Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Seismometer-accelerometer-accelerometer, Seismometer : this is a transduc...

Seismometer : this is a transducer in which signal is proportional to the displacement. Accelerometer : This is a transducer in which signals is proportional to the a

Necessity of transmission system , Necessity of Transmission System ...

Necessity of Transmission System The main purpose of Transmission system is to provide a means to vary the torque ratio between the engine and the road wheels. It means th

Multiview Projections, I''m having trouble with some drawing questions, whe...

I''m having trouble with some drawing questions, where I am given two orthogonal projections (front and side view) of an unknown 3D object, I have to draw the top view using a mite

Net hydrostatic moment on the cylinder, A long cylinder of radius 2 m hinge...

A long cylinder of radius 2 m hinged at point A is used as an automatic gate. When the water level reaches 15 m the gate automatically opens. Determine the magnitude of the net hyd

Resistance spot welding, Resistance Spot Welding In this process, a spo...

Resistance Spot Welding In this process, a spot of weld is made between overlapping sheets by means of two cylindrical copper alloy electrodes, one on top and the other at the

Currency bull spread and bear spread, Currency Bull Spread and Bear Spread:...

Currency Bull Spread and Bear Spread: A currency bull spread is constructed by buying a call option for a particular underlying currency and simultaneously writing a call opti

Find the horizontal hydrostatic force, Question. In the system shown below...

Question. In the system shown below, the force exerted by the free jet issuing from the sharp-edged circular nozzle and impinging on the small circular plate is just su±cient to k

Determine the loss of information during exchange in iges, Determine the Lo...

Determine the Loss of Information During Exchange in IGES Loss of Information During Exchange : Information would inevitably be lost when information is passed between two CAD

Governors, How a governor works? I mean how it''s regulate the speed of for...

How a governor works? I mean how it''s regulate the speed of for example electricity generators?

Calculate diameter of runner, A radically inward flow turbine working under...

A radically inward flow turbine working under a head of 10 m and running at 250 rpm develops 185 KW at the turbine shaft. At inlet tip of the runner vane, the peripheral velocity o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd