Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine the forces in all the members of the truss, A truss of span 10 me...

A truss of span 10 meters is loaded as shown in Figure. Determine the forces in all the members of the truss by Method of Joint.

Gun fires - projectile motion, Gun fires - projectile motion: A gun fi...

Gun fires - projectile motion: A gun fires a projectile along with a muzzle velocity of 300 m/sec as illustrated in Figure. Find its angle of inclination so that it strikes a

Find the maximum torque - i-section, Find the maximum torque - I-section: ...

Find the maximum torque - I-section: An I-section 150 × 80 mm has flanges 6 mm thick and web 4 mm thick. Discover the maximum torque that may be safely applied if the shear st

Determine reactions on compound beams , Determine reactions on compound bea...

Determine reactions on compound beams: Determine reactions at the support A , B , C , and D for arrangement of compound beams shown in the figure given below.

Part contact states, Part Contact States The loading, movement and unlo...

Part Contact States The loading, movement and unloading of parts via the manufacturing system should be scheduled through supervisory computer. In contrast along with classical

Dislocation, Diff. B/w edge and screw dislocation

Diff. B/w edge and screw dislocation

Find out the average resistance of the ground, Find out the average resista...

Find out the average resistance of the ground: In a construction of pile-driving for building, a pile driver of mass 25 kg freely drops through a height of 3 metre on the top

Compute the outside diameter of the shaft, Compute the outside diameter of ...

Compute the outside diameter of the shaft: A hollow shaft of diameter ratio is 0.4 is needed to transit 600 kW at 120 rpm. The maximum torque being 20% greater than the mean t

Determine the reactions at beam, Determine the reactions at bea: A can...

Determine the reactions at bea: A cantilever AB, 1.8 m long is fixed at A and carries uniformly distributed load of 20 kN/m over its entire length and a point load of 30 kN at

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd