Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Illustrates about the term rectangular footings, Illustrates about the term...

Illustrates about the term rectangular footings? RECTANGULAR FOOTINGS: The design of rectangular footings is similar to that of the square footings. The major difference is

Thermal stress, how did the formula derived smax = Ed1 a ?T/d 2

how did the formula derived smax = Ed1 a ?T/d 2

Show leak area preparation, Q. Show Leak Area Preparation? Clearly mark...

Q. Show Leak Area Preparation? Clearly mark the location of the leak on the flange with a permanent marker. Notes: 1. Depressurizing hydrocarbon lines in non-emergency event

Rotary converters, ROTARY CONVERTERS Historically, these type of power so...

ROTARY CONVERTERS Historically, these type of power sources were developed first for arc welding applications and even now these types are popular. These rotary converters are of

Classification of force - mechanics, Classification of force: Single f...

Classification of force: Single force is of two types that is, Tensile and compressive. Generally in a body several forces are acting. When a number of forces of different mag

Explain the machining processes, Machining Processes In machining proce...

Machining Processes In machining processes, also known as Metal cutting or chip forming processes, material is removed from a work piece to get the final shape of the product.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd