Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Illustrate the universal support of data types, Universal Support of Data T...

Universal Support of Data Types To address inherent functional incompatibilities, we take the exact opposite route to the 'least common denominator' approach of previous soluti

Perfect frame - truss, Perfect Frame - Truss: Perfec t Frame The...

Perfect Frame - Truss: Perfec t Frame The frame that is composed of such members, which are sufficient to keep the frame in equilibrium, when the frame is sustaining the

Determine the elements of the vdafs version 2.0, Determine the Elements of ...

Determine the Elements of the VDAFS version 2.0 Elements of the VDAFS version 2.0 are shown in Table. Curves and surfaces are described with the help of points, set of points

Find dmension of strongest rectangular beam, Q.   Find the dimension of str...

Q.   Find the dimension of strongest rectangular beam that can be cut out of log of 25 mm  diameter. Sol .: b 2 +  d 2 = 25 2 d 2 = 25 2 -  b 2 As M/I = σ/y; M =

Show the limitations of rigid bed models, Q. Show the Limitations of Rigid ...

Q. Show the Limitations of Rigid bed models? Due to vertical exaggeration, model slope automatically becomes steeper than in the prototype, this slope exaggeration being the sa

Press tools, Difference between press forminig and hammer forming

Difference between press forminig and hammer forming

Question.., Two concentric perforared plates are seperated by a 200mm laund...

Two concentric perforared plates are seperated by a 200mm launder and form the flow exit for a clarifier (figure 1). The inlet water flow of 1200 mcubed/hour into the clarifier is

Superconductivity, what all are the application of superconductivity in dai...

what all are the application of superconductivity in daily life?

Thermodynamic, what is the difference between intrinsic and extrinsic proce...

what is the difference between intrinsic and extrinsic process?

Expression for the normal and tangential stresses, Expression for the norma...

Expression for the normal and tangential stresses: By sing Mohr's circle, derive expression for the normal and tangential stresses on a diagonal plane of material subjected t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd