Question

What is meaning of driving succession of driven piles?


Answer

In Basement construction, if piles are driven from centre to perimeter, there is a propensity of soils to move away from. Such lateral group of soil might cause break to nearby structures and utilities.

Though, if piles are driven from outside perimeter inwards, there are slight soil lateral movements. These results in a well-compacted core with an excess pore water pressure built up to resist loading of piles. So, shorter pile lengths than original designed ones might result. Still, some time after pile driving operation, excess pore water stress is dissipated and shorter driven piles might not be able to take up the original design loads. In this state redriving is required to drive piles to deeper depths after indulgence of excess pore water pressure.

 


Related Discussions:- Meaning of driving succession of driven piles

Define the vapor pressure, Define the Vapor Pressure The partial pressu...

Define the Vapor Pressure The partial pressure exerted at the surface of a liquid at the liquid/vapor interface. The liquid molecules are released into the vapor phase when the

Aggragates, methods of extracting aggregates

methods of extracting aggregates

What is the role of sunfilter in building, QUESTION (a) Using an illu...

QUESTION (a) Using an illustration, describe what happens to sunrays when it passes through the atmosphere to reach the ground. (b) What is the role of a sunscreen/sunfil

Consolidated undrained or consolidated drained analysis, Question In de...

Question In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis? Answer Effec

Distinguish among active and passive earth pressure, Distinguish among  'ac...

Distinguish among  'active' and 'passive' earth pressure. Describe clearly Rebhann's graphical construction method to evaluate the earth pressure on a retaining wall. What are t

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Define radiography - underwater inspection of bridge, Define Radiography - ...

Define Radiography - Underwater Inspection of Bridge? Radiographic non-destructive examination of components is based on the phenomenon that materials absorb radiation energy a

Define the cracking - underwater inspection of bridge, Define the Cracking ...

Define the Cracking - underwater inspection of bridge? A crack is a linear fracture in concrete. There can be several types of cracks starting from surface and going into the c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd