Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Explain macroscopic approach - thermodynamics, Explain Macroscopic Approach...

Explain Macroscopic Approach - Thermodynamics 1. In this method a fixed quantity of matter is considered without taking into account the events taking place at molecular level.

Reasons of attribution of raft foundations by rigid method, What are the re...

What are the reasons of attribution of raft foundations by rigid method? The overdesign of raft foundations by rigid method can be attributed to three major reasons: a. Ther

Advantages and limitations of adhesive bonding, Advantages and Limitations ...

Advantages and Limitations of Adhesive Bonding The description so far might be concluded through listing main advantages of adhesive joints. (a) The adhesive joints assist

Types of registration in entrepreneurship development, Types of Registratio...

Types of Registration Provisional Registration Certificate ( PRC ) This is given for the pre-operative period and enables the units to obtain the term loans and worki

Problems on cantilever truss, Problem s on Cantilever Truss: In the c...

Problem s on Cantilever Truss: In the case of cantilever trusses, it is not required to determine the support reactions. The forces in members of cantilever truss are obtaine

Explain index jig, Explain Index Jig? 1. This type of jig, as the...

Explain Index Jig? 1. This type of jig, as the name suggests, incorporate a suitable indexing mechanism, by means of which the work piece can be indexed to required posit

Screw conveyors, Screw Conveyors: Screw conveyors are used principally f...

Screw Conveyors: Screw conveyors are used principally for transmitting materials in the form of powder or paste with the application of rotating screw. For example feedin

Calculating the number of kanban card sets, Calculating the number of kanba...

Calculating the number of kanban card sets: A hospital desires to set up a Kanban system to manage its supply of blood with the regional blood bank. The regional blood bank tr

Determine m.i. of i section about 2 centroidal axes, Q.  An I section has d...

Q.  An I section has dimensions Top flange = 8 cm × 2 cm; Bottom flange = 12 cm  × 2 cm; Web = 12 cm × 2 cm; Over all the depth of section = 16 cm. Determine M.I. of  I s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd