Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Fire dampers - air-conditioning guidelines, Clearly indicate fire dampers o...

Clearly indicate fire dampers on ducts penetrating fire rated partitions, equipment rooms, duct shafts, ceiling outlets, etc. Detail fire dampers on drawings if required. For

Explain about vertical vessels, Q. Explain about Vertical Vessels? Vert...

Q. Explain about Vertical Vessels? Vertical vessels shall normally be designed as self-supporting units, and shall resist overturn based upon wind or earthquake considerations.

Physics, Ask question #Minimum 1010 words accepted#

Ask question #Minimum 1010 words accepted#

What is the combined stiffnes, A competitor in a hill-climb event finds dur...

A competitor in a hill-climb event finds during practice that his car becomes airborne at a particular point on the hill.  Shortly after landing the lowest point in the car just co

What is the rol of forecasting, a) Illustrate the important of Ergonomics i...

a) Illustrate the important of Ergonomics in a manufacturing sector or in service sector in the context of productivity. b) What is the rol of "Forecasting" Plays in production

Scope of thermodynamics in thermal engineering, Scope of thermodynamics in ...

Scope of thermodynamics in thermal engineering Sol: Thermal engineering is a very important associate branch of mechanical, metallurgical, aerospace, chemical, marine, auto

Takt time for sand blasting, Takt Time for sand blasting:            ...

Takt Time for sand blasting:             Tatk time is crucial in manufacturing process. It determines the speed of production to produce a product. Time is money toward prod

Wilson hartnell governor, how to design and fabricate wilson hartnell gover...

how to design and fabricate wilson hartnell governor?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd