Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

Will water damage concrete, As far as only concrete is concerned i.e. plain...

As far as only concrete is concerned i.e. plain concrete, the effect of water seepage is very little (depending upon the grade of concrete) whereas for RCC (reinforced cement concr

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Binomial distribution - exact probability, Binomial Distribution - exact pr...

Binomial Distribution - exact probability: For the binomial distribution having n = 10, y = 0.4, find p (X ≤ 4) using equations and verify that equation gives a better approxi

Water retaining structure, Question Why do BS8007 specify permissible c...

Question Why do BS8007 specify permissible crack width of water retaining structure as 0.2mm for severe, extremely severe exposure? Answer For break width less than

Calculate the total board feet, A project engineer has ordered 100 hardwood...

A project engineer has ordered 100 hardwood boards, 1-1/4-in thick by 8-in wide and 8-ft long.  The total board feet ordered is most nearly:  Solution: 1.25" x 8" x 8' x 100

Surveying, A pre- engineering base line was run down a very steep hill.rath...

A pre- engineering base line was run down a very steep hill.rather than measure horizontaily down hill with steel tape: surveyor measured the vertical angle with the theodolite and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd