Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Organisation set-up - construction of railway line, Organisation set-up: ...

Organisation set-up: The civil engineering department of the Railways is responsible for the maintenance of railway lines. The maintenance organisation consists of Chief Engi

Calculate the length of plastic deformation, Calculate the length of plasti...

Calculate the length of plastic deformation: Calculate the length of plastic deformation along 45 o in case the applied stress σ is 63.25% of yield stress in the plate of abo

What are the capabilities of step, What are the capabilities of STEP In...

What are the capabilities of STEP Industry-Developed STEP Capabilities AP-203, Configuration Control for 3D Design of Mechanical Parts and Assemblies, provides a very robust

Compute the displacement of the particle, Compute the displacement of the p...

Compute the displacement of the particle: The acceleration time diagram for particle is as specified below .Computed velocity of the particle at several time intervals, plot v

Cylinder block-basic components of engine , Cylinder Block: This serves a...

Cylinder Block: This serves as an enclosure to the cylinder. The cylinder is an integral part of cylinder block in 100 cc motorcycle. Figure : Cylinder Block

Applications, applications of dynamically induced emf

applications of dynamically induced emf

Various properties of lubricant , Various Properties of Lubricant Vi...

Various Properties of Lubricant Viscosity: The property of lubricant which is a measurement of the internal friction of lubricating oil is called its viscosity. The vi

Wave motion, Wave motion takes place all throughout nature, from the waves...

Wave motion takes place all throughout nature, from the waves of the ocean to the electromagnetic waves that comprise visible light. Though different types of waves involve differe

Advance dynamics, Ask question i have an assisgment can you please tell me ...

Ask question i have an assisgment can you please tell me how much does it cost #Minimum 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd