Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Gears, Gears : A gear is a disc with teeth on its boundary. If these teeth...

Gears : A gear is a disc with teeth on its boundary. If these teeth are formed at its inner boundary then this gear is known as an internal gear (annulus). These types of gears ar

Safety in tig welding-radiation energy hazard, SAFETY IN TIG WELDING-Radiat...

SAFETY IN TIG WELDING-Radiation Energy Hazard Radiant energy may cause injury to the welder in two areas, eye and the skin. Any personnel, whether the welder, inspection person

Horizontal deflection , A  truss  is  shown  in  the  given figure. Compute...

A  truss  is  shown  in  the  given figure. Compute  the horizontal deflection of  joint D formed by  both  the  load  and  fabrication  error  (bar  AE  is  30mm  too  long).  For

Joint preparation and identification, The joint bevels shall be prepared in...

The joint bevels shall be prepared in accordance with the registered and approved weld procedure. Internal and external surfaces to be welded shall be clean and free from paint, o

Home home, why 4R kinematic chain do not form different mechanisms?

why 4R kinematic chain do not form different mechanisms?

Closed system - thermodynamics system, Closed System: The system tha...

Closed System: The system that can exchange energy with the surrounding but not the mass. The quantity of matter hence remains fixed. And the system can be described as cont

Corrosion in boiler, Q. Corrosion in Boiler? With proper BFW treatment,...

Q. Corrosion in Boiler? With proper BFW treatment, and maintaining pH within a certain range (9.2 to 9.4) and removing oxygen from the system, a stable passive film will be for

Energy method, A semi circular frame of flexural rigidity EI is built at A ...

A semi circular frame of flexural rigidity EI is built at A and caries a vertical load W at B. calculate the magnitude of the vertical and horizontal deflection at B and hence the

What is product definition data interface, Product Definition Data Interfa...

Product Definition Data Interface (PDDI) IGES provided a very practical first solution for CAD data exchange, complete with an exchange file format. It was remarkable in the sp

Corrctoin couple, when correction couple should be applied?

when correction couple should be applied?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd