Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Velocity ratio for open belt drive, V elocit y Ratio for Open Belt Drive:...

V elocit y Ratio for Open Belt Drive: Figure Consider a simple belt drive (that is one driver and one follower) as shown in the figure given below Let D 1

Final project , Hi ... I have a final project I need to finish it soon abou...

Hi ... I have a final project I need to finish it soon about 3 weeks from now ... to design any machine by the Solidworks program .... please feed me back if you can .. thank you

Crankshaft design, i have designed a crankshaft for 3 cylinder engine i wan...

i have designed a crankshaft for 3 cylinder engine i want to know how to balance it

Erosion-corrosion in steam service, Q.What is Erosion-Corrosion in Steam Se...

Q.What is Erosion-Corrosion in Steam Service? Depending on the steam quality, Let-down valves are subject to erosion-corrosion when pressure drop exceeds 1000kPa. Hard facing i

Resultant of coplanar concurrent force system, Resultant of coplanar concur...

Resultant of coplanar concurrent force system: The resultant force, of given system of forces can be found out by the resolution method, which is discussed below: Assume th

Theoretical results-conventional priority rules, Theoretical Results I...

Theoretical Results In the particular machine case, several theoretical results are identified or can be derived: (a) If each operation can be scheduled such that everyone

Engine oil replacement procedure, Engine oil replacement Motorcycle i...

Engine oil replacement Motorcycle is thoroughly drained by kicking the vehicle several times. Inspect the drain bolt washer and replace if necessary. Tighten the drai

Turbines, Illustrate governing Mechanism of Francis turbine.

Illustrate governing Mechanism of Francis turbine.

Level of safety organization, Level of Safety Organization This level ...

Level of Safety Organization This level comprises representatives of safety departments working at shop floor level or along with workers. The personnel will in fact implement

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd