Measuring Kanban

 Two commonly cited methods of measuring the performance of a manufacturing process are flow through time and work in progress inventory levels.

Flow through time is takes once unit to pass through the entire process from start to finish ( on average) . in the kanban system both of these measures are at least partially dependent upon lot sizes.

For example if a kanban system uses 25 workstations and a lot size of 54th the average WIP will be near 100 units. If the cycle time for a balanced load is say two minutes per item ( using the lot size of 4 ) . flow through time will be close to 200 minutes (allowing for some variation) : one unit of product will flow through the system in 200 minutes.


Related Discussions:- Measuring kanban

Explain about the technical skills of a successful manager, Explain about t...

Explain about the technical skills of a successful manager. Technical skill: Technical skill considers to the proficiency into handling processes, techniques and methods

Send the mail to all the staffs, QUESTION Nathan is the floor Manager a...

QUESTION Nathan is the floor Manager at Bell Enterprise. Lately he has been concerned with staffs not respecting the lunch hours. He has warned them but with no avail. He then

Costco Business Structure, What is Costco''s vertical and horizontal busine...

What is Costco''s vertical and horizontal business structure?

BIG DATA, You are required to write a report on how Big Data can be used in...

You are required to write a report on how Big Data can be used in Decision Support and Business Intelligence (DS&BI). You are required to select/ research a use case for Big Data.

Define what is meant by value analysis, "Only projects with a positive NPV ...

"Only projects with a positive NPV should be considered and projects with a negative NPV should be discarded". Briefly discuss this statement. Define what is meant by 'Value A

Characteristics of business process reengineering, The major characteristic...

The major characteristics are: 1. Several jobs are combine into  one. 2. Employees make decisions ( empowerment of  employees.) decision making  becomes  part of  the job.

Value chain analysis , I want to make a report on Value chain analysis for ...

I want to make a report on Value chain analysis for Recycle used cloth business

How will an investor earn risk less arbitrage, Question: 1. What factor...

Question: 1. What factors might an individual investor take into account in determining her or his investment policy? 2. Distinguish between fundamental and technical securi

Critical, MHow in a free society like the U.S., can a small group of people...

MHow in a free society like the U.S., can a small group of people continually control so much of the wealthiness 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd