Q. Optimum binder content in bituminous pavement?
Amount of binder to be added to a bituminous mixture can't be too excessive or too little. Principle of designing the optimum amount of binder content is to comprise sufficient amount of binder so that aggregates are fully coated with bitumen and voids within the bituminous material are sealed up. The durability of bituminous pavement can be improved by the im-permeability achieved. Furthermore a minimum amount of binder is necessary to prevent the aggregates from being pulled out by abrasive actions of moving vehicles on the carriageway.
Though the binder content can't be too high since it would lead to the instability of the bituminous pavement. Basically, resistance to deformation of bituminous pavement under traffic load is decreased by the inclusion of excessive binder content.
Strength of Concrete at the Transfer Stage Concrete strength in the member at the transfer stage should conform to the design requirements. The frequency of the sampling and t
Discuss about the fibre reinforced concrete Tensile strength of concrete may be improved by using a higher grade of concrete or by using special concretes such as fibre reinfor
differences between highway pavement and airfield pavement
Geotechnical project specifications require that the soil's optimum moisture content of 24% be maintained during the roadbed's construction. The field moisture test finds that fi
Define Equipments and tools required for under water Inspection of Bridge? Since the underwater inspection of stone masonry substructures involve only a cursory inspection of t
distribution of shear stress in triangular section
Question What is major disparity between capping beams and ground beams for piles? Answer Capping beams for piles plan to transferring loads from directly spaced c
how to design gusset plate design
describe in detail the various parts of a total station
Explain National Contingency Plan (NCP) - Provides detailed direction on the action to be taken at a hazardous waste site, including emergency actions and a method to rank site
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd