Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Longitudinal strain produced - hollow cast iron cylinder, Longitudinal stra...

Longitudinal strain produced - hollow cast iron cylinder: A hollow cast iron cylinder 4 m long, 300 mm is the outer diameter, and thickness of metal 50 mm is subjected to cen

Determine the interface temperature, A steel pipe with 50 mm OD is covered ...

A steel pipe with 50 mm OD is covered with a 6.4 mm asbestos insulation followed by a 25 mm layer of fiber-glass insulation [K = 0.0485 Wmk]. The pipe temperature is 393 K and the

Enthalpy - thermodynamics, Enthalpy: Sol: The enthalpy is total ener...

Enthalpy: Sol: The enthalpy is total energy of gaseous system. It takes into consideration, internal energy and pressure, volume effect. Thus, it can be defined as follows:

Isothermal compression, The critical Temperature of a gas is the highest te...

The critical Temperature of a gas is the highest temperature for which isothermal compression of the gas results in ? Will an adiabatic ?ash result in more, the same, or less va

Electrodes- stainless steel electrodes, Stainless Steel Electrodes A vari...

Stainless Steel Electrodes A variety of stainless steel electrodes are now being manufactured to produce weld metal similar to composition of most base metals. However, the analy

Technical limitations of extension of screw conveyor, Technical Limitations...

Technical Limitations of Extension of screw conveyor Technical Limitations: Breakdown of hinged joint at intermediate condition of link. ?Not proper extension of coaxi

High temperature materials in boilers, Q. High temperature materials in Boi...

Q. High temperature materials in Boilers? A thin refractory layer between the shield and boiler tube is recommended in areas subject to moderate temperatures and levels of corr

Braking system in motorcycle, Braking System: A brake is a component of a ...

Braking System: A brake is a component of a motorcycle which is used to apply frictional resistance to a moving vehicle to stop or retard it by absorbing its kinetic energy. The f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd