Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Calculate the minimum required cross-sectional area, A lifting shackle in a...

A lifting shackle in a glass-making factory is made from a special high-temperature stainless steel. It is expected that the shackle will experience a tensile load of 5kN and th

Find the minimum weight to keep equilibrium, Find the minimum weight to kee...

Find the minimum weight to keep equilibrium: A belt supports the two weights W 1 an d W 2 over a pulley as shown in the figure given below. If W 1 = 1000N, fi

Heat treatment of tool steels, Heat Treatment of Tool Steels This trea...

Heat Treatment of Tool Steels This treatment in case of tool steels in a significant step before actually employing the tool. Most properties are attained after heat treatment

Determine m.i. of i section about 2 centroidal axes, Q.  An I section has d...

Q.  An I section has dimensions Top flange = 8 cm × 2 cm; Bottom flange = 12 cm  × 2 cm; Web = 12 cm × 2 cm; Over all the depth of section = 16 cm. Determine M.I. of  I s

Calculate the magnitude of forces, The greasted and least resultant of forc...

The greasted and least resultant of forces performing on a body are 35 KN and 5 KN respectively. Calculate the magnitude of forces. What could be the angle between these forces if

Coplanar and non-coplanar forces, Coplanar and Non-Coplanar Forces: In...

Coplanar and Non-Coplanar Forces: In this unit, you have learnt to identify the different systems of forces. You have also learnt the many techniques of adding the forces to g

Feed speed-spindle rpm-cutting time material removal rate, A hole of 25 mm ...

A hole of 25 mm diameter and 62.5 mm depth is to be drilled. The suggested feed is 1.25 mm/rev.and the cutting speed is 60 m/min. Assume the clearance height is 5 mm. Determine: f

Mockup of tube to tubesheet, what are the tests to carried out after mockup...

what are the tests to carried out after mockup preparation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd