Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

What is slush moulding, Q. What is Slush moulding? Slush moulding is an...

Q. What is Slush moulding? Slush moulding is an excellent method for producing open-end objects. It is an inverse process of dipping, in which the inside of the mould is coated

Write down the uses of vernier caliper and steel rule tools, Write down the...

Write down the uses of following tools and make neat sketches of the same : (a) Vernier Caliper (b) Steel Rule

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Significance of damping coefficient, Physical significance of damping coeff...

Physical significance of damping coefficient and it''s unit.

Program evaluation and review techniques, Program Evaluation and Review Tec...

Program Evaluation and Review Techniques: The Rola and Cola Corporation is a professional II nursing home aspiring to become I nursing home. It desires to provide the ultimate

Manufacturing processes, Manufacturing Processes: Importance of Manuf...

Manufacturing Processes: Importance of Manufacturing: The importance of manufacturing is that a gives usable product from the ore of different metals and from different mate

Calculate the standard time, a) The total estimated time for an operation i...

a) The total estimated time for an operation ie assembly of a pin is 2 minutes. If the rating is 120% determine normal time. If total allowances allowed are 10% for that job, calcu

Purpose of internal review, Q. Purpose of Internal review? The Project ...

Q. Purpose of Internal review? The Project Engineer in consultation with affected disciplines decides the timing of an internal review of IFR issue drawings. Each involved dis

Explain double bolting, Q. Explain Double Bolting? Where low strength b...

Q. Explain Double Bolting? Where low strength bolts must be used, initial bolting with higher strength low temperature bolts may be necessary to minimize accumulative strain an

Linear problen, A paper mill produces two grades of paper viz. , X and Y. B...

A paper mill produces two grades of paper viz. , X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd