Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Maximum stress in the beam due to bending, For the beam shown below, we nee...

For the beam shown below, we need to determine: (i)  the support reactions R L and R R (ii) the shear force and bending moment diagrams (iii) the maximum stress in the b

Calculat ethe total amount of phase, Question 1 For an equilibrium cool...

Question 1 For an equilibrium cooled alloy of 92%D/8%C, which of the above diagrams best represents the microstructure at 0°C? Question 2 For an equilibrium cooled allo

Composities, example with its properties

example with its properties

Significance of damping coefficient, Physical significance of damping coeff...

Physical significance of damping coefficient and it''s unit.

What is wrap-around, The major purpose of a wrap-a-round is to make a strai...

The major purpose of a wrap-a-round is to make a straight line around a pipe to aid in cutting the pipe to its proper length. It is used mainly as a template or a straight edge.

Mechanical properties of materials, A tensile test on a specimen having an ...

A tensile test on a specimen having an initial diameter of 13.11 mm and an initial gauge length of 200.0 mm, gave the following data:

Renewable Energy, I am attending Thermodynamics class at the university. Th...

I am attending Thermodynamics class at the university. The professor asked me to write a research on Renewable Energy: Solar Power. The report should be of 10 pages and at least 10

Applied chemistry, hardness of bore well water is less than sea water .just...

hardness of bore well water is less than sea water .justif

Describe the slope - area method, Q. Describe the Slope - Area Method? ...

Q. Describe the Slope - Area Method? In the event of infeasibility of Velocity Area method on account of either rapid rise or fall of floods or lack of equipment or any other r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd