Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine the maximum vertical load, It shows the test rig for the assignme...

It shows the test rig for the assignment of an indeterminate structure at the Materials Lab. The indeterminate structure consists of three pin-jointed members made of the same stee

Calculate the response of the system, A Spring - mass system which is subje...

A Spring - mass system which is subjected to a harmonic force FCoswt. calculate the response of the system, refer figure Given x (0) = 0.01 m x(0) = 0.04 m/sec w = 30 rad/

Determine force on a body to pull or push, Determine force on a body to pul...

Determine force on a body to pull or push: Q: A wooden block having weight of 50N rests on the horizontal plane. Determine force required which is acted at an angle of 15° to

Soldering, Soldering This is a group of join process, which generates, co...

Soldering This is a group of join process, which generates, coalescence of materials by heating them to a suitable temperature and by using a filler metal having a melting point

Carnot cycle, what is mimnimum data for modelling a unique carnot cycle

what is mimnimum data for modelling a unique carnot cycle

Welding, what is the average speed of travel in gas tungsten arc welding

what is the average speed of travel in gas tungsten arc welding

Show the procedure of compute flange stresses, Q. Show the Procedure of Com...

Q. Show the Procedure of Compute flange stresses? Compute flange stresses and the actual bolt stress using: - COLT values for gasket seating stress, ‘y' and the gasket facto

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd