Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Torsion of a cylinder, Torsion of a Cylinder Let a cylinder of length  ...

Torsion of a Cylinder Let a cylinder of length  l  and radius  R  be clamped at one end and twisted at the other end by applying a torque τ about the axis of the cylinder. Each

Cases of equilibrium , Cases of equilibrium: What are cases of equili...

Cases of equilibrium: What are cases of equilibrium? Sol.: As a result of the acting forces, the body may be having one of the following states: (1) The body can mo

Calculate the minimum thickness, A circular thin steel diaphragm having an ...

A circular thin steel diaphragm having an effective diameter of 20mm is clamped around its periphery and is subjected to a uniform gas pressure of 180kN/m^2. Calculate the minim

Lubrcants, what is the difference between mineral and vegetable oils in ter...

what is the difference between mineral and vegetable oils in terms of oiliness and oxidization?

Find out the centre of gravity of a wire, Find out the centre of gravity of...

Find out the centre of gravity of a wire: Find out the C. G. of a wire of uniform cross-section bent into shape of a semicircle as illustrated in Figure. Solution

Clutch complaints by repairing of motorcycle , Clutch Complaints Natur...

Clutch Complaints Nature of complaints could be that of following : (a) Clutch judder (jerking) (b) Clutch slipping (c) Half clutch noise

Problems on cantilever truss, Problem s on Cantilever Truss: In the c...

Problem s on Cantilever Truss: In the case of cantilever trusses, it is not required to determine the support reactions. The forces in members of cantilever truss are obtaine

Shaft in parallel, SHAF T IN PARALLEL: SHAF T IN PARALLEL: The sh...

SHAF T IN PARALLEL: SHAF T IN PARALLEL: The shaft are in parallel when the driving torque is applied at the junction of shafts and resisting torque is at other ends of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd