Measuring Kanban

 Two commonly cited methods of measuring the performance of a manufacturing process are flow through time and work in progress inventory levels.

Flow through time is takes once unit to pass through the entire process from start to finish ( on average) . in the kanban system both of these measures are at least partially dependent upon lot sizes.

For example if a kanban system uses 25 workstations and a lot size of 54th the average WIP will be near 100 units. If the cycle time for a balanced load is say two minutes per item ( using the lot size of 4 ) . flow through time will be close to 200 minutes (allowing for some variation) : one unit of product will flow through the system in 200 minutes.


Related Discussions:- Measuring kanban

Business communication, How communication helps in the operator of business...

How communication helps in the operator of business? I don''t solve the question perfectly please give some solution

Explain relationship development theories, Question: i) Recall a time w...

Question: i) Recall a time when you have been the target of rumours or gossip. How might these influence the development of a friendship (whether the gossip is spread by the pe

Illustration based on business opening hours, Business opening hours a...

Business opening hours a) Opportunity cost refers to the cost of the next best alternative that is foregone in a decision. In this case, it refers to the loss income by not op

What are the main selection criteria for erp software?, Question 1 Warigon...

Question 1 Warigon is a retail company and they want to automate the payment system. Take up that you are the design engineer of that company. What are the aspects that you would

Maintanace, as an enterpreneur ,if given 50000 what business would you do?

as an enterpreneur ,if given 50000 what business would you do?

Effective management of quality, QUESTION 1 Failing to plan is planning...

QUESTION 1 Failing to plan is planning to fail. (a) Describe four types of plans that can be designed for an effective management of quality. (b) For planning to be effec

Explain the components of the specific business environment, Question: ...

Question: (a) Frederick Taylor observed that workers worked below their optimum level (soldiering). He thus devised systematic methods based on a set of principles. These princ

Marketing interface, mention 5 measures that will make a dis pleased custom...

mention 5 measures that will make a dis pleased customer patronize the school canteen

How is market mix illustrated by p variables of marketing, How is the marke...

How is the market mix illustrated by the P variables of marketing? The given figure demonstrates the market mix, additionally sub divided as: The marketing mix is the centra

Briefly discuss how management theory evolved, QUESTION Great feats of ...

QUESTION Great feats of human achievement such as the Egyptian pyramids, the Great Wall of China, the Colosseum in Rome and the Taj Mahal in India all bear testimony to skilled

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd