Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Importance of tendons in post-tensioned members, Importance of Tendons in p...

Importance of Tendons in post-tensioned members Tendons in post-tensioned members are subjected to different amounts of stresses (among themselves) due to following reasons.

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Doors, About Doors,windows&vendilators

About Doors,windows&vendilators

A concrete compression machine, Question In a concrete compression test , ...

Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in

Determine the statements about unit area or borrow pit, Determine the State...

Determine the Statements about Unit Area or Borrow Pit? Ans: I.  Sometimes called Average Depth II. Works well for volumes for building sites and surface mines III. Needs

Define limitations of radiography - inspection of bridge, Define Limitation...

Define Limitations of Radiography - Underwater Inspection of Bridge? i. Radiography is a costly and time consuming method, which re- quires extensive safety measures to be adop

Rivet, cold driven rivet

cold driven rivet

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd