Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Plastic material and rigid plastic material, Plastic material and rigid pla...

Plastic material and rigid plastic material: For the plastic material, there is stress at which plastic deformation begins. A rigid plastic material is one in which the ela

Slidercrank, connecting rod AB of length L support a variable compressiv fo...

connecting rod AB of length L support a variable compressiv force F .Drive an expression for the moment of F about the crank axis O in the term of F L r and angle

Problems on structural design of combined footings, Problems on Structural ...

Problems on Structural Design of Combined Footings a. Two columns 50 cm x 50 cm in size support service loads of 1200kN and 800kN.The centre to centre spacing between columns

Calculate the mechanical output power, A 415 V, 5 kW, 50 Hz, 4-pole, 3-phas...

A 415 V, 5 kW, 50 Hz, 4-pole, 3-phase wound-rotor induction motor has the following characteristics:  Stator winding resistance R 1 = 2.1 Ω, Referred rotor windi

Rotary converters, ROTARY CONVERTERS Historically, these type of power so...

ROTARY CONVERTERS Historically, these type of power sources were developed first for arc welding applications and even now these types are popular. These rotary converters are of

Air filter cleaning steps, Air Filter Cleaning :  Air filter filters the a...

Air Filter Cleaning :  Air filter filters the air, which enters into the carburetor. Then, this air mixes with fuel and this mixture enters into engine. If air is not clean, it wi

Define yoke or magnetic frame - dc generator, Yoke or magnetic frame It...

Yoke or magnetic frame It is the outer cover of the machine. An even number of pole cores are bolted to the yoke. Its serves the following purposes 1. It gives mechanical su

Equiliubrium, Review questions condition of equilibrium grade 11 unit 7

Review questions condition of equilibrium grade 11 unit 7

Define the application of hydrostatic sensor paver machine, Application of ...

Application of Hydrostatic sensor paver machine The Hydrostatic sensor paver machine that is used for lying bituminous Mixed material, roll-down or lean-mixed concrete, track-

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd