Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Explain hardness - water softening, Explain Hardness - Water Softening ...

Explain Hardness - Water Softening 1) Hardness is used to characterize a water that does not lather well, causes a scum in the bath tub and leaves hard, white, crusty deposits

Compute the negative skin friction of the pile group, A square pile group o...

A square pile group of 9 piles passes by a recently filled up material of 4.5 m depth. The diameter of the pile is 30 cm and pile spacing is 90 cm centre to centre. If the unconfin

Surveying, obstacles in chain surveying

obstacles in chain surveying

List the factor that affect the permeability of a given soil, List the fact...

List the factors that affect the permeability of a given soil. Determine the precautions that should be taken so that satisfactory permeability data may be obtained. Explaining

Marine piles circular in cross section, Question Give reason that why a...

Question Give reason that why are most marine piles circular in cross section? Answer As marine piles, there are a number of options existing for selection, name as H-

Ranging, describe reciprocal ranging

describe reciprocal ranging

Surveying, how to make plain scale

how to make plain scale

Cement, Why we mixm pozzolona in cement

Why we mixm pozzolona in cement

What is corrosion inhibitors, Q. What is Corrosion inhibitors? Corrosio...

Q. What is Corrosion inhibitors? Corrosion inhibitors are chemical substances that when added in small concentrations, stop or decrease the corrosion or reaction of metalwith t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd