Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

CIM, CIM in architecture?

CIM in architecture?

Motorcycle repairing, In MOTORCYCLE REPAIRING we have gone through various ...

In MOTORCYCLE REPAIRING we have gone through various complaints related to engine starting, problem related to gear, clutch, etc. and their possible reasons of trouble making. The

Define a crm and what are its uses, The process of learning more about clie...

The process of learning more about clients needs such as information about customers , sales, marketing effectiveness, responsiveness and market trends is called as Customer Relati

Scope of thermodynamics in thermal engineering, Scope of thermodynamics in ...

Scope of thermodynamics in thermal engineering Sol: Thermal engineering is a very important associate branch of mechanical, metallurgical, aerospace, chemical, marine, auto

Stress-strain carves for ductile materials, Stress-strain carves for ductil...

Stress-strain carves for ductile materials: A material is said to be ductile in nature, if it elongates before fracture. One this type of material is mild steel. Shape of stre

Flow work and flow energy - thermodynamics, Flow Work and Flow Energy - the...

Flow Work and Flow Energy - thermodynamics: Flo w Work:  The flow work is energy needed to move the working substance against its pressure It is called as flow or displac

Balancing of several masses rotating in different planes, The crank shaft o...

The crank shaft of a high speed pump has a parallel shaft of 2.5 cm diameter and 48 cm in length. It carries three eccentrics each of 6 cm in diameter and uniform thickness of 1.8

Type of lubrication systems , Type of Lubrication Systems The complete...

Type of Lubrication Systems The complete lubrication of a vehicle can be divided into two systems. (a) Engine lubrication system. (b) Chassis lubrication system.

Determine the minimum thickness required, Determine the minimum thickness r...

Determine the minimum thickness required: A thin spherical shell of 2 m diameter is subjected to an internal pressure of 1.5 N/mm 2 . If the allowable tensile stress of the ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd