Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine the proper torque values from the flange, Q. Determine the proper...

Q. Determine the proper torque values from the Flange? Determine the proper torque values from the Flange Closure Sheet. Apply the torque, using a hand torque-measuring wrench,

Foreign inclusions-slag inclusions-oxide films in fusion wel, Foreign Inclu...

Foreign Inclusions   Slag inclusions This is formed due to entrapment of oxides and non metallic solid material in the weld deposit or between the weld metal and base met

Mircometer, How is a micrometer used?

How is a micrometer used?

Discuss relative demerits and merits of belt, Discuss relative demerits and...

Discuss relative demerits and merits of belt, rope and chain drive for transmission of power and find the condition for transmitting the maximum power in a flat belt drive.

Ideal fluids in motion, In hydrostatic we consider that fluids were at rest...

In hydrostatic we consider that fluids were at rest. Now we relax this consideration but with caution. We will discuss the flow of an real fluid. There are the assumptions about pe

Friction, Friction: When a body moves or tends to move over the other ...

Friction: When a body moves or tends to move over the other body, a force opposing the motion develops at the contact surfaces. This force that opposes the movement or the ten

Torsion, diameter = 100mm length = 470mm power = 4000 w radians = 78 shear ...

diameter = 100mm length = 470mm power = 4000 w radians = 78 shear modulus 60000 n/mm^2 determin the maximum shear stress and angle of twist

Explain working of plate heat exchangers, Q. Explain working of plate heat ...

Q. Explain working of plate heat exchangers? For gasket plate heat exchangers handling flammable materials, the same spacing requirements for air coolers should be applied. If

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd