Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

What is the pull required on brake arm to stop wheel, A simple band brake p...

A simple band brake performs on a drum of 600mm in diameter that is running at 200 r.p.m. The coefficient of friction is 0.25. The brake band has a contact at 270 o one end is fas

Explain Functions of springs as on following points, 1. store energy 2. app...

1. store energy 2. apply force on a body 3. balance force between two bodies 4. absorb vibrations of body

What are the constructional aspects of well foundations, What are the Const...

What are the Constructional Aspects of Well Foundations  There are several aspects which require careful consideration during sinking of well foundations. They are i)  Prepa

About learning software''s, I am am Mtech student of Machine design and I a...

I am am Mtech student of Machine design and I am willing to join some core companies so is this the right time for learning some software''s if yes which are they...

Instantaneous stress formula, Ask quesinstantaneous stress formulation #Min...

Ask quesinstantaneous stress formulation #Minimum 100 words accepted#

Specific properties of a system, Specific Properties of a System The ex...

Specific Properties of a System The extensive properties while estimated on the unit mass basis result in intensive property that is as well known as specific property. For exa

Two stroke and four stroke engines, T w o Stroke and Four Stroke Engines:...

T w o Stroke and Four Stroke Engines: In  the two stroke engines thermodynamic cycle is completed in One revolution of crank shaft whereas in 4 stroke engines the cycle is c

Breather tube-stator plate oil seal complaints, Breather tube : Check brea...

Breather tube : Check breather tube for blockage and also air filter box hole where breather tube is connected, for any blockage.

Biaxial tension-compression state, Given:  A brittle material has an ulti...

Given:  A brittle material has an ultimate tensile strength of 300 MPa and an ultimate compressive strength of  -1000MPa.  Assume that failure can be represented by the Modified

Calculate all the mass-normalised modal vectors, The body, suspension and e...

The body, suspension and engine mounting system of a vehicle may be idealised as a three degree of freedom system consisting of a bar of mass 1400 kg and the centre of mass at G, 1

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd