Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Space mass and weight - mechanics, Space mass and weight: The geometri...

Space mass and weight: The geometric region occupied by bodies called as space. When body changes its position w. r.t. the other bodies, then body is known to be in motion.

Describe brazing process, Brazing is a technique of joining two similar of...

Brazing is a technique of joining two similar of dissimilar metal pieces together by heating the surfaces and by using a non-ferrous filler metal having its melting point above 42

Mounting systems for the welding head-boom mounted type, Mounting Systems ...

Mounting Systems For The  Welding Head-Boom mounted type These are the most versatile type of welding systems. Normally the boom is supported by means of a column. The welding

#thermodynamic, heat pump to estimate the COP acts as refrigerator experime...

heat pump to estimate the COP acts as refrigerator experiment abstract

Fuse-fundamentals of electricity , Fuse :  Fuse wire is made of soft ...

Fuse :  Fuse wire is made of soft metal and housed in a glass tube. It is connected in circuit. It protects the electrical accessories, which may be damaged by the overflow o

Trusses, Differentiate between perfect, deficient and redundant trusses

Differentiate between perfect, deficient and redundant trusses

Clearance volume, Clearance Volume ( V C ) : The nominal volume of the c...

Clearance Volume ( V C ) : The nominal volume of the combustion chamber above the piston when it is at the top dead centre is the clearance volume. It is designated as V C an

Define gas welding, Q. Define Gas Welding? Metal joining process in whi...

Q. Define Gas Welding? Metal joining process in which the ends of pieces to be joined are heated at their interface by producing coalescence with one or more gas flames (such a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd