Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

#boiler.., what is the essentials of a good boiler?

what is the essentials of a good boiler?

Predictive control algorithms, Predictive Control Algorithms Escaping S...

Predictive Control Algorithms Escaping Scheduling Errors via Partial Look-ahead Since previously mentioned above, the heuristic priority rules that are normally utilized in

Determine directions of the wave vectors-double refraction, Double Refracti...

Double Refraction An unpolarized plane wave is incident from free space onto a quartz crystal (n e = 1.553 and n o = 1.544) at an angle of incidence 30°. The optic axis lies i

Thermodynamics, define the first and second law of thermodynamics.

define the first and second law of thermodynamics.

Explain the principal of resistance welding, Can you explain the principal ...

Can you explain the principal of resistance welding? Classify various Resistance welding processes and Illustrate in detail two of them. With the help of neat and clean graph ex

Volume fraction of fibres, Volume fraction of fibres: The epoxy materi...

Volume fraction of fibres: The epoxy material is prepared to be stressed to its full strength. What must be volume fraction of fibres? Solution Here σ′ = 1200 MPa,

Seasonal-component analysis, Seasonal-Component Analysis: A food proce...

Seasonal-Component Analysis: A food processor uses a moving average to forecast next month's demand. Actual demand data for the past few months is available as depicted in the

Transmission system , Transmission System: In a two-wheeler, the transmiss...

Transmission System: In a two-wheeler, the transmission system means the whole arrangement that transmits the power from the engine crankshaft to the rear wheel.

Concept and application of limiting friction, Concept and application of li...

Concept and application of limiting friction: Sol.: The maximum value of frictional force that comes into play, when the body just begins to slide over the surface of the ot

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd