Order sequences and order release, Mechanical Engineering

Assignment Help:

Order Sequences and Order Release

For this system, sequences of orders for particular parts (batch size 1) are produced in the following way: for each machine, here is, for each shift, a prescribed maximal load level ζ is calculated as ζ (machine type, shift number) = ζ0 (machine type) + Δ ζ (shift number) Δ ζ is arbitrary parameter, the load variation.

Because of the processing sequences structure, the average load ζ0 can only be selected freely on three of the four categories of machines. The selected values are as:

For case 1: 98 percent on HV, DOER and 98 percent on ECOC

For case 2: 98 percent on HV, DOER and 70 percent on ECOC

The load amplitude Δ ζ is understood to be either 0, - 30 percent, or + 30 percent. The actual part mix for simulation is produced from a basic random part type sequence along with average element type frequencies of 10 percent for part 1 and 9 percent for other parts. For all shift, there is a load account for all machines. An order for an exact part type is accepted as extended as the load accounts for all needed machines and for this shift it must not exceed the maximum load level ζ for this shift and these machines. Also, this is skipped. If no more element types can be accepted for this shift, the order sequence for this shift is finish. The subsequent order in the basic sequence becomes the initial new order for the subsequent shift. The actual average part frequencies are hence various from the values in the basic sequence.

As load level can be above 100 percent machine capability, there are backlogs. They are carried above to the subsequent shift. Over the initial 5, 10, 15 and so on, consecutive shifts, the average load level variations are put to zero.

The real order sequences are produced from five various basic element type sequences and five fundamental load variation sequences for all of the conditions illustrated below.

In case 1, orders are released along with equivalent spacing over the duration of a shift within every 19 minutes. In case 2, all orders are released at the starting of a shift. This offers rise to a considerably longer queues for the initial half shift, in exacting at the loading station.

Hence, the characteristics of case 1 can be summarized as: evenly distributed high loads on the machines along with temporary overload; at the stations, short to moderate queues. Within case 2, the characteristics can be specified as: part types 1-5 only need machines that are not bottlenecks; only element types 6-11 utilize machines that may be overloaded; the queues are long; the loading station is a dangerous resource.

Additionally to above conversation, the due date distribution is a critical parameter also that affects the presentation of the  scheduling policies. The due dates are produced as multiples of four hour (1/2 shift) intervals from order free. The percentage of orders for every value of this demanded throughput time was found such as under scheduling as per to FIFO a prescribed value of percentage of late jobs of as 30, 50, 70, and 85% was attained. The resulting distributions are shown in Table no.2 (a) and (b).  The  resulting  ratios  of  demanded  to  real  throughput  times  for  the various situations under the FIFO rule have also been specified in aforementioned tables.

The conditions A-D correspond to case 1, the percentage of late jobs raising from 30-85, the conditions E-H correspond to case 2 along with similar levels of late jobs under the FIFO rule.

Table no.2 (a): Due Dates Distribution for Situation A-D

Situation A : Case 1, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            10

480                            10

720                            10

960                            35

1200                          35

Average Throughput Time: 900 min

Demanded/achieved flow factor: 1.29

 

Situation  A  :  Case  1,  50%  late  jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

240                            10

480                            25

720                            30

960                            25

1200                          10

Average Throughput Time: 720 min

Demanded/achieved flow factor: 1.03

 

Situation A : Case 1, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            24

480                            34

720                            32

960                            5

1200                          5

Average Throughput Time: 559 min

Demanded/achieved flow factor: 0.80

 

Situation  A  :  Case  1,  85%  late  jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

240                            60

480                            25

720                            5

960                            5

1200                          5

Average Throughput Time: 408 min

Demanded/achieved flow factor: 0.57

 


Related Discussions:- Order sequences and order release

Master production schedule, Master Production Schedule: A manufacturin...

Master Production Schedule: A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week

Thermodynamics, Q2 A 3kW electric water heater is a cylindrical element hav...

Q2 A 3kW electric water heater is a cylindrical element having outside diameter 10mm. The heat transfer between the heater and the surrounding water is 980W/m2K. Determine the leng

Explain frequency reuse, Explain frequency reuse In the cellular conce...

Explain frequency reuse In the cellular concept, service area is separated into regions called cells and the available frequency is divided among these cells. Every cellular b

Wet h2s corrosion, There is risk of wet H 2 S corrosion in all emulsion and...

There is risk of wet H 2 S corrosion in all emulsion and gas lines from the Inlet Separator up to and including the Treater. Full compliance to NACE is highly recommended to contro

What is the basic working principle of capacitive transducer, Answer any fi...

Answer any five questions. a) Describe calibration and state its types. b) Which are the kinds of test signals? c) What is the basic working principle of piezo-electric tr

Ejection seat, basic idea in designing of aircraft ejection seat

basic idea in designing of aircraft ejection seat

Swing arm shock absorber , Swing Arm Shock Absorber :   This type of suspe...

Swing Arm Shock Absorber :   This type of suspension is used to serve for rear part of motorcycle. The advantage of this type of suspension is that large deflections are absorbed.

Make evaluation for the engine efficiency, (a) Differentiate between carnot...

(a) Differentiate between carnot Heat pump and carnot Heat engine. What is the basic cycle for a carnot Heat pump ? Explain it. (b) A reversible heat engine delivers 0.6 K at po

Define term transfer of stress to footing, Define term transfer of stress t...

Define term transfer of stress to footing. Transfer of Stress to Footing:  The column transfers the load to the top of the footing by bearing. The magnitude of the pressure

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd