Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Governor, what is the formula of sensitivity of governor?

what is the formula of sensitivity of governor?

Show the geometric similarity, Q. Show the Geometric Similarity? When m...

Q. Show the Geometric Similarity? When model is required to provide an aid merely for visualisation, scaler reproduction of form is sufficient which is termed Geometric Similar

Determine the thermal efficiency of cupola, With the help of neat diagrams ...

With the help of neat diagrams explain various parts of Cupola. Define its operation. How the thermal efficiency of Cupola calculated? What do you mean by Die casting process? G

Performance criteria-aspects of scheduling , Performance Criteria This ...

Performance Criteria This is assumed that an FMS is the part of a superior production process. Consequently the performance of the FMS is not a major goal but imply to attain c

Thermodynamics, show that work is a path function and not a point funtion ?...

show that work is a path function and not a point funtion ?

Determine the change in diameter, Determine the change in diameter: A ...

Determine the change in diameter: A thin spherical shell of 1.8 m diameter is 10 mm thick. This is filled with a liquid so that the internal pressure is 1 N/mm 2 . Determine t

Show oil production, Q. Show Oil production? Bitumen emulsion from fiel...

Q. Show Oil production? Bitumen emulsion from field enters into the CPF emulsion inlet header. Depending on the emulsion temperature it may be cooled through two series exchang

Design of a bicycle frame, Design of a Bicycle Frame : Figure  depicts a si...

Design of a Bicycle Frame : Figure  depicts a simple bicycle frame, which is to be built of hollow aluminium tubing with outside diameter of 20 mm and wall thickness of 2 mm. The f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd