Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Can you illustrate sea coal, Q. Can you illustrate Sea Coal? Sea coal o...

Q. Can you illustrate Sea Coal? Sea coal or coal dust is finely ground soft coal (pulverized coal). It is added to moulding sand used to make ferrous castings. It tends to obta

Equipment for resistance welding, EQUIPMENT FOR RESISTANCE WELDING The ...

EQUIPMENT FOR RESISTANCE WELDING The equipment for resistance welding is different from that for arc welding for the following reasons: Resistance welding machines are complica

Electro gas welding, ELECTRO GAS WELDING This process is an extension ...

ELECTRO GAS WELDING This process is an extension of MIG  I MAG welding, designed for single pass vertical welding of steel plates in the thickness range of 10 to 38 mm. The tw

Calculate the shear flow in wall - flange areas, Calculate the shear flow i...

Calculate the shear flow in each wall of the fuselage section below. The flange areas are 1 sq in and the web thicknesses are 0.05 in. The material has modulus E = 10 mpsi and G =

Process planning, we have to design crane we did already with calculation r...

we have to design crane we did already with calculation remaining is process planning

Material Science, What is tetra & octahedral voids & how are they formed ?

What is tetra & octahedral voids & how are they formed ?

Find the machine fraction for machine operation, 1.Two machining operations...

1.Two machining operations, A (3 minutes per part) and B (10 minutes per part), are performed sequentially to manufacture a part. Machines A and B produce 5% and 6% defective items

Indicator diagram and indicated power - thermodynamics, Indicator diagram a...

Indicator diagram and indicated power: An indicated diagram is graph between pressure and volume. The former being taken on the vertical axis and latter on the horizontal axis

Find out force on each member - truss, Find out force on each member - Trus...

Find out force on each member - Truss: A truss is as shown in the figure given below. Find out force on each member and the nature of it.  Sol.: First we calculate sup

Determine the brake power of an engine, Determine the Brake power of an Eng...

Determine the Brake power of an Engine which is running at a fixed speed of 300 r.p.m. and carries a rope brake Dynamometer. The Dead weight on the spring balance and engine readin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd