Movement accommodation factor for joint sealant, Civil Engineering

Assignment Help:

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint sealant can tolerate and is typically expressed as a percentage of the minimumdesign joint width. Failure to fulfil this requirement results in overstressing the joint sealants. 

For example if the expected movement to be accommodated by a certain movement joint is 4mm, the minimum design joint width can be computed as 4÷30% = 13.3mm when the movement accommodation factor is 30%. If the calculated joint width is too large, designers can either select another brand of joint sealants with higher movement accommodation factor or to redesign arrangement and locations of joints.


Related Discussions:- Movement accommodation factor for joint sealant

Surveying, What is the shrinkage factor

What is the shrinkage factor

Design storm water drains to match soffit, Question Why is it best to desig...

Question Why is it best to design storm water drains to match soffit? Answer Storm water drains gather storm water in their corresponding catchment areas throughout rainst

Void ratio, a soil sample is 38mm in diameter and 76mm and in its natural c...

a soil sample is 38mm in diameter and 76mm and in its natural condition weighs 168g.when dried completely in an oven weighs 13o.5g.the value of Gs is 2.73.what is the degree of sat

Energy absorbed in heeling during vessel berthing, Q. Energy absorbed in he...

Q. Energy absorbed in heeling during vessel berthing? When a vessel   berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of

Explain the soil texture and soil structure, (a) Explain the 'Soil Texture'...

(a) Explain the 'Soil Texture' and 'Soil structure'. What are the various terms used to explain the above properties of the soil? (b) A clay sample having natural moisture conte

Environmental Question, An activated sludge tank treats 1 MGD from the pri...

An activated sludge tank treats 1 MGD from the primary clarify and has an X of 2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank and has

Pre-stressing work, Under which situation shall engineers use jacking in ag...

Under which situation shall engineers use jacking in agreement end only and from both ends in pre-stressing work?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd