Moisture-Density Relationship:
Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-known is the Proctor test, prescribed by IS : 2720-Part VII. This consists of compacting the soil in three layers in a mould 100 cm3 volume, with a rammer 2.6 Kg dropped from a height of 31 cm, giving 25 blows on each layer. The Proctor density so derived is used for low volume roads such as Rural Roads. For high volume highways, a heavy compaction is prescribed. The test known as modified AASHTO compaction that (IS : 2720-Part VIII) uses a heavier rammer 4.5 Kg weight, dropped from a height of 45.7 cm, the soil being compacted in 5 layers, each layer receiving 25 blows.
For controlling the density achieved in the field, a core is cut and its volume measured by pouring sand (sand replacement method). Knowing the weight of the core removed and its volume, the density is calculated. It is customary to specify 95 per cent of the laboratory MDD (modified AASHTO compaction) for embankment and 97 per cent for the subgrade for highways. For low volume Rural Roads, it is customary to specify 97 per cent of the laboratory MDD (Proctor's test) for embankment and 100 per cent for the subgrade.
Classification of the damage according to the type of structures The level of damage in spatial trusses has also been classified into three different levels based on th
dek type bridge
how to calculate the specific gravity and water absorption of coarse aggregate
Determine the Limit State of Serviceability Cracking Cracking of concrete should not affect the appearance or durability of the structure. The criteria of limit state of cracki
What role does modulus of elasticity play in the pavement layer arrangement
Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru
Define Permissible Bearing Pressure on poly tetra fluoro ethylene? For the purpose of design, it is important to lay down permissible bearing pressure on PTFE sliding surfaces.
What is cofferdams
Topographical Survey and Preparation of Drawings: Topographical Survey for a road project consists of three sequential stages: (a) Reconnaissance Survey, including a study
flow chart for wet process
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd