Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Evaluate the specific enthalpy - thermodynamics, Evaluate the specific enth...

Evaluate the specific enthalpy - thermodynamics: Steam is being generated in a boiler at a pressure of 15.25 bar. Calculate the specific enthalpy when ( i )  Steam i

Describe cutting ratio - shear plane and shear angle, a) Define various typ...

a) Define various types of chips and factors responsible for their formation with diagram b) Describe cutting ratio, shear plane and shear angle. c) Sketch Merchant circle di

Determine the wire drawing - cold drawing processes, Determine the Wire Dra...

Determine the Wire Drawing - cold drawing processes Similar to above process bars are first pickled, washed and coated to prevent any oxidation. After this rods are passed t

Need of alternate conceptual system design, What do you mean by Management ...

What do you mean by Management Information System (MIS)? What are its advantages ? Also give the qualities of an ideal MIS. What is the basic need of alternate conceptual system

Hinged support, Hinged Support: Hinged (Pin) Support: At hinged end,...

Hinged Support: Hinged (Pin) Support: At hinged end, beam cannot move in any direction support will not develop any resisting moment, but it can develop reaction in any of t

Closed system - thermodynamics system, Closed System: The system tha...

Closed System: The system that can exchange energy with the surrounding but not the mass. The quantity of matter hence remains fixed. And the system can be described as cont

Standard factory formed insulation on flanges and valves, Q. Standard facto...

Q. Standard factory formed insulation on Flanges and Valves? All fittings are to be insulated with standard factory formed insulation. All joints shall be buttered and sealed.

Branches of mechanics, Branches of mechanics: Mechanics is basically d...

Branches of mechanics: Mechanics is basically divided in to two parts Static's and Dynamics, Dynamics is further divided in kinematics and kinetics Statics: It deals with

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd