Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Cement, Why we mixm pozzolona in cement

Why we mixm pozzolona in cement

Materials that provide a path to the magnetic flux are , Materials that pro...

Materials that provide a path to the magnetic flux are? Answer: These are magnetic materials

Shape factor, For a solid circular shaft transmitting torque, the shape fac...

For a solid circular shaft transmitting torque, the shape factor is

State the coulomb earth pressure theory, A masonry wall with vertical back ...

A masonry wall with vertical back has a backfill 5 m behind it. The ground level is horizontal at the top and the ground water table is at ground level. Measured the horizontal pre

#title.cement factor, Aplease provide tables for each design mix and also t...

Aplease provide tables for each design mix and also the, high early strengh.l thanks

WBM Road, if the WBM Road is constructed with 80mm , 40mm metal what will b...

if the WBM Road is constructed with 80mm , 40mm metal what will be the depreciation factor per year, how much thickness of the layer will be reduced per year due to trafic and rai

What do you mean by M.A.S. accounts, Q. What do you mean by M A S Accounts?...

Q. What do you mean by M A S Accounts? This stands for material at site account. This is a suspense head of account that is maintained to watch actual consumption of materials

Hydraulics, A tank with vertical sides contain 3m of water in the bottom, o...

A tank with vertical sides contain 3m of water in the bottom, overlain by 4m of oil with no intermixing. Draw pressure diagram due to the oil and water on one of the tank sides and

Backward and forward curved vanes in pumps, Backward curved vanes vs. forwa...

Backward curved vanes vs. forward curved vanes in pumps  Power of a pump is related to discharge as follows: Power = k 1 Q + (k 2 Q 2 / tan A) Where K 1 and K 2 are

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd