Order quantity and reorder point, Mechanical Engineering

Assignment Help:

Example: Order Quantity and Reorder Point:

Daily demand for a particular product manufactured by ABC company is distributed normally with a mean of 30 and standard deviation of 5. The source of supply is reliable and maintains a constant lead time of 6 days. The expense of placing the order is Rs. 8.5 and annual holding cost is Rs. 0.75 per unit. There is no stock out costs, and unfilled orders are filled as soon as the order arrives. Consider sales occur over the whole 365 days of the year. Determine the order quantity and reorder point to satisfy a 95 per cent probability of not stocking out throughout the lead time.

Solution

For this problem, we shall first calculate the order quantity Q as well as the reorder point R. Given data are

d'  = 30 S = Rs. 8.5      σ d   = 5   H = Rs. 0.75   D = 30 (365)   L = 6

The optimal order quantity is

1152_Order Quantity and Reorder Point.png

For calculating the reorder point, we ought to calculate the amount of product used during the lead time and add this to the safety stock.

The standard deviation of demand throughout the lead time of six days is computed from the variance of the individual days. As each day's demand is independent

564_Order Quantity and Reorder Point1.png

Since, z is 1.64,

R = d'L + z σL  = 30 (6) + 1.64 (12.2474) = 200.0857 units

To sum up the policy derived in this instance, an order for 498 units is placed whenever the number of units remaining in inventory drops to 200 units.

Attaining actual order, setup, carrying and shortage costs is hard. For instance, Figure compares the ordering costs that are supposed linear to the real case where every addition of a staff person causes a step enhanced in cost. Mostly inventory systems are affected by two major problems viz. maintaining sufficient control over each inventory item, and ensuring that accurate records of stock on hand are kept.

 

1339_Order Quantity and Reorder Point2.png

Figure: Cost to Place Orders Versus the Number of Orders Placed : Linear Assumption and Normal Reality


Related Discussions:- Order quantity and reorder point

Define properties of system, Define Properties of System For defining a...

Define Properties of System For defining any type of system particular parameters are required. Properties are those observable characteristics of the system, which can be util

How to calculate coupling factor?, Q. Two coils with self inductances 1H an...

Q. Two coils with self inductances 1H and 4H have a mutual inductance of 1H. The RMS value of current flowing in the two coils is 4A and 1A respectively. Find  the coupling factor

Determine the net work - mechanics, Determine the net work: Q: 5 m ...

Determine the net work: Q: 5 m 3   o f air at 2 bar, 27°C is compressed to 6 bar pressure following PV 1.3   =C . It is expanded subsequently adiabatically to 2 bar. C

Explain working of belt transmission type dynamometer, Explain construction...

Explain construction and working of Belt transmission type Dynamometer?

Explain the semi universal drilling machine, Explain the semi universal dri...

Explain the semi universal drilling machine The semi universal drilling machine this machines, in addition to the above three basic movements, carry provision for swinging of

Show the tensile properties of material, Q. Show the tensile properties of ...

Q. Show the tensile properties of material? Tensile properties indicate how the material will react to forces being applied in tension. A tensile test is a fundamental mechanic

Explain the process for solve screw conveyer problem, Process for solve scr...

Process for solve screw conveyer problem For fully automatic extension of screw conveyer according to screed width we have to go for some design changes, At the end of main

Consider some publications of the bureau of standards, Consider some public...

Consider some publications of the Bureau of Standards. The following publications of the Bureau of Standards shall be read along with this section of footings. a. IS 456 in

Calculate diameter of runner, A radically inward flow turbine working under...

A radically inward flow turbine working under a head of 10 m and running at 250 rpm develops 185 KW at the turbine shaft. At inlet tip of the runner vane, the peripheral velocity o

Spring, direct shear and torsional shear of the coil

direct shear and torsional shear of the coil

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd