Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Comparison between work and heat - thermodynamics, Comparison between work ...

Comparison between work and heat - thermodynamics: There are a number of similarities between heat and work. 1. Both heat and work are transient phenomena. The systems do n

THERMODYNAMICS, COMPRESSOR MOSTLY USED FOR SUPERHEATING OF IC ENGINES IS CA...

COMPRESSOR MOSTLY USED FOR SUPERHEATING OF IC ENGINES IS CALLED ----------COMPRESSORS

Trusses, Differentiate between perfect, deficient and redundant trusses

Differentiate between perfect, deficient and redundant trusses

General safety and service tips, In general safety and service tips, you le...

In general safety and service tips, you learnt about general service and safety tips those must be followed while working in workshop. It gives the competency statements useful for

Evaluate the directions and magnitude of principal stresses, (a) At a point...

(a) At a point in a material under stress, the resultant intensity of stress across a certain plan is 100 N/mm 2 (compressive) inclined at 30 o to its normal. On another plane th

Seam welding, Seam Welding Seam welding is different from spot welding ...

Seam Welding Seam welding is different from spot welding by the fact that roller type electrodes are used in the former case. The principle and process of welding are the same

Design a remote control transmitter, You are required, as part of a small t...

You are required, as part of a small team, to design a remote controlled buggy that can be made to move forwards, backwards and from side to side. The basic buggy and motors are pr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd