Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Coated electrodes and their classifications, COATED ELECTRODES AND THEIR CL...

COATED ELECTRODES AND THEIR CLASSIFICATIONS Welding technology has changed tremendously over the past decades. Its application is found in all sectors of industries, smaller or l

Torsion equation for solid circular shaft, Prove the torsion equation T/J=τ...

Prove the torsion equation T/J=τ/R=C. θ/L for the solid circular shaft. State the various assumptions used on above said equation.

Solve the equation by newton raphson method, Calculate root of equation 3x ...

Calculate root of equation 3x = 100 cosx + 1 by Newton Raphson method correct to three decimal places Calculate root of equation xe x = cosx by Secant method correct to three d

Determine elongation because of self weight of conical bar, Determine elong...

Determine elongation because of self weight of conical bar: Sol.: Consider conical bar ABC of length L with the diameter d fixed rigidly at AB . Let attention be focuse

Symmetric central force, Symmetric Central Force A central force is sph...

Symmetric Central Force A central force is spherically if the magnitude of the force does not depend on the direction (angles  θ , or  Ø ) of the particle but only on distance

What is polymers, Q. What is polymers? The term "polymer" is derived fr...

Q. What is polymers? The term "polymer" is derived from the two Greek words: poly, meaning "many", and meros meaning "parts" or "units". Thus polymers are composed of a large n

Stroke and clearance volume - thermodynamics, Stroke and Clearance Volume: ...

Stroke and Clearance Volume: Stroke The distance traveled by piston from the topmost positions of it (also called Top dead centre TDC ), to its bottom most position (or

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd