Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine a static feedforward controller, By operation of the distillation...

By operation of the distillation columns you are often interested to maintain output despite fluctuations in the composition, ex. feed composition and feed flow. One possible actua

Define current for electrical resistance welding, Q. Define Current for ele...

Q. Define Current for electrical resistance welding? - With other parameters kept constant, the temperature in resistance welding is regulated by controlling the magnitude a

If engine does not start at cranking speed troubleshooting , If Engine Does...

If Engine Does Not Start at Cranking Speed Causes of Problem Remedy Incorrect electrode gap of spark plug Fouled spar

Illustrate the inversions of a double slider crank chain, Draw and Illustra...

Draw and Illustrate all the inversions of a double slider crank chain. Get an expression for the length of a belt in 1. an Open belt drive ;  And 2. a Cross belt drive.

How to observe water level, Q. How to observe water level? Site for ins...

Q. How to observe water level? Site for installing gauges should be properly selected. The reach should be reasonably straight and of uniform cross· section and slope. The leng

Determine fraction of the load would cnt fibers carry, Carbon nanotubes (CN...

Carbon nanotubes (CNTs) with low weight (density = 1.3 g/ cm^3), high tensile strength (50 GPa), and modulus of elasticity (1 TPa) in the axial direction have been touted as the st

Isothermal transformation, Isothermal Transformation: Austenite is no...

Isothermal Transformation: Austenite is not normally converted in martensite instantly but the procedure continues for some time. Various steels take various time for full tr

Two Stage Reciprocating Air Compressors, How does the Two Stage Reciprocati...

How does the Two Stage Reciprocating Air Compressor works?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd