Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Concrete pavement - thickness, Concrete Pavement: Thickness T...

Concrete Pavement: Thickness The thickness of concrete pavements is determined from the stresses induced due to loads and temperature. The thickness adopted is genera

Calculate the amount of waste, Calculate the Amount of Waste A municipa...

Calculate the Amount of Waste A municipal solid waste department plans to separate a portion of the ferrous metal, newsprint and cardboard from its MSW waste stream. The depart

leveling, what are the diff.types of levels used in levlin

what are the diff.types of levels used in levling

Survey, how to draw longitudinal profile

how to draw longitudinal profile

Construction - concrete pavement, Construction: Construction is usual...

Construction: Construction is usually done by one of the three methods: (a) Manual method, providing steel or wooden forms, pouring concrete and compacting by means of nee

Foundation, classification of foundation

classification of foundation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd