Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

.VIABRATIONS, WHAT IS DAMP VIBRATION FACE ANGLE SIMPLE HARMONIC MOTION NAT...

WHAT IS DAMP VIBRATION FACE ANGLE SIMPLE HARMONIC MOTION NATURAL CIRCULAR FREQUENCY FORCE VIBRATION

Evaluate the diameter of bar, As a student engineer illustrate what design ...

As a student engineer illustrate what design consideration you would like to account for parts manufactured by machining and forging. A circular bas of 500mm length is hinghed f

Find out the proof load in close coiled helical spring, Find out the proof ...

Find out the proof load in close coiled helical spring: A close coiled helical spring is built of 6 mm diameter wire. The coil diameter is equal to 80 mm, number of coil is 10

Stresses., temparature stresses in composite bars

temparature stresses in composite bars

Tensile testing of Fibre, What is the relation between break point elastici...

What is the relation between break point elasticity and Yield point elasticity.?

Applications, applications of dynamically induced emf

applications of dynamically induced emf

Working of davis steering gear process, (a) What do you understand by steer...

(a) What do you understand by steering gear ? Explain with a clean sketch the working of Davis steering gear process. Also show the required equation between wheel base and distanc

Jet pump, full detail of jet pump nozzle design

full detail of jet pump nozzle design

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd