a)Draw a network for the project. b)Determine the critical path. Activity Duration Activity Duration 1-2 15 5-10 22 1-3 13 6-9 33 1-4 1
It can be seen from the optimal solution for the foundry problem that two resources, raw material-1 and labor, are exhausted whereas the other two resources, raw materi
Maximize p = (3)x + 2y subject to 2x + y 3x + 4y >= 12
Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0
A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i
Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X 1, X2 = 0
A PAPER MILL PRODUCES TWO GRADES OF PAPER VIZ., X AND Y. BECAUSE OF RAW MATERIAL RESTRICTIONS, IT CANNOT PRODUCE MORE THAN 400 TONS OF GRADE X PAPER AND 300 TONS OF GRADE Y PAPER I
simple Size When a survey is undertaken and it is not possible to cover the entire population, the marketing researcher has to answer a basic question - how large s
Question: (a) Distinguish between (i) a single-channel and a multiple-channel waiting line; (ii) a birth and a death process with regard to queueing theory. (b) Explain
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd