Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Determine the types of losses of prestress, Determine the types of losses o...

Determine the types of losses of prestress A loss of prestress will affect the stress distribution on a section of the member. It is therefore necessary to estimate the probabl

Drawing, how to draw an elipse

how to draw an elipse

Timber, TIMBER Timber refers to wood utilized for construction works. A...

TIMBER Timber refers to wood utilized for construction works. Actually the word timber is derived from an old English word 'Timbrian' that means 'to build'. A tree that yields

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

How quality control is maintained in a rolled fill dam, Sketch a curve show...

Sketch a curve showing the relation among dry density and moisture content for Standard Proctor test and indicate the salient features of the curve. Describe why soils are compacte

Diffrence between rowe cell and oedometer apparatus, Q. Diffrence between R...

Q. Diffrence between Rowe cell and Oedometer apparatus? The benefits of using Rowe cell over oedometer apparatus are:  (i)  It possesses control facilities for drainage and

Calculate carbon intensity, how to calculate the carbon intensity (gC/MJ) f...

how to calculate the carbon intensity (gC/MJ) for gasoline ( C7H16 ) , we have the Energy Density = 32.2 MJ/L Fluid Density = 0.727 g/mL

Maintenance of terminal building, Maintenance of Terminal Building: A...

Maintenance of Terminal Building: All accessories such as lighting, water, sanitation, telephone and public address system should be maintained in a good condition. Disposal

Foundation, The strap serves the same purpose as the interior portion of a ...

The strap serves the same purpose as the interior portion of a combined footing but is much narrower to save materials. ? The resultant soil pressure is assumed at the centers of b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd