Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Fire dampers - air-conditioning guidelines, Clearly indicate fire dampers o...

Clearly indicate fire dampers on ducts penetrating fire rated partitions, equipment rooms, duct shafts, ceiling outlets, etc. Detail fire dampers on drawings if required. For

How will you measure the engine oil level?, (a) Why do we change the engine...

(a) Why do we change the engine oil at periodic intervals? (b) What are the recommended instructions to change engine oil? (c) How will you measure the engine oil level?

Calculating the number of kanban card sets, Calculating the number of kanba...

Calculating the number of kanban card sets: A hospital desires to set up a Kanban system to manage its supply of blood with the regional blood bank. The regional blood bank tr

Determine the velocity, Question The three freight cars are rolling alo...

Question The three freight cars are rolling along the horizontal track with the velocities shown in the Figure. After the impacts occur the three cars become coupled together a

What will be the alteration of pressure, A copper tube 1.2 m long, has 80mm...

A copper tube 1.2 m long, has 80mm internal diameter and 2 mm wall thickness. It has closed ends, and is filled with water under pressure. What will be the alteration of pressure i

Determine the rate of heat removal - mechanics, Determine the rate of heat ...

Determine the rate of heat removal: Carbon dioxide passing through heat exchanger at rate of 100kg/hr is cooled down from  800 0 C to 50 0 C . Write down the steady flo

Describe the extrution process, Q. Describe the extrution process? The ...

Q. Describe the extrution process? The extrusion process, in many cases produces material in an intermediate form for subsequent reprocessing to its final component form. The p

Piping, difference between pipe and tube

difference between pipe and tube

Derive the stability condition of a four wheel vehicle, Derive the stabilit...

Derive the stability condition of a Four wheel Vehicle AND Two wheel Vehicle moving in a curved Path? Explain with working, measurement and construction of brake power by Rope b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd