Q. Necessity of pile tip cover for rock-socketed H-piles?
In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The objective of such arrangement is to avoid the potential occurrence of corrosion to H-piles just in case concrete cover isn't designed at pile tips. Though recent field andlaboratory observations had reservation of this viewpoint. In case H-piles are designed to be placed directly on top of rock surface, it provides tip resistance to limit the pile movement in the event of bond rupture between H-piles and grout. Some contractors can choose to tamp the H-piles by employing drop hammers to make sure the H-piles are founded directly on top of rock surface. Practically speaking, it poses difficulties at the time of process of tamping since there is a chance of possible buckling of long H-piles when too much energy is provided to piles.
Define the Cavitation - underwater inspection of bridge? Cavitation damage is caused by repeated impact forces caused by collapse of vapour bubbles in rapidly flowing water. Th
Tack coat - emulsified asphalts vs. cutback asphalts Emulsified asphalt is a suspension of asphalt in water by employing an emulsifying agent that imposes an electric charge o
what are the cement testing?
What is compacting factor
Define Drag load test of shock transmission unit? This test ensures that excessive load should not be transmitted to the structure by the STU. As per the test the STU shall hav
State about the Prestressing Steel For prestressed concrete members, the high-tensile steel, used generally, consists of wires, bars or strands. The high tensile strength of s
#questidisadvantage of steelon..
Q. Method of construction of a bored cast-in-situ concrete pile? Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole
explain registers and factors influencing them
i want the meaning of crete
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd