MATLAB support for fault analysis in transmission lines, Electrical Engineering

Assignment Help:
The devices in power system shown in Figure 2 have the following ratings:

G1 : 100 MVA, 13.8 kV grounded Y, X” = 0.15 pu, X2 = 0.015 pu Xo = 0.05 pu
G2 : 50 MVA, 20.0 kV grounded Y, X” = 0.15 pu, X2 = 0.015 pu Xo = 0.05 pu
T1 : 100 MVA, 13.8/138 kV (both grounded), X1 = 0.08 pu, X2 = 0.08 pu Xo = 0.08 pu
T2 : 50 MVA, 20.0/138 kV, ?-Y grounded Y, X1 = 0.08 pu, X2 = 0.08 pu Xo = 0.08 pu
L1 : 100 MVA, 138 kV grounded X1 = 19 ?, X2 = 19 ?, Xo = 50 ?,


Figure 2

Assume that all resistances in the power system can be neglected. The system base apparent power is ____ (to be specified by your lecturer)MVA, and the base line voltage is 13.8 kV at bus 1. Assume that the voltage at bus 1 is 13.8 kV and that the power system is initially unloaded.

2. Use Matlab to:

a. Find the sub transient per-phase equivalent circuits of this power system for positive-, negative- and zero-sequence component.

b. Find the subtransient fault current at the fault found at the location indicated by X for:



i) A symmetrical three-phase fault
ii) A single line-to-ground fault
iii) A line-to-line fault
iv) A double line-to-ground fault

(A student will solving for the transient fault line current for two (2) types of fault to be specified by the lecturer).

Related Discussions:- MATLAB support for fault analysis in transmission lines

Common source amplifier, Common Source Amplifier A common-source ampl...

Common Source Amplifier A common-source amplifier is one of three basic single-stage field-effect transistor abbreviated as FET amplifier topologies, commonly used as a volta

logical and with accumulator instruction , ANA  Logical AND with Accumula...

ANA  Logical AND with Accumulator Instruction This  instruction is used to logically AND the accumulator  of any register or memory location  with the  accumulator and the r

What are the various tones used in stronger telephony, Q. What are the vari...

Q. What are the various tones used in stronger telephony? When called party line is obtained, exchange control equipment transmits out the ringing current to telephone set of t

Performance mapping & implementation plan - power supply, Importance Perfor...

Importance Performance Mapping & Implementation Plan - Power Supply Another data presentation device in which several managers find appealing is the significance-performance m

Define serial in - serial out shift registers, Define Serial In - Serial Ou...

Define Serial In - Serial Out Shift Registers? An essential four-bit shift register can be constructed using four D flip-flops. The register is the first cleared forcing all fo

Determine the voltage regulation at full load, A three-phase, wye-connected...

A three-phase, wye-connected, cylindrical-rotor synchronous generator rated at 10 kVA and 230  V has a synchronous reactance of 1.5per phase and an armature resistance of 0.5  pe

Binary coded decimal addition, Q. Binary Coded Decimal Addition Now as ...

Q. Binary Coded Decimal Addition Now as in conventional decimal addition, Binary Coded Decimal addition is performed one decimal digit at a time. What happens when the sum g

When both mt2 and gate are negative, When both MT 2 and Gate  are Negativ...

When both MT 2 and Gate  are Negative In this case N 3   works as a remote gate. Current  flows form layer P 2 to layer  N 3 junction N 1 P 1 is reverse biased  and it  br

Design a mealy system, Design a Mealy system whose output is 1 iff there ha...

Design a Mealy system whose output is 1 iff there have been exactly two 1's followed by a 0 and then a 1. (a) Assume overlapping is allowed (b) Assume overlapping is not

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd