Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Construct a plain scale, Construct a plain scale: The distance between...

Construct a plain scale: The distance between Indore and Bhopal is 180 kilometer. It is represented on the map via 9 centimeter. Construct a plain scale for such map, illustra

Find the maximum permissible, A wooden cylinder (specific gravity = 0.6) of...

A wooden cylinder (specific gravity = 0.6) of circular cross - section having length L and diameter D floats in water. Find the maximum permissible (L/D) ratio so that the cylinder

Bevel gear, What is the face cone. Difference between tooth face and face ...

What is the face cone. Difference between tooth face and face cone?

Projection welding, Projection Welding Projection welding is similar to...

Projection Welding Projection welding is similar to spot welding but for the fact that the welding takes place at the projections on the surface of the metals and flat shaped e

Compute the outside diameter of the shaft, Compute the outside diameter of ...

Compute the outside diameter of the shaft: A hollow shaft of diameter ratio is 0.4 is needed to transit 600 kW at 120 rpm. The maximum torque being 20% greater than the mean t

Carburettor in motorcycle, Carburettor: It supplies the air fuel mixture a...

Carburettor: It supplies the air fuel mixture at varying proportions that suits the changing operating conditions of motorcycle. The carburettors for 100 cc and 125 cc motorcycle

Principle of equilibrium - mechanics, Principle of equilibrium: Sol.:...

Principle of equilibrium: Sol.: Principle of equilibrium can be divided in to three main parts; (1) Two Force Principle: As the Resultant is zero when body is in equili

Design lay-down areas for plant, Q. Design lay-down areas for plant? De...

Q. Design lay-down areas for plant? Designated lay-down areas are areas specifically positioned to enable equipment maintenance to be carried out. These are normally assigned f

Pseudo force, why we feel increase in weight when elevator goes up?

why we feel increase in weight when elevator goes up?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd