Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Gating system design, Explain the several types of pattern allowances with ...

Explain the several types of pattern allowances with neat sketch. Show the six important - aspects of gating system design. Illustrate briefly their functions.

Stages in making a spot welding, Q.Show the procedure of spot welding ? ...

Q.Show the procedure of spot welding ? The steps involved in making a spot weld are listed below and shown but before spot welding one must make sure that (i) The job is clea

Continuous and salt bath furnaces, Continuous Furnace: Parts to be tr...

Continuous Furnace: Parts to be treated are situated on several sort of conveyor that move into the furnaces as per to programmed heating cooling cycle. The time for unloadin

Computer aided process planning, eXPLAIN THE GRAPHICAL IMPLEMENTATION OF TO...

eXPLAIN THE GRAPHICAL IMPLEMENTATION OF TOOL PATH GENERATION

What is called materials which can store electrical energy, Materials which...

Materials which can store electrical energy are called (A) magnetic materials.  (B) semi conductors. (C) dielectric materials.  (D) super conductors. Ans: Mater

Welding of pressure parts in boilers, This section covers welding of pressu...

This section covers welding of pressure parts including those non-pressure parts when welded to pressure parts. All welding design functions necessary within the contract shall be

Mass flow rate - thermodynamics, Mas s Flow Rate (m ): In absence of ...

Mas s Flow Rate (m ): In absence of any mass getting stored system we can write; Mass flow rate at inlet = Mass flow rate at outlet That is, m f1  = m f2 as m f  = d

Governor, what is hartnell governor

what is hartnell governor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd