Q. Method of construction of a bored cast-in-situ concrete pile?
Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole and is driven with the help of a bailer. Further boring below this casing is carried out by chiselling and the side walls are kept stable by circulating bentonite slurry inside the bore hole. The Bentonite clay used in the operation should conform to provisions made in IS : 2911 -Part -1, section -2. After reaching the founding level, the chisel is removed, the bore hole flushed and the reinforcement cage lowered into the hole and held in position by tack welding it to the support bars at the top of the casing.
After this the concreting is carried out by using a "tremie" .The concreting is continued till a good quality concrete is seen at the top of the bore hole. The concrete used is a high slump mix (not leaner than M 20 grade ). Cast-in-situ piles in which the steel shell is left in the ground ensures the quality of concrete and offers corrosion protection in soils containing chlorides and sulphates.
Question What are main dissimilarities in function between rock anchors and rock sockets ? Answer Rock anchors are used first and foremost for resisting uplift forc
I have a writing that needs to be corrected
Define Physical deterioration - underwater inspection of bridges Typical defects include: - Scaling - Cracking - Spalling - Disintegration - Abrasion
Maximum shear stress: The state of stress at a critical point of a strained solid is given by σ x = 70 kN/mm 2 , σ y = - 50 kN/mm 2 and τ xy = 45 kN/mm 2 . If the strength
Compare the probabilities: Use the central limit theorem to compute P (¦ X - μ ¦ ≥ k), k = 1, 2,3,4,5 where X and μ are as defined in Example. Compare the probabilities with t
A sand deposit of 12 m thick overlies a clay layer. The water table is 3 m below the ground surface. In a field permeability pump-out test, the water is pumped out at a rate of 540
CASTE DISCRIMANIMATION
Facilities that discharge wastewater to a publicly owned treatment works? Facilities that discharge wastewater to a POTW (publicly owned treatment works) are known as subject t
discussion of each bitumen test, its significance and importance in understanding and working with bitumen
i need journals or articles of forensic structural engineering
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd