Moisture-density relationship, Civil Engineering

Assignment Help:

Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Autocad, Please check the file

Please check the file

Two property rule , The state of a pure substance of given mass is defined ...

The state of a pure substance of given mass is defined by specifying two appropriate properties provided that 1. The system is in equilibrium 2. Gravity, motion, electricity,

Deterioration in steel, How abrasion and earthquake causes deterioration in...

How abrasion and earthquake causes deterioration in steel structures

Whole base of mat, Question In modeling a nonrigid mat foundation by us...

Question In modeling a nonrigid mat foundation by using elastic springs, have a uniform modulus of subgrade reaction be used along whole base of mat ? Answer A bed of

Infrastructure railway design, The objective of this module is:- - For t...

The objective of this module is:- - For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibili

Drawbacks of curing by ponding and polythene sheets, Question What are the ...

Question What are the main drawbacks of curing by ponding and polythene sheets ? Answer Purpose of curing is to decrease the speed of heat loss of freshly placed concrete to atm

Define pressure on an inclined plane, Define Pressure on an Inclined Plane ...

Define Pressure on an Inclined Plane Similar to a vertical plane, fluid pressure increases linearly with increasing depth. The average pressure on an inclined plane occurs at t

Determine the term - final tension, Determine the term - Final Tension ...

Determine the term - Final Tension The tension in tendons after losses of prestress have taken place is called as final tension. Final tension is taken to be corresponding  to

Advantages of unbonded post-tensioning systems, Advantages of unbonded post...

Advantages of unbonded post-tensioning systems Similarly, some advantages of unbonded post-tensioning systems over bonded post-tensioning ones may be written as under :  (a)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd