Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine the heat rejection, In an engine working on Diesel cycle inlet pr...

In an engine working on Diesel cycle inlet pressure and tem are 1 bar and 17 o c respectively. Pressure at the end of adiabatic compression is 35 bar. He ratio of expansion i.e. af

Back Rake Angle, Why is back rake angle preferred to be negative for brittl...

Why is back rake angle preferred to be negative for brittle materials?

State about the computer-aided design, State about the Computer-aided desig...

State about the Computer-aided design Computer-aided design (CAD), high-quality character fonts, data plots, and artists' sketches all contain smooth curves and surfaces. The pa

Energy method, A semi circular frame of flexural rigidity EI is built at A ...

A semi circular frame of flexural rigidity EI is built at A and caries a vertical load W at B. calculate the magnitude of the vertical and horizontal deflection at B and hence the

Calculate the reactions at the bottom of the vessel, (a) What are the basic...

(a) What are the basic conditions for a body to be in state of equilibrium? (b) Two steel cylinders of similar diameter are supported in a rectangular vessel. The width of the v

Heat exchangers - air-conditioning guidelines, Q. Heat Exchangers - air-con...

Q. Heat Exchangers - air-conditioning guidelines? Location, size and capacity clearly indicated. Control valves indicated. Space for tube removal, keep space clear of pipes, va

What is hybrid sweep, Hybrid Sweep It combines linear and/or non-linear...

Hybrid Sweep It combines linear and/or non-linear sweep via set operations. In this case, two point sets are swept in two different directions and the two resulting swept volum

Ancillary railway structures, Ancillary Railway Structures: Overhe...

Ancillary Railway Structures: Overhead Transmission Lines When the line is electrified, the electric loco has to pick up the electric current from a cable that runs

Define specific volume (v) of System, Define Specific Volume (v) It is ...

Define Specific Volume (v) It is illustrated as volume occupied by the unit mass of the system. Its unit is m 3 /kg. Certain volume is reciprocal of density. ν = v/m; m 3 /k

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd