Moisture-Density Relationship:

Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.

For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.


Related Discussions:- Moisture-density relationship

Surveying., with a neat well labelled, explain reciprocal ranging in survey...

with a neat well labelled, explain reciprocal ranging in surveying.

Max. moment at cantilever, max. moment at cantilever in up or down of suppo...

max. moment at cantilever in up or down of support or free of end

Surving, describe the methods of reducing the levels,and their relative adv...

describe the methods of reducing the levels,and their relative advantages and disadvantages.

Paints, painting wood work and steel

painting wood work and steel

Underwater problems in bridge construction, Q. Underwater problems in bridg...

Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding

Influence Line for shear at Support, I have to draw the IL for the shear at...

I have to draw the IL for the shear at a roller support and am not sure how it should look

Explain equations for a triangular (v-notch weir), Explain Equations for a ...

Explain Equations for a triangular (V-notch weir) Used for small flow rates. C 2 is a coefficient which varies from 0.58 to 0.61 depending upon the notch angle.  Q = C

Estimate the size estimating the rcc structures, PART - A 1.  Can you e...

PART - A 1.  Can you enumerate the benefits of individual wall method of estimation? 2.  Estimate the single room of size  3m x 4m x height 3m  using individual wall method?

State the procedure of prestressing, State the procedure of prestressing ...

State the procedure of prestressing When these wires cool down, concrete is poured in the moulds in which these tendons are provided in a stretched condition. Using this proces

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd