For compaction of free-draining sands or gravels, what is optimum moisture content to grab maximum density?
Answer
Compaction curve of dirty materials is completely different from that of clayey materials. For sands, gravels, there are two states of affairs of utmost density, namely completely dry condition and complete water saturation. For humidity content of sand and gravels between two states, dry density obtained is lesser than that obtained in above-mentioned states. Occurrence of capillary forces account for difficulty of compaction sand at water contents between almost dry and saturated state. They are shaped in partially filled water invalid between soil particles and do as elastic ties cementing soil particles jointly. Compaction curve for clay is appropriate for majority of soil types apart from sands and gravels since a little amount of clay in soils is enough to create soils impermeable.
Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw
Radial flow pumps for small flows and high heads In radial flow pumps, a diffuser/volute is generally designed at it outlet to convert the kinetic energy obtained during the pu
Grade of Cement: In India, the following grades of cement are used for roads : Ordinary Portland Cement (OPC) Grade 33 Grade 43 Grade 53 Portland Pozz
Cross-sectional area of flow (ft 2 ) (A) For rectangular channels = (w)(d). For trapezoidal channels, divide the flow area into two side triangles and one center rectangle, so
Comparison of pre and post-tensioning A comparison between pre-tensioned and post-tensioned concrete members can be made on the basis of the following considerations. (a) T
Construction: Construction is usually done by one of the three methods: (a) Manual method, providing steel or wooden forms, pouring concrete and compacting by means of nee
Define Advantages of Shock Transmission Unit? (a) STU is simple to install with minimal traffic disruption. (b) STU can be used for strengthening of existing bridges also. T
how can we build a complete home on an area of 500 meter squares with garden and house and a garage
what is the actual quantity of water to be mixed in various grade of concrete and also the size of gravel to be mixed with in RCC work. Also I want to know the difference between a
State the term - Failure Due to Strain In most of the cases of pre-stressed concrete construction, the failure of underreinforced and lightly reinforced members shall take pla
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd