Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Maximum stress failure criterion, a) Determine the value of σ 0 to cause f...

a) Determine the value of σ 0 to cause failure when θ=30°, according to the maximum stress failure criterion.  Consider both σ 0 > 0 and σ 0 e.g. "failure in longitudinal tens

Explain the tool signature, Explain the Tool Signature The tool angles ...

Explain the Tool Signature The tool angles have been standardized by the American standards association. The seven important elements comprise the signature of the cutting tool

Describe split pattern or two piece pattern, Split pattern or two piece pat...

Split pattern or two piece pattern This is the most widely used type of pattern for intricate castings. When the contour of the casting make sits withdrawal from the mould diff

Forced air cooling - type of cooling system, Forced Air Cooling: A fa...

Forced Air Cooling: A fan makes a difference between natural air cooling and forced air-cooling. The fan supplies the required air to carry away heat from the engine cylinder

Evaluate plant load factor, a) Illustrate principal of magneto hydro dynami...

a) Illustrate principal of magneto hydro dynamic system (MHD) with diagram? b) a thermal power plant has two 60 MW units each running for 8000hrs and one 30MW unit running for 2

Fracture toughness of material of plate, Fracture toughness of material of ...

Fracture toughness of material of plate: A large thin plate carrying a crack of 70 mm at its centre is subjected to fluctuating stress cycle perpendicular to crack. s max = 7

Find the cycle efficiency, Develop an EES Code for a Rankine cycle with reh...

Develop an EES Code for a Rankine cycle with reheat and with 2 open feedwater heaters.  The cycle is shown below:  Use the following conditions: 1.  700 psi, 850F 2.  500

Short-term scheduling and control, Short-Term Scheduling And Control Th...

Short-Term Scheduling And Control The major objective at this stage is to make sure the efficient and smooth operation of the system in the event of unforeseen disturbances. Th

Manufacturing technology, Details of rolling process,Different rolling meth...

Details of rolling process,Different rolling methods,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd