Moisture-Density Relationship:
Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.
For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.
How desalination of water can be acheived by reverse osmosis and electrodialysis process?
With the aid of Mohr's circle diagram describe what means by active and passive Rankine states is in a cohesionless soil with a horizontal surface. As obtain an expression for the
Uses of Bricks In the following civil works Bricks are used: a. in building blocks. b. For lining of ovens, chimneys and furnaces. c. As aggregates in providing water
types of cement
The survey has identified the beginning and ending points along an urban arterial highway that require new sidewalks. The first station is located at 5+88 and the second station is
Question What is main mechanism of formation of soil plugs in marine driven steel piles with reinforced concrete infill? Answer Throughout initial driving process, ope
what do you mean by buttering mixers
aaa
Cut and Fill Calculation Using Cross Section Method
Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd