A square pile group of 9 piles of 25 cm diameter is arranged with a pile spacing of 1m. The length of the piles is 9 m. Unit cohesion of the clay is 75 kN/m2.

Neglecting bearing at the tip of the piles Verify the group capacity.

Assume adhesion factor of 0.75.

 


Related Discussions:- Neglecting bearing at the tip of the piles

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Airport., draw a typical layout of airport ?

draw a typical layout of airport ?

Determine the total lateral pressure on the wall, A masonry retaining wall ...

A masonry retaining wall is 1.5 m wide at the top, 3.5 m wide at the base and 6 m high. It is trapezoidal in section and has a vertical face on the earth side. The backfill is leve

Define the concept of creep of concrete, Define the concept of Creep of Con...

Define the concept of Creep of Concrete Creep of concrete is another important characteristic. It represents progressive strains in concrete which occur at constant value of st

Explain the term - non-bonded prestressed concrete, Explain the term - Non-...

Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd