Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

What are preheat and interpass temperature, Q. What are Preheat and interpa...

Q. What are Preheat and interpass temperature? Preheat and interpass temperatures shall be in accordance with the applicable codes. Materials that require preheat for welding

Express the compression force of hydraulic cylinder, Express the compressio...

Express the compression force C in the hydraulic cylinder of the car hoist in terms of the angle Θ, see Fig Q3. The mass of the hoist is negligible compared with the mass of the ve

Describe poissons ratio, (i) Describe Poisson's Ratio. (ii) A circular r...

(i) Describe Poisson's Ratio. (ii) A circular rod of 100mm diameter and 500 mm length is subjected to a tensile force of 1000 KN. Calculate the modulus of bulk modulus, rigidity

Illustrate the process of insulation on pipe, Q. Illustrate the process of ...

Q. Illustrate the process of insulation on pipe? Factory fabricated sectional pipe insulation shall be applied in staggered joint construction and secured with wire loops or ba

Key words used in road under special conditions, Keywords used in appropria...

Keywords used in appropriate technology: Hill Roads : Roads in hilly and mountainous terrain. Landslides : The slippage of mass of hill face. Retaining Walls : Str

Welding, #what is porosity in welding is this different from pin hole

#what is porosity in welding is this different from pin hole

Dynamics, a motorcycle is used to stunt show to go over a valley . if the i...

a motorcycle is used to stunt show to go over a valley . if the initial speed at A is u m/s, determine a. the minimum U so that the motorcycle reaches the bank at B. b. the veloc

What is two way punching shear, What is Two Way Punching Shear? Two Way...

What is Two Way Punching Shear? Two Way Punching Shear In columns, generally the tendency of the column is to punch through the footing.  This also is to be considered in de

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd