Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

#totto cycleitle.., for an otto cycle, compression ratio=8.5:1,air inlet=15...

for an otto cycle, compression ratio=8.5:1,air inlet=15degree celsius and pressure=101.3kpa, maximum cycle temperature= 1800degree celsius, what is temperature after compression,te

Site selection - planning a new airport, Site Selection: The followi...

Site Selection: The following consideration govern the choice of site for an airport : (a)        The area served must be able to generate and attract the estimated passen

Wilson hartnell governor, how to design and fabricate wilson hartnell gover...

how to design and fabricate wilson hartnell governor?

Two stroke engine - thermodynamics, T w o Stroke Engine In the two st...

T w o Stroke Engine In the two stroke engine, instead of valves ports are given, these are opened and closed by moving piston. Through inlet port, the mixture of air and fuel

Calculate the outer diameter of hollow shaft, A solid shaft of diameter d i...

A solid shaft of diameter d is taken in power transmission. Because of modification of existing transmission system, it is needed to replace the solid shaft by a hollow shaft of th

Cell covers--battery components , Cell Covers: Each cell is covered from ...

Cell Covers: Each cell is covered from the top of the cell covers and the terminals projected from the cell covers. The terminals are arranged alternatively in a line.

Scheduling and sequencing, Scheduling and Sequencing: This unit begin ...

Scheduling and Sequencing: This unit begin with the basic concept and the role of scheduling in industry. Several job- sequencing rules to address the manufacturing process ar

State the postulates of special theory of relativity, State the postulates ...

State the postulates of special theory of relativity and deduce from them the Lorentz transformations. Define an inertial frame of reference and derive the Lorentz transformatio

Program evaluation and review techniques, Program Evaluation and Review Tec...

Program Evaluation and Review Techniques: The Rola and Cola Corporation is a professional II nursing home aspiring to become I nursing home. It desires to provide the ultimate

Logistics - inbound and outbound, Logistics - Inbound and Outbound: Lo...

Logistics - Inbound and Outbound: Logistics plays a vital role in designing and shaping of SCM in a firm. Without an effective logistics system the effectiveness of the firms

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd