Moisture-Density Relationship:
Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.
For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.
An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank
Compass surveying
applying quadratics in civil engineering
Explain Coagulation Surface waters must be treated to remove turbidity, color and bacteria The traditional sand filtration is not sufficient in removing bacteria, viru
Explain the Inventory inspections - Inspection of Bridge? These inspections are normally performed following new construction, modifications, or repair to establish as-built or
Define the term - Clamp splice In a Clamp splice, bolts and nuts alongwith clamp plates are used. Tendons are held in-between the clamp plates and these clamp plates are tighte
how do I find the design strength of concrete?
derivation for above topic
How can we reduced frictional losses Frictional losses can be reduced by several methods, such as : (a) Over-tensioning the tendons by an amount equal to the maximum frictio
find out the interior angleS with diagrame LINE AB, BC, CD, DE, EA Fore bearing 60''30" , 122'' , 46'' , 205''30" , 300''
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd