Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Draw bending moment diagram, Draw bending moment diagram: Draw the she...

Draw bending moment diagram: Draw the shear force diagram (SFD) & bending moment diagram (BMD) for the beam illustrated in Figure . Solution Reaction at the support A,

Desgin of furnce - combustion chamber, Desgin of furnce - combustion chambe...

Desgin of furnce - combustion chamber: • Deside on type of furnace :need review of furnace types (grete,fluidized bed,puluerised coal or other. • Sectch of furnace design with

3d design software, Which software is worth in learning for upcoming techno...

Which software is worth in learning for upcoming technologies in mechanical field?

Show seismic loads for ground supported equipment, Q. Show Seismic Loads Fo...

Q. Show Seismic Loads For Ground Supported Equipment? V = C s W is the governing equation for horizontal seismic base shear of ground supported equipment. C s  = 1.2A v S/(RT

Organization structure and design, Describe, using examples, what is meant ...

Describe, using examples, what is meant by job specialization, identifying it advantages and disadvantages.

Correction couple, what is correction couple&why it is needed

what is correction couple&why it is needed

Determine the loss of information during exchange in iges, Determine the Lo...

Determine the Loss of Information During Exchange in IGES Loss of Information During Exchange : Information would inevitably be lost when information is passed between two CAD

Solve equation by gauss elimination method, Solve the following equation by...

Solve the following equation by Gauss elimination Method : 2x + y + z = 10, 3x + 2y + 3z = 18; x +4y +9z = 16 Solve by Gauss-Seidal iteration method: 20x + y - 2z = 17; 3x

Flux cored arc welding, Flux Cored Arc Welding Single Pass F illet Weld...

Flux Cored Arc Welding Single Pass F illet Welds upto (8.0 mm) maximum and groove welds made with a single pass or a single pass each side, may be made using an E70T-X electrod

Evaluate the reaction at support, Evaluate the reaction at support: Q...

Evaluate the reaction at support: Q: Find out the reaction at support as shown in figure given below     First draw FBD of the system as shown in the given figur

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd