Moisture-Density Relationship:
Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.
For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.
character of working of survey
Explain economical span if bridges
Question Give genuine reason that why are steel tubular marine piles often driven open-ended? Answer In marine structure where piles are constantly topic to major la
Water Transportation: Water transport, in its various forms, is one of the most efficient forms of transport, because of low fuel consumption, low environmental pollution and
How to use plaster cement in sand? Cement sand plaster is a layer of cement & sand mortar that is applied over walls made of brickwork, cement block work, RCC walls and RCC co
Solved examples on linear programming partB
Explain the Basic requirement of Design of shock transmission unit? The STU must withstand the specified design load. The stroke of the piston must be bigger than the movement
Find out the joint distribution: Let X I and X 2 be two independent random variables each distributed uniformly in the interval [ 0, a ], where a > 0 is a constant. Find out
List the ingredients of cement And their functions
Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge? Ans.- 1. General - The minimum length of LWR depends upon - i. Range of temporary variati
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd