answer Acetylene gas is usually used for gas wel

State the angle of inclination of the failure plane, The stresses at failur...

The stresses at failure on the failure plane in a cohesionless soil mass were: Shear stress = 4 kN/m 2 ; normal stress = 10 kN/m 2 . Verify the resultant stress on the failure plan

Practice to form washout regulators, Question Why are two gate regulato...

Question Why are two gate regulators necessary in regular practice to form washout regulators ? Answer In fact, situation is analogous to that of fire hydrants in tha

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Explain ductile iron pipes and mild steel pipes, Ductile iron pipes vs. mil...

Ductile iron pipes vs. mild steel pipes as pressurized pipelines For water main pipe size less than 600mm, ductile iron is generally used since internal welding for steel pipe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd