Moisture-density relationship, Civil Engineering

Assignment Help:

Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Shear force and bending moment, how to draw shear force and bending moment ...

how to draw shear force and bending moment from load intensity

State about the pre-tensioned concrete, State about the pre-tensioned concr...

State about the pre-tensioned concrete In pre-tensioned concrete, the tendon stresses are transferred  to concrete by  virtue of bond  of concrete to the  surface of steel tend

Compute the stresses at top and bottom fibres, Compute the stresses at top ...

Compute the stresses at top and bottom fibres in a simply supported pre-stressed concrete beam with a rectangular cross section, 200 mm wide and 400 mm deep at sections A-A, B-B an

Dynamical method of earthquake force analysis, Earthquake force analysis me...

Earthquake force analysis method Dynamical method In contrast with the static loading, dynamical analysis method is discussed. In this method, structure reflections at any poin

Planning stage of the audit, Materiality is used only at the planning stage...

Materiality is used only at the planning stage of the audit. Ans: I disagree with the statement because: When planning the audit, the auditor considers what would make the fi

Estimate the net present worth - construction management, Three alternative...

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection wi

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Average heating season outside temperature, Produce a manual determination ...

Produce a manual determination to determine the instantaneous rate of heat loss (kW) through one part of the fabric (eg roof, glazed area, wall) based on an internal building desig

Measure the safe load on the pile, A wood pile of 10 m length is driven by ...

A wood pile of 10 m length is driven by a 1500 kg drop hammer falling by 3 m to a final set equal to 1.25 cm per blow. Measure the safe load on the pile using the Engineering Ne

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd