Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

About Transfer Function block, How can i change the normal function block p...

How can i change the normal function block parameter[1 1]=>(s+1) to (s-1)?

Computation for the magnitude, A horizontal line ABCD measuring 9m is acted...

A horizontal line ABCD measuring 9m is acted upon by forces of magnitude 400, 600, 400 and 200 N at points A, B, C, D respectively with downward direction. These point are so locat

Gravitation, What is the clear difference between gravitational potential a...

What is the clear difference between gravitational potential and gravitational potential energy ? Ans) A body A of mass m is placed in the gravitational field of a body B of mass

Express the compression force of hydraulic cylinder, Express the compressio...

Express the compression force C in the hydraulic cylinder of the car hoist in terms of the angle Θ, see Fig Q3. The mass of the hoist is negligible compared with the mass of the ve

Piston rings-basic components of engine , Piston Rings: Piston rings (Fig...

Piston Rings: Piston rings (Figure), fitted into the grooves around the piston, provide a tight sealing effect between the piston and the cylinder wall thus preventing leakage of

Explain degree of freedom - jig and fixture, Explain Degree of Freedom - Ji...

Explain Degree of Freedom - Jig and Fixture The complete location of components inside a jig or fixtures can be understood with the help of figure. The work piece is a

Define the boundary representation of solids, Define the Boundary Represent...

Define the Boundary Representation of solids Boundary model or b-rep model is based on the topological notion that a physical object is bounded by a set of faces. These faces a

Describe natural and synthetic sand, Q. Describe Natural and Synthetic Sand...

Q. Describe Natural and Synthetic Sand? Natural sand: A natural sand is the on which is available from natural deposits. Only assistive and water need to be added to it to ma

Determine initial tension in the belt, A flat belt, 8 mm thick and 100 mm w...

A flat belt, 8 mm thick and 100 mm wide transmits power between two pulleys, running at 1600 m/min. The mass of the belt is 0.9 kg/m length. The angle of lap in the smaller pulle

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd