Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Explain about horizontal vessels, Q. Explain about Horizontal Vessels? ...

Q. Explain about Horizontal Vessels? Horizontal vessels shall preferably be designed for two saddle supports attached by welding. Design of saddle supports and calculation of

MATERIAL SCIENCE, IF ONE SOLID PHASE SPLITS INTO TWO SOLID PHASES ON HEATIN...

IF ONE SOLID PHASE SPLITS INTO TWO SOLID PHASES ON HEATING THE REACTION IS CALLED

Determine hardness of material, Determine hardness of material: Hardne...

Determine hardness of material: Hardness is surface property. It can be defined as resistance of material against permanent deformation of surface in the form of scratch, inde

What is metal jacketing, Q. What is Metal Jacketing? a) Metal jacketing...

Q. What is Metal Jacketing? a) Metal jacketing shall be Alcan T-3000-H14 series, T-1100-H14 or approved equivalent stucco embossed aluminum with a factory applied moisture barr

Find maximum torque which can be transmitted by belt drive, Find maximum to...

Find maximum torque which can be transmitted by belt drive: A belt is stretched over the two identical pulleys having diameter D meter. The initial tension in belt throughout

Geometrical modeling of curves, Geometric modeling is an integral part of a...

Geometric modeling is an integral part of any Computer-Aided-Design (CAD) system. A geometric model is defined as the complete representation of graphical and non-graphical informa

Welded pressure joint requirements, Q. Welded Pressure Joint Requirements? ...

Q. Welded Pressure Joint Requirements? The welded pressure joint requirements should be selected to be suitable to the need; however, the following shall apply: Welded joint

Cam profile, sketch and discuss the uses and application of the following t...

sketch and discuss the uses and application of the following types of cam follower;knife edge,roller and flat ended.

Resultant of concurrent force system, Resultant of Concurrent Force System:...

Resultant of Concurrent Force System: The resolution of forces helps in finding out the resultant of a number of forces working on a body as it decrease vectorial addition to

Ultrasonic examination, Q. Ultrasonic Examination? Ultrasonic examinati...

Q. Ultrasonic Examination? Ultrasonic examination, UT and the acceptance criteria shall be in accordance with the Code and performed in accordance with written procedures. W

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd