Moisture-Density Relationship:
Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.
For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.
Belt Conveyors: Belt conveyors are used for conveying materials on a continuous basis. The materials usually handled are coal, mineral ores and stone. They are commonly instal
I have a writing that needs to be corrected
Using an optical square how would you perform a rectangular tie?
#estimate of rcc beam
define
how can you draw contours of a non square grid?
Question In search reclamation, what are considerations in choosing between trailer suction hopper dredgers and grab dredgers ? Answer Trailer suction hopper dred
Enumerate the Variation in tendon stress In post-tensioned construction, several tendons are simultaneously stretched and anchored at the ends. It is assumed that all tendons
what is a 1st sort,2nd sort, 3rd sort stone masonary
The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd