Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Assignment, AskTask 2 (3 questions) Material engineers should be conversant...

AskTask 2 (3 questions) Material engineers should be conversant of various materials, their properties, manufacturing process involved, environmental issues, monetary issues and mo

Analysis of trusses, State the assumptions in pin joined trusses?

State the assumptions in pin joined trusses?

Welding, function of helium shielding gas

function of helium shielding gas

Theorem of parallel axis, Theore m of parallel axis It states that if ...

Theore m of parallel axis It states that if the M.I. of plane area about the axis passing through the C . G . can be denoted by I G . The M . I . of area about any other

Find out the moment of inertia of a semicircle, Find out the moment of ine...

Find out the moment of inertia  of a semicircle: Find out the M. I. of a semicircle ABM around its periphery AB and also around centroidal axes x and y as illustrated in Figur

Mechanicalthermodynamics, Does this college offer courses in the field of m...

Does this college offer courses in the field of mechanicalthermodynamics?

Calculate the greatest stress - plate, Calculate the greatest stress - plat...

Calculate the greatest stress - plate: A rectangular plate 10 mm thick within a hole of 50 mm diameter drilled on this is as shown in Figure 10. This is subjected to axial pul

Evaluate the speed of train, Evaluate the speed of train: A train of ...

Evaluate the speed of train: A train of mass 200KN has frictional resistance of 5N per KN. Speed of train, at the top of an inclined of 1 in 80 is 45 Km/hr. Find speed of tra

Explain interpoles or commutating poles, Interpoles or commutating poles ...

Interpoles or commutating poles Interpoles are ?xed to the frame in among main poles. They are used for sparkless commutation, i.e, to improve commutation.

What do you mean by weld and hold time, Q. What do you mean by Weld and hol...

Q. What do you mean by Weld and hold time? Weld time During this period the welding current flows through the circuit, i.e., it enters from one electrode, passes through t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd