Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Nitrogen storage and vaporizer, Q. Nitrogen storage and vaporizer? Bulk...

Q. Nitrogen storage and vaporizer? Bulk cryogenic storage of nitrogen must be located away from process equipment, preferably at the edge or corner of the process area where fi

Determine reactions force, Determine reactions force: Thr e e spher...

Determine reactions force: Thr e e sphere A , B and C weighing 400N, and 200N and having radii 400mm,  600mm and 400mm respectively are placed in trench as shown in t

Find out moment of inertia, Find out Moment of Inertia: Find out Momen...

Find out Moment of Inertia: Find out Moment of Inertia of an I shaped area around its centroidal axis as illustrated in Figure.  Solution  (i)        The area of

Design analysis drafting machine, hello,my name is mustapha from iran I wa...

hello,my name is mustapha from iran I want design piston engine (structure design cranckshaft ,rod,bearing,...)

Explain the conventional frame, Show schematic diagram showing the layout o...

Show schematic diagram showing the layout of transmission system of four-wheel driven car. Explain briefly the following types of frame: (a) Conventional frame (b) Integra

Calculate the time required to complete the job, Five jobs are performed fi...

Five jobs are performed first-on Machine-I and then on Machine-II. Time in hours taken by each job on each machine is given below :

Hill roads - road under special conditions, Hill Roads: Alignment ...

Hill Roads: Alignment Selection and Geometric Design Standards Here, you have already learnt how an alignment of a hill road has to be selected. The selection of a g

Objectives to service sector , Objectives After studying this unit, yo...

Objectives After studying this unit, you should be able to discuss the scope and extent of service industry, describe the phases of two wheeler industry growth, an

Dryness fraction of steam - thermodynamics, Drynes s Fraction of Steam: ...

Drynes s Fraction of Steam: Dryness fraction of steam is factor which used to specify the quality of steam. It can be defined as the ratio of weight of dry steam W d s pr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd