Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Explain the working of die casting, Q. Explain the working of Die Casting? ...

Q. Explain the working of Die Casting? In the die casting process the, mould used for a casting is permanent called a die casting. it is shown in figure. It is thus quite diffe

Determine maximum fibre stress - beam, Determine Maximum fibre stress: ...

Determine Maximum fibre stress: A beam of rectangular section of 80 mm to 120 mm carries a uniformly distributed load of 40 kN/m over a span of 2 m an axial compressive force

Inspection of flange assembly, Q. Inspection of Flange assembly? Flange...

Q. Inspection of Flange assembly? Flanges shall be clean and free of old gasket fragments, scratches, burrs, pits, etc. if needed, the flange surfaces shall be cleaned with a s

Calculate the significant figure, Do not round intermediate calculations, h...

Do not round intermediate calculations, however for display purposes report intermediate steps rounded to four significant figures. Give your final answer(s) to three significant f

Determine the point of intersection jets, A tank has two identical orifices...

A tank has two identical orifices in one of its vertical sides. The upper orifice is 3m below the water surface and lower one is 5m below the water surface. If the value of Cv for

Thermodynamics, we can use in proove of energy is a propertyof system we ca...

we can use in proove of energy is a propertyof system we can use (E) instead of (dQ-dW)

Nominal strain and true strain, Nominal Strain and True Strain: Nomina...

Nominal Strain and True Strain: Nominal Strain is ratio of change in length per initial length.  Nominal strain =  Change in length / Initial length = Δ L /   L

What is strap footing, What is strap footing? Strap Footing You have...

What is strap footing? Strap Footing You have to use cantilever or strap footings when the proximity of a property line precludes the use of other types for example an isola

Mechanics, what are the angle between two force to make their resultant a m...

what are the angle between two force to make their resultant a minimum and maximum respectively .

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd