Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

What is linear sweep, Linear Sweep In linear sweep, the path is a linea...

Linear Sweep In linear sweep, the path is a linear or circular vector described by a linear, most often parametric. Linear sweep can be divided into translational and rotationa

Equilibrium diagram, what do understand by the term equilibrium diagram

what do understand by the term equilibrium diagram

Theoretical results-conventional priority rules, Theoretical Results I...

Theoretical Results In the particular machine case, several theoretical results are identified or can be derived: (a) If each operation can be scheduled such that everyone

Dislocation, Diff. B/w edge and screw dislocation

Diff. B/w edge and screw dislocation

Find out deflection under the load, Find out Deflection under the load: ...

Find out Deflection under the load: A beam of span 4 m is subject to a point load of 20 kN at 1 m from the left support and a Udl of 10 kN/m over a length of 2 m from the righ

The baseline dimension command, The Baseline Dimension Command You can ...

The Baseline Dimension Command You can use this command to generate a series of dimensions from a single base point. You must already have created the first dimension in the se

Radiative heat transfer, how to find view factor for a cylinder to humanbod...

how to find view factor for a cylinder to humanbody at a distance?

What is squeeze time, Q. What is Squeeze time? It is the time between t...

Q. What is Squeeze time? It is the time between the initial application of the electrode pressure on the work and the initial application of current to make the weld. During th

Illustrate about plant type and process, Q. Illustrate about Plant Type and...

Q. Illustrate about Plant Type and Process? Plant layout is influenced by the type of plant (both the industry and technology utilized) and the kind of process units and associ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd