What do you understand by “line balancing”? What happens if balance doesn’t exist?

Related Discussions:- mb0044

How to find the order quantity, The supplier is reliable and maintains a co...

The supplier is reliable and maintains a constant lead time of 5 days. The cost of placing an order is $10 and the cost of holding inventory is $0.50 per unit per year. There are n

What does acknowledging sources involve, What does acknowledging sources in...

What does acknowledging sources involve? Sources of information and the ideas of others that you use in your assignments, research and class activities may include books, journa

Explain widespread problem in industry, In light of today's high standard o...

In light of today's high standard of living, why do you think that employee theft is such a widespread problem in industry?

Describe international compensation, Existing salary for managers is 45,000...

Existing salary for managers is 45,000 euros (58,567 us dollars) plus bonuses. Average salary for managers in range is 60,000 euros (78,090), no bonuses. Recommendations must inclu

Explain appropriate technique to develop a forecast, Air travel on Mountain...

Air travel on Mountain Airlines for the past 18 weeks was: Week Passengers Week Passengers 1 406 10 440 2 410 11 446 3 420 12 451 4 415 13 455 5 412 14 464 6 420 15 466 7 424 16 47

Design of work systems, A worker machine operation was found to involve 3.5...

A worker machine operation was found to involve 3.5 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The workers time averaged 2.3 minutes per cycle

Determine the optimal order quantity as well the annual cost, The home good...

The home goods department of a large department store sells 175 units per month of a certain large bath towel. The unit cost of a towel to the store is $2.50 and the cost of placin

Explain self-awareness and empathy, The perceptual distortion of projection...

The perceptual distortion of projection can be controlled thru a high degree of/ 1.ethical behaviour/2.cognitive consistency/3.emotional discernment/4. self-awareness and empathy/5

Assume the length of critical path in a project, Suppose the length of crit...

Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing

Dolly

2/12/2013 7:13:31 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd