Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Governors, friction characteristics

friction characteristics

Check ferrite content of austenitic stainless steel weld, Q. Check ferrite ...

Q. Check ferrite content of austenitic stainless steel weld? Check the ferrite content of each austenitic stainless steel weld, including overlay welds, in the as-welded condit

Pumps, three indications of centrifugal pump cavitating

three indications of centrifugal pump cavitating

Explain objectives of radial drill machine, Explain Objectives of Radial dr...

Explain Objectives of Radial drill machine There are many objectives such like, 1.   With the help of angle drill machine, an angle hole can be produced at any angle.  2.

Renewable Energy, I am attending Thermodynamics class at the university. Th...

I am attending Thermodynamics class at the university. The professor asked me to write a research on Renewable Energy: Solar Power. The report should be of 10 pages and at least 10

Matlab program, write a matlab program to generate shear force diagram

write a matlab program to generate shear force diagram

Calculate transmitted force, A machine having a mass of 100 Kg and supporte...

A machine having a mass of 100 Kg and supported on springs of total stiffness 7.84 x 105 n/m has an unbalanced rotating element which results in a disturbing force of 400 N at a sp

Determine in detail about the depth of foundation, Location with Respect to...

Location with Respect to Depth The depth below ground level at which the bottom of a foundation structure is located depends on number of factors, the most important of which

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd