Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Illustrated about the term bending moment, Illustrated about the term bendi...

Illustrated about the term bending moment? Bending Moment The critical section for bending moment for masonry or concrete block walls is half-way between the centre line and

Convert the flow-rate of a compressor, Convert the flow-rate from Am3/h to ...

Convert the flow-rate from Am3/h to Sm3/h Consider a compressor (model ABC-Z4).  The compressor has a suction pressure of 3 barg, and a discharge pressure of 6 barg.  The inlet

Thermal efficiency and compression ratio, Thermal efficiency and compressio...

Thermal efficiency and compression ratio: Calculate thermal efficiency and compression ratio for automobile working on otto cycle. If energy generated per cycle is thrice whi

Automation material specifications, Q. Automation Material Specifications? ...

Q. Automation Material Specifications? Automation Material Specifications include the development and / or review of material specifications, and the review of data sheets, mat

Determine the percentage increase in power possible, An open belt connects ...

An open belt connects two flat pulleys. The pulley diameters are 300 mm and 450 mm and the corresponding angles of Cap are 160 o and 210 o . The smaller pulley runs at 200 r.p.

Expression for strain energy, Expression for strain energy: Derive an...

Expression for strain energy: Derive an expression for strain energy because of torsion.                                          Sol.: The work done in straining shaf

Causeways, Paved Dips: Paved dips, also known as bed level causeways,...

Paved Dips: Paved dips, also known as bed level causeways, are structures consisting of gentle and shallow depressions in the road where the water is allowed to flow over the

Determine the loss of information during exchange in iges, Determine the Lo...

Determine the Loss of Information During Exchange in IGES Loss of Information During Exchange : Information would inevitably be lost when information is passed between two CAD

Gathering lines, Gathering Lines: A gathering line, also called a lad...

Gathering Lines: A gathering line, also called a ladder track, is one into which a number of parallel tracks merge. This is shown in Figure. It is used in marshalling yards.

Find out ratio of upper end area to lower end area of bar, Find out ratio o...

Find out ratio of  upper end area to lower end area  of bar of uniform strength Sol : The figure given to us shows a bar subjected to external tensile load P. If bar had be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd