Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Fluid mechanics.., write the conservation of mass for steady flow throught ...

write the conservation of mass for steady flow throught a streamtube with asingal one dimensional inlet 1and exit 2

Alloy materials control, Q. Alloy materials control? All low alloy and ...

Q. Alloy materials control? All low alloy and high alloy equipment components including fittings, flanges and sections of pipe and all welds shall be individually tested by Ven

Derivation, how to find the equation for deflection of a cantilever beam su...

how to find the equation for deflection of a cantilever beam subjected to udl in terms of Airy''''s stress function

Calculate the value of force - frictionless pulley, Calculate the value of ...

Calculate the value of force - frictionless  A block weighing 5KN is attached to the chord that passes over the frictionless pulley, and supports weight of 2KN. The coeffic

Scanning electron microscope, 1- Explain the rationale of using a small WD ...

1- Explain the rationale of using a small WD to improve resolution. 2- In a tungsten SEM , Why does a high accelerating voltage provide the potential for higher resolution?  Why

Coplanar and non-coplanar forces, Coplanar and Non-Coplanar Forces: In...

Coplanar and Non-Coplanar Forces: In this unit, you have learnt to identify the different systems of forces. You have also learnt the many techniques of adding the forces to g

Statics, what are the common application of statics in industry

what are the common application of statics in industry

Working of gasifier combined cycle power plant, With the help of a neat dia...

With the help of a neat diagram illustrate the working of Gasifier combined cycle power plant. Describe with the help of neat diagram the working of Pressurised water reactor nu

Local stresses - vessel rigging analysis, Q. Local Stresses? Local stre...

Q. Local Stresses? Local stresses in the vessel shell/head/skirt/base rings from the lifting attachments (such as lugs, trunnions, etc.), shall be determined for the imposed lo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd