For compaction of free-draining sands or gravels, what is optimum moisture content to grab maximum density?
Answer
Compaction curve of dirty materials is completely different from that of clayey materials. For sands, gravels, there are two states of affairs of utmost density, namely completely dry condition and complete water saturation. For humidity content of sand and gravels between two states, dry density obtained is lesser than that obtained in above-mentioned states. Occurrence of capillary forces account for difficulty of compaction sand at water contents between almost dry and saturated state. They are shaped in partially filled water invalid between soil particles and do as elastic ties cementing soil particles jointly. Compaction curve for clay is appropriate for majority of soil types apart from sands and gravels since a little amount of clay in soils is enough to create soils impermeable.
Describe 'general shear failure' and 'Local shear failure'. Differentiate among (i) Shallow foundation and deep foundation, (ii) Gross and net bearing capacity, (iii) S
The drainage system of a cantilever wall shown in Figure As 1 became blocked after a heavy rainstorm and the groundwater level, which was originally below the base, rose to1.5 (m)
Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep
coefficent of friction in circular pipes
Define Hydraulic tools for underwater inspection of bridge? Hydraulic tools involve grinders, rotary brushes and scrubbers. The benefits of hydraulic tools are the same as thos
What are main and key benefits of piers constructed monolithically with bridge deck over usage of bearings?
State the Design process of Prestressed Concrete Most of the times, the design process is an interactive and trial procedure in which the cycle of analysis - design - analysis
Q. Method of construction of a bored cast-in-situ concrete pile? Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole
explain the term
distribution of shear stress in triangular section
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd