Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Up milling and down milling, table representing the differences between up ...

table representing the differences between up milling and down milling

Thermodynamics project , ES 347 - Thermodynamics Project Assigned: 3/28/201...

ES 347 - Thermodynamics Project Assigned: 3/28/2013 Due: 4/25/2013 Problem specification 5 kg of air is contained in a piston-cylinder device, initially at a pressure of 2MPa and a

Evaluate the inclination of the slotted bar, In a slotted and crank lever q...

In a slotted and crank lever quick return motion mechanism, the distance between the fixed centres is 240 mm and the length of the driving crank is 120 mm. Evaluate the inclination

Significance of damping coefficient, Physical significance of damping coeff...

Physical significance of damping coefficient and it''s unit.

Capp for forming processes, CAPP for Forming Processes Sheet metal par...

CAPP for Forming Processes Sheet metal parts are produced from flat sheets on presses using special metal forming dies. Process planning for sheet metal parts involves complex

Determine the angular-velocity of uniform bar, Determine the angular-veloci...

Determine the angular-velocity of uniform bar: A uniform bar of length l and mass M is hinged at its end B and is released from its horizontal position BA. Determine its angul

Steam, what is dry ness fraction?

what is dry ness fraction?

Find a relationship chart , A manufacturing facility consists of five depar...

A manufacturing facility consists of five departments, 1, 2, 3, 4 and 5. It produces four components having the manufacturing product routings and production volumes indicated in t

Describe organic binders and its working, Q. Describe Organic binders and i...

Q. Describe Organic binders and its working? Organic binders: The binders are most frequently used in core making. Cereal binders are obtained from wheat, corn or rye; resins

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd