Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Stress analysis of components and structures, Consider the expansion loop d...

Consider the expansion loop displayed in the diagram below, which is part of a long pipeline.  The loop is made up of a uniform pipe section and is subjected to a temperature raise

Design requirements, A steel member supported by a tie bar has a load of 15...

A steel member supported by a tie bar has a load of 15 000 lbs on it. If the force on the steel member of 1.2 in 2 cross section is 14,180 lbs and the force on the tie bar of diam

Determine the value of registers, The ARM microprocessor has 32 bit instruc...

The ARM microprocessor has 32 bit instructions and 32 bit registers. Explain why this means that immediate addressing cannot be used to load a register with a 32 bit constant. T

What is fusion bonding, Q. What is Fusion Bonding? Fusion Bonding shall...

Q. What is Fusion Bonding? Fusion Bonding shall refer to the fusion bond coating process which utilizes heat to melt adhere the coating material to the metal surface. Fusion Bo

Virtual work, Explain the principle of virtual work

Explain the principle of virtual work

Determine the number of steel and bronze disks, Choose a wire rope for a ve...

Choose a wire rope for a vertical mine hoist to lift a load of 55 KN from a depth 300 meters. A rope speed of 500 meter/min is to be attained in 10 seconds. A multi -disk clutch

Insulation and heat tracing, • insulation thickness • heat tracing type (gl...

• insulation thickness • heat tracing type (glycol, electric, steam): • controlled or self-limiting • traps • identification • requirements limits

What is the make group of euler operators, The Make Group of Euler Operator...

The Make Group of Euler Operators The Make group consists of four operators for adding some elements into the existing model creating a new one, and a Make-Kill operator for ad

Evaluate resultant of the system - mechanics, Evaluate resultant of the sys...

Evaluate resultant of the system: Q: Figure given below shows two vertical forces and couple of moment 2000 Nm acts on horizontal rod, which is fixed at end A .  Determin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd