Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Calculate the vertical anchoring forces, A converging elbow (see Figure 4) ...

A converging elbow (see Figure 4) turns water through an angle of 135 o in a vertical plane. The flow cross-section diameter is 400 mm at the elbow inlet, section (1), and 200 mm

THERMODYNAMICS, what is second law of thermodynamics

what is second law of thermodynamics

Refrigeration, In a steam jet refrigeration system, the ejector extracts 3....

In a steam jet refrigeration system, the ejector extracts 3.3 m3/s of saturated water vapor at a temperature of 7.2 °C from the flash chamber. The return water from the cooling coi

Company level - safety organization, Company level - Safety Organization ...

Company level - Safety Organization This is at company level and will straight report to the corporate director. He has to always monitor safety policies of the company and b

Rubber, Rubber Rubber is a plastic that is largely derived from natura...

Rubber Rubber is a plastic that is largely derived from natural sources and utilized in a modified form. For automobile tyres, Rubber is well identified as material. Rubber re

Thermodynamics, Problem specification 5 kg of air is contained in a piston-...

Problem specification 5 kg of air is contained in a piston-cylinder device, initially at a pressure of 2MPa and a specific volume of 0.08m3/kg. The air then expands, as an ideal ga

Objectives to service sector , Objectives After studying this unit, yo...

Objectives After studying this unit, you should be able to discuss the scope and extent of service industry, describe the phases of two wheeler industry growth, an

Find the differential equation, Find the Differential Equation Flow pr...

Find the Differential Equation Flow problems where the Reynolds number is very, very small (Re (a) The space between two coaxial cylinders is filled with an incompressible

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd