Moisture-density relationship, Civil Engineering

Assignment Help:

Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Shape and soundness test - testing of aggregates, Shape and Soundness Test ...

Shape and Soundness Test - Testing of aggregates: Shape For providing a good interlock and strength, the aggregates should be cubical in shape. Elongated and flaky pa

Distomat., write a note on distomat

write a note on distomat

Direct levelling, to find height difference between two or more points in d...

to find height difference between two or more points in different conditions

Loss of prestress due to elastic shortening of concrete, Loss of Prestress ...

Loss of Prestress due to Elastic Shortening of Concrete Due to elastic shortening of  concrete, tendons are able to reduce their stretched length to the same extent upto which

LEED, Need this assignment due in 10 hours

Need this assignment due in 10 hours

Water bound macadam, Water Bound Macadam: Water Bound Macadam (WBM) i...

Water Bound Macadam: Water Bound Macadam (WBM) is a dense and compact course of a road pavement composed of stone aggregates held together by a film consisting of gravel or s

Explain terzaghi theory of bearing capacity, a) Explain Terzaghi's theory o...

a) Explain Terzaghi's theory of bearing capacity of shallow strip foundations. Determine the three bearing capacity factors and give their values for  Φ  = 0' case. (b) Descreib

Frames, how to analyse a frame

how to analyse a frame

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd