What is meaning of driving succession of driven piles?


Answer

In Basement construction, if piles are driven from centre to perimeter, there is a propensity of soils to move away from. Such lateral group of soil might cause break to nearby structures and utilities.

Though, if piles are driven from outside perimeter inwards, there are slight soil lateral movements. These results in a well-compacted core with an excess pore water pressure built up to resist loading of piles. So, shorter pile lengths than original designed ones might result. Still, some time after pile driving operation, excess pore water stress is dissipated and shorter driven piles might not be able to take up the original design loads. In this state redriving is required to drive piles to deeper depths after indulgence of excess pore water pressure.

 


Related Discussions:- Meaning of driving succession of driven piles

Normal approximation to compute the probability, Normal approximation to co...

Normal approximation to compute the probability: A lot contains 100 articles of which 10 are defective. The lot is rejected if a random sample of 10 articles drawn from the lo

Ironmongery, fabrication methods of ironmongery

fabrication methods of ironmongery

Determine the coordinate for point r, For the project work points (x,y) sho...

For the project work points (x,y) shown in the figure the bearing of point R is due West. The coordinate for point R is most nearly:    Solution: Determine the length o

Elastic curve, elastic curve of a simply supported beam with triangular loa...

elastic curve of a simply supported beam with triangular load

Seasoning of timber, Seasoning of Timber It is a process by which moist...

Seasoning of Timber It is a process by which moisture content in a freshly cut tree is reduced to a appropriate level. The durability of timber is increased by doing so. The se

Doors, About Doors,windows&vendilators

About Doors,windows&vendilators

Physics, A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinat...

A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinate system as shown. Another point charge q1 = 4.0 µC is is initially located at point P, a distance d1 = 6.0 cm fro

Jacking face for pipe-jacking, Ground settlement occurs ahead or behind the...

Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti

Methods of contouring by grid points, the elevations of grid points for an ...

the elevations of grid points for an area as follows: 1 2 3 4 5 6 7 8 F 690 709 726 732 735 740 743 747 E 696 715 729 736 740 737 739 740 D 702 723 733 742 737 737 745 747 C 707 72

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd