Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Alignment of piping flanges, Q. Alignment of piping flanges? Alignment ...

Q. Alignment of piping flanges? Alignment of piping flanges shall be in accordance with ASME B16.5. This code specifies that: • Flange centerline misalignment must be within

Calculate the primary voltage and real power measurements, Question: A ...

Question: A 7.2kVA single phase 50Hz, 480Vrms: 240Vrms transformer can be modelled using the primary referred approximate equivalent circuit shown in Figure 1 below. Fi

Co2 welding gun / torch-co2 welding, CO 2 Welding Gun / Torch The torc...

CO 2 Welding Gun / Torch The torch assembly consists of conduits to supply the consumable wire electrode and the shielding gas into the welding gun. The torch assembly may als

Compare two stroke with four stroke engine, Compare Two Stroke with four st...

Compare Two Stroke with four stroke Engine: T w o Stroke Engine In two stroke engine all the four operation that is suction, compression, ignition and exhaust are compl

Design an evaporator system, Q. Design an Evaporator System? The Evapor...

Q. Design an Evaporator System? The Evaporator System is designed to produce high quality distillate. The feed water to the evaporator system is dosed with antiscalant and rece

Force on string - mechanics, Force on String: A string ABCD , attach...

Force on String: A string ABCD , attached to the two fixed points A and D has two weight of 1000N each attached to it at points B and C . The weights rest with portio

What are the capabilities of step, What are the capabilities of STEP In...

What are the capabilities of STEP Industry-Developed STEP Capabilities AP-203, Configuration Control for 3D Design of Mechanical Parts and Assemblies, provides a very robust

Mechanical Vibrations in Strings, Description & Derivation of Mechanical Vi...

Description & Derivation of Mechanical Vibration in Strings, Rods and Aero Foil Flutter

Wilson hartnell governor, how to design and fabricate wilson hartnell gover...

how to design and fabricate wilson hartnell governor?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd