Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Moments, what is resultant of coplanar non concurrent forces

what is resultant of coplanar non concurrent forces

Closed - open or isolated system, (a) Specify, giving reasons whether the f...

(a) Specify, giving reasons whether the following systems are closed, open or isolated when in operation (i) Kitchen Refrigerator (ii) Ice-cream freezer (iii) Scooter Engi

Determine tension in the rope - motion of lift, Determine tension in the ro...

Determine tension in the rope: An elevator cage of mineshaft, weighing 8KN when, is lifted or lowered by means of wire rope. Once man weighing 600N entered it and lowered wit

AUTOMOTIVE CONTROL, Ask DIFFERENTIAL AMPLFIER USED WITH THERMOCOUPLEquestio...

Ask DIFFERENTIAL AMPLFIER USED WITH THERMOCOUPLEquestion #Minimum 100 words accepted#

Lubricating system, what are the functions of a lubricating system

what are the functions of a lubricating system

Melting point, What is melting point of aluminium?

What is melting point of aluminium?

Objectives of motorcycle repairing , Objectives: After studying this unit ...

Objectives: After studying this unit and subsequent practicing, you should be able to acquire the skills required for troubleshooting of a motorcycle and identify different

Battery is not charging motorcycle problem, If Battery is Not Charging ...

If Battery is Not Charging Causes of Problem Remedy Electrolyte specific gravity NG Charging not done fully

Magnitude of the load - hollow cast iron cylinder, Magnitude of the load - ...

Magnitude of the load - hollow cast iron cylinder: Q: A hollow cast iron cylinder 4 m long, 300 mm is the outer diameter, and thickness of metal 50 mm is subjected to central

Necessity of brakes , Necessity of Brakes To stop a vehicle in nor...

Necessity of Brakes To stop a vehicle in normal as well as emergency conditions. To slow down the speed to turn, pass hurdles etc.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd