Normal approximation to compute the probability, Civil Engineering

Assignment Help:

Normal approximation to compute the probability:

A lot contains 100 articles of which 10 are defective. The lot is rejected if a random sample of 10 articles drawn from the lot contains more than 2 defectives. Use normal approximation to compute the probability that the lot is accepted.

Solution:

Let X represents the number of defective articles in the sample. The variable X follows the hypergeometric distribution with parameters

N = 100,n - 10,M = l0 and has E(X) = 10.(10/100) = 1 and

V(X) =σ2 = 10.10/100.(1-(10/100)) (100-10/100-1) =9/11

The required probability is

903_Normal approximation to compute the probability.png


Related Discussions:- Normal approximation to compute the probability

State about the pre-tensioned concrete, State about the pre-tensioned concr...

State about the pre-tensioned concrete In pre-tensioned concrete, the tendon stresses are transferred  to concrete by  virtue of bond  of concrete to the  surface of steel tend

Construction of passenger terminal building, Construction of Passenger Term...

Construction of Passenger Terminal Building: There are various concepts in planning and constructing passenger terminal buildings. These are : (a)        The international

Surveying, with a neat well labelled sketch, explain reciprocal ranging.

with a neat well labelled sketch, explain reciprocal ranging.

Dry process of cement, i want a complete flow chart of dry process of cemen...

i want a complete flow chart of dry process of cement

Pattern of load distribution of piles in such agreement, Question For a...

Question For a rigid pile cap with vertical piles at middle and raking piles at the sides, what is pattern of load distribution of piles in such agreement? Answer Becau

Parallel pipe systems or multipath pipeline problems, Parallel Pipe Systems...

Parallel Pipe Systems or Multipath Pipeline Problems Two or more sections of piping (branches) of different diameters, lengths and/or pipe materials originating and terminating

Immersed tube method for underwater crossings, Immersed tube method for und...

Immersed tube method for underwater crossing includes the following basic construction steps: (i)  Prefabricating long tunnel units (concrete orsteel shell) in a dry-dock or shi

Show the settlement due to vibration, Q. Show the Settlement due to Vibrati...

Q. Show the Settlement due to Vibration? The foundation resting on cohesionless soil and subjected to vibrations will result in settlements of higher magnitude. In sandy soil

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd