Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Working of impulse turbine, Working of Impulse turbine: The technique ...

Working of Impulse turbine: The technique in which multiple system of rotors are keyed to a common shaft, in series and the steam pressure of jet velocity is absorbed in stage

What are the benefits of value engineering, Normal 0 false fa...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Calculate the cycle and production rate , Calculate the Cycle and Productio...

Calculate the Cycle and Production Rate for Single-Machine Robotic Cell Determine the cycle and production rate for a single-machine robotic cell for an 8-hr shift if the syst

High speed circuit-carburettor in high speed condition , High Speed Circuit...

High Speed Circuit : The speed of motorcycle is further increased by raising the throttle valve. In this condition, fuel and air enter through main passage and main jet as can be

CAPP, what is MIPLAN system

what is MIPLAN system

TURBINE, Is it possible to rotate turbine blades without any fluid means th...

Is it possible to rotate turbine blades without any fluid means there is no requirement of water or air to rotate turbine blade. blades may rotates with the help of spring compress

Find out its centre of gravity, Find out its centre of gravity: A squa...

Find out its centre of gravity: A square plate of uniform thickness and density is bent along M 1 M 2 till corner C coincides along with centre C′. Find out its centre of gr

Strength of material and engineering mechanics, Di fferentiate between str...

Di fferentiate between strength of material and engineering mechanics Sol.: Three primary areas of mechanics of solids are statics, dynamics and the strength of materials.

Calculate the normal time for this operation, a) Describe Industrial Engine...

a) Describe Industrial Engineering. Discuss its scope and use in service and manufacturing industries. b) Deriving the stop watch study in a machine shop, ten observation of a d

Engineering Mechanics, What are the practical applications of solid cylinde...

What are the practical applications of solid cylinder or shaft under cyclic axial loading

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd