Moisture-density relationship, Civil Engineering

Assignment Help:

Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Define the phreatic line and phreatic zone, Define the Phreatic Line and Ph...

Define the Phreatic Line and Phreatic Zone Phreatic Line: In an unconfined aquifer, it represents the water table.   Phreatic Zone: In an unconfined aquifer, it is located b

Determine the coordinate for point r, For the project work points (x,y) sho...

For the project work points (x,y) shown in the figure the bearing of point R is due West. The coordinate for point R is most nearly:    Solution: Determine the length o

Determine about the statement - failure at cracking load, Determine about t...

Determine about the statement - Failure at Cracking Load This brittle mode of failure is likely to occur in those pre-stressed elements that are concentrically pre-stressed wit

Moment of Inertia of a T Beam, Calculate the moment of inertia and section ...

Calculate the moment of inertia and section modulus (top and bottom of the beam) about the z-axis of the beam cross section of Fig.

Land Surveying, What is the difference between accuracy and precision.

What is the difference between accuracy and precision.

Biological wastewater engineering, a. We put a lot of time and effort into ...

a. We put a lot of time and effort into cultivating our activated sludge microbial community. So why do we waste sludge out of it? b. A wastewater discharges to Puget sound, a mari

Define Statically indeterminate structures, Statically indeterminate struct...

Statically indeterminate structures a. Fall into two categories: 1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected to temperature/forc

Equipments required for under water inspection of bridge, Define Equipments...

Define Equipments and tools required for under water Inspection of Bridge? Since the underwater inspection of stone masonry substructures involve only a cursory inspection of t

What is rail lubricators, Q. What is Rail Lubricators? 1. P & M type of...

Q. What is Rail Lubricators? 1. P & M type of lubricators - These lubricators can be used for lubrication of FF rails as well as BH rails. 2. Elgi grease pump - Elgi Bucket

Explain the term -tendon splices, Tendon splices Tendon splices are us...

Tendon splices Tendon splices are used to join tendons when continuous prestressed concrete , members require long tendons to achieve continuity. Several types of tendon splic

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd