Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Thermal, mean effective pressure of dual cycle

mean effective pressure of dual cycle

What is the function of a spark plug?, (a) What is the function of a spark ...

(a) What is the function of a spark plug? (b) What are the types of spark plugs? Point out the differences between them. (c) Describe the construction of a spark plug with th

Determine the minimum acceptable diameter of the shaft, The Shaft is made o...

The Shaft is made of a material with an allowable shear strength of 80 Mpa. a.       Develop the torque diagram b.      Determine the minimum acceptable diameter of the shaft

Two-or-three-dimensional-motion, Net force acting on particle of mass 2 kg ...

Net force acting on particle of mass 2 kg is 10N in north direction.At t=o, particle was moving eastwards with 10m/s. Find displacement and velocity of particle after 2 seconds.

Heat, how to prove heat is a path function?

how to prove heat is a path function?

Project, project on solid work 2012 The Final Project is to design a mechan...

project on solid work 2012 The Final Project is to design a mechanical assembly in Solidworks. The design must consist of a minimum of 60 parts, 30 of which must be unique. A uniqu

Cylinder bore-engine terminology , Cylinder Bore: The nominal inner diame...

Cylinder Bore: The nominal inner diameter of the working cylinder is called the cylinder bore and is designated by the letter D and is usually expressed in millimetre (mm).

Determine the relative maximum error, a) Round off the numbers 865250 amd 3...

a) Round off the numbers 865250 amd 37.46235 to four significant figures and compute Ea, Er, Ep in each case. b) IF u= 4 x 2 y 3 /z 4 and errors in x, y, z be 0.001, determine

Petrol-general safety tips , Petrol: Work in a well-ventilated area. Keep ...

Petrol: Work in a well-ventilated area. Keep flames or sparks away from the work area or where petrol is stored.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd