Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Find out the wave retarders in tandem, Wave Retarders in Tandem Write th...

Wave Retarders in Tandem Write the Jones matrices for the following retarders: (a) A π/2 wave retarder with the fast axis along the x direction. (b) A π wave retarder with

How to drill 500 sheets paper , How to drill 500 sheets paper ?in 4 mm dia ...

How to drill 500 sheets paper ?in 4 mm dia , holes are same distance as its dia (4mm) in one line.

Determine the stresses in each rod, A rigid bar ABCD is hinged at A and sup...

A rigid bar ABCD is hinged at A and supported by a bronze rod, 2m long, and a steel rod 1m long as shown in figure A load of 80 KN is applied at end B. Determine the stresses in ea

What is the density of plastic, Plastics are the common term for a wide ran...

Plastics are the common term for a wide range of synthetic or semi synthetic polymerization products. There are many dissimilar plastics; all have their own density!

Determine of poissons ratio, a) Show that if E is assumed to be correctly c...

a) Show that if E is assumed to be correctly calculated, an error of 1% in the evaluation of C will involve an error of about 6% in the determine of Poisson's ratio when its correc

Submerged arc welding, Submerged Arc Welding   Single pass filler we...

Submerged Arc Welding   Single pass filler welds upto (8.0 mm) maximum and groove welds made with a single pass or a single pass each side, may be made using an E7os-x elect

Heat treatment of tool steels, Heat Treatment of Tool Steels This trea...

Heat Treatment of Tool Steels This treatment in case of tool steels in a significant step before actually employing the tool. Most properties are attained after heat treatment

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd