Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Screw jack, give equivalence of screw jack and friction on an inclined plan...

give equivalence of screw jack and friction on an inclined plane

Volume fraction of fibres, Volume fraction of fibres: The epoxy materi...

Volume fraction of fibres: The epoxy material is prepared to be stressed to its full strength. What must be volume fraction of fibres? Solution Here σ′ = 1200 MPa,

Friction, law of static friction

law of static friction

Aspects of scheduling , Aspects Of Scheduling  The difficulty is a mod...

Aspects Of Scheduling  The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficu

Briefly explain model scale design, Q. Briefly explain Model scale design? ...

Q. Briefly explain Model scale design? Knowledge of dynamic similarity conditions enables evaluation of model scales. Almost alI the problems related to river hydraulics are ab

Hydro turbine, in hydro turbine vaccum is present in casing or not? & if no...

in hydro turbine vaccum is present in casing or not? & if not then how suction is take place?

Auto - associative network, We seek to test if an auto-associative network ...

We seek to test if an auto-associative network is capable of recalling certain memories. Here you will test if patterns can be completed or recovered. You are given a single patter

Functions of geometric modeling, Q. Functions of geometric modeling? De...

Q. Functions of geometric modeling? Design Analysis • Evaluation of area, volume, mass and inertia properties. • Interference checking in assemblies. • Analysis of

Dynamics of the water tank, A Perspex tank ure 1), which has parallel sides...

A Perspex tank ure 1), which has parallel sides for the top part of its height and a 'V' shaped section for the bottom part and a constant width throughout, is used as a receptacle

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd