Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Design lay-down areas for plant, Q. Design lay-down areas for plant? De...

Q. Design lay-down areas for plant? Designated lay-down areas are areas specifically positioned to enable equipment maintenance to be carried out. These are normally assigned f

Optimization, consider the following LPP max z=9x1+8x2+5x3 subject to 2x1+3...

consider the following LPP max z=9x1+8x2+5x3 subject to 2x1+3x2+x3 5x1+4x2+3x3 x1,x2,x3>_0 (a)solve using simlex method (b)hence using the sesitivity analysis

Explain conveyor and auger, Conveyor and auger Two Hydraulic motors are...

Conveyor and auger Two Hydraulic motors are provided for individual control of two conveyors and Auger, which are provided for individual control of material on both the sides

Determine the process of modelling, Determine the process of modelling ...

Determine the process of modelling The process of modelling is much easier, if mathematical description of an object, or at least of part of an object may be applied. In the fi

Tension testing, The first laboratory report, covering the two-part exercis...

The first laboratory report, covering the two-part exercise involving tension testing and stress concentrations is due in lab two weeks after the conclusion of fatigue testing.

Calculate the radius of plates, Calculate the radius of plates: A lami...

Calculate the radius of plates: A laminated steel spring, simply supported at the ends & centrally loaded, along a span of 0.8 m; is needed to carry a proof load of 8 kN; and

Annealing temp, hiw can i fix the maximum temp of the aluminium

hiw can i fix the maximum temp of the aluminium

Calculate drilling speed and machining time, Calculate Drilling Speed and M...

Calculate Drilling Speed and Machining Time Calculate the drilling speed if a 50 mm dia hole of 60 mm depth is to be drilled in a M.S. component. The feed rate is 0.2652 and M

Water vortex fountain, hi there there is many way to make the water vortex...

hi there there is many way to make the water vortex but am not sure how can we make the one like > (www.williampye.com/work/charybdis)

What is shallow foundation, What is Shallow foundation Shallow foundati...

What is Shallow foundation Shallow foundations are those where the depth D

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd