Order sequences and order release, Mechanical Engineering

Assignment Help:

Order Sequences and Order Release

For this system, sequences of orders for particular parts (batch size 1) are produced in the following way: for each machine, here is, for each shift, a prescribed maximal load level ζ is calculated as ζ (machine type, shift number) = ζ0 (machine type) + Δ ζ (shift number) Δ ζ is arbitrary parameter, the load variation.

Because of the processing sequences structure, the average load ζ0 can only be selected freely on three of the four categories of machines. The selected values are as:

For case 1: 98 percent on HV, DOER and 98 percent on ECOC

For case 2: 98 percent on HV, DOER and 70 percent on ECOC

The load amplitude Δ ζ is understood to be either 0, - 30 percent, or + 30 percent. The actual part mix for simulation is produced from a basic random part type sequence along with average element type frequencies of 10 percent for part 1 and 9 percent for other parts. For all shift, there is a load account for all machines. An order for an exact part type is accepted as extended as the load accounts for all needed machines and for this shift it must not exceed the maximum load level ζ for this shift and these machines. Also, this is skipped. If no more element types can be accepted for this shift, the order sequence for this shift is finish. The subsequent order in the basic sequence becomes the initial new order for the subsequent shift. The actual average part frequencies are hence various from the values in the basic sequence.

As load level can be above 100 percent machine capability, there are backlogs. They are carried above to the subsequent shift. Over the initial 5, 10, 15 and so on, consecutive shifts, the average load level variations are put to zero.

The real order sequences are produced from five various basic element type sequences and five fundamental load variation sequences for all of the conditions illustrated below.

In case 1, orders are released along with equivalent spacing over the duration of a shift within every 19 minutes. In case 2, all orders are released at the starting of a shift. This offers rise to a considerably longer queues for the initial half shift, in exacting at the loading station.

Hence, the characteristics of case 1 can be summarized as: evenly distributed high loads on the machines along with temporary overload; at the stations, short to moderate queues. Within case 2, the characteristics can be specified as: part types 1-5 only need machines that are not bottlenecks; only element types 6-11 utilize machines that may be overloaded; the queues are long; the loading station is a dangerous resource.

Additionally to above conversation, the due date distribution is a critical parameter also that affects the presentation of the  scheduling policies. The due dates are produced as multiples of four hour (1/2 shift) intervals from order free. The percentage of orders for every value of this demanded throughput time was found such as under scheduling as per to FIFO a prescribed value of percentage of late jobs of as 30, 50, 70, and 85% was attained. The resulting distributions are shown in Table no.2 (a) and (b).  The  resulting  ratios  of  demanded  to  real  throughput  times  for  the various situations under the FIFO rule have also been specified in aforementioned tables.

The conditions A-D correspond to case 1, the percentage of late jobs raising from 30-85, the conditions E-H correspond to case 2 along with similar levels of late jobs under the FIFO rule.

Table no.2 (a): Due Dates Distribution for Situation A-D

Situation A : Case 1, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            10

480                            10

720                            10

960                            35

1200                          35

Average Throughput Time: 900 min

Demanded/achieved flow factor: 1.29

 

Situation  A  :  Case  1,  50%  late  jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

240                            10

480                            25

720                            30

960                            25

1200                          10

Average Throughput Time: 720 min

Demanded/achieved flow factor: 1.03

 

Situation A : Case 1, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            24

480                            34

720                            32

960                            5

1200                          5

Average Throughput Time: 559 min

Demanded/achieved flow factor: 0.80

 

Situation  A  :  Case  1,  85%  late  jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

240                            60

480                            25

720                            5

960                            5

1200                          5

Average Throughput Time: 408 min

Demanded/achieved flow factor: 0.57

 


Related Discussions:- Order sequences and order release

Semi-active suspension systems, With an open loop system, the only way to m...

With an open loop system, the only way to modify the behaviour of the system is to modify the values of physical parameters in the system. For instance we can modify the damping co

Rotary vacuum, Explain with the aid of a sketch how a rotary vacuum (ROVAC)...

Explain with the aid of a sketch how a rotary vacuum (ROVAC) filter works. Derive describing equations to predict the ROVAC's filtration performance in terms of the effect of drum

Torsion , in the torsion equation the term j/r is called

in the torsion equation the term j/r is called

Woodwork, with the aid of notes and sketches describe how you would transfe...

with the aid of notes and sketches describe how you would transfer the design from a sheet of paper onto the wooden panel prior to carving

Stroke and clearance volume - thermodynamics, Stroke and Clearance Volume: ...

Stroke and Clearance Volume: Stroke The distance traveled by piston from the topmost positions of it (also called Top dead centre TDC ), to its bottom most position (or

Reactions at grouted end of cantilever beam, Reactions at grouted end of ca...

Reactions at grouted end of cantilever beam: Q: Find reactions at grouted end of cantilever beam shown in figure given below     Draw free body diagram of the beam

Show the sources of ignition, Q. Show the Sources of Ignition? Sources ...

Q. Show the Sources of Ignition? Sources of Ignition - Possible sources of ignition include the following: • Electrical: Sparks or arcs may occur when current carrying cont

Evaluate maximum stress, Show that for a flat circular steel plate subjecte...

Show that for a flat circular steel plate subjected to uniform pressure on one surface, the maximum stress when the periphery is freely supported is 1.65 times that when the periph

Calculate the coefficient of performance of refrigerator, (a) List out the ...

(a) List out the advantages of air refrigeration system besides of vapour refrigeration system . (b) A vapour Compression refrigerator uses R-40 and acts between temperature - 1

Explain classification of welding processes, Classification Of Welding Proc...

Classification Of Welding Processes The classificated depending upon the nature of heat source and its movement resulting in spot, seam or zonal welds; or on the extent of heat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd