Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Excessive pedal pressure required motorcycle problem, If Excessive Pedal Pr...

If Excessive Pedal Pressure Required Causes of Problem Remedy Incorrect shoe placement Improper anchor pin position l

Drum brake-types of brake , Drum Brake: The construction of drum brake is...

Drum Brake: The construction of drum brake is clearly shown in Figure 2.40. In a rotating brake drum stationary brake shoes are attached concentric to the axle hub. A back plate

Welding, what is the average speed of travel in gas tungsten arc welding

what is the average speed of travel in gas tungsten arc welding

Find the stresses by finite method, The stepped bar in Fig Q6 is stretched ...

The stepped bar in Fig Q6 is stretched along the vertical axis and the maximum upward displacement is found to be 0.008 m. The bar has cross-sectional areas of A 1 and A 2 ov

Mechanical data for line designation tables, Q. Mechanical Data for Line De...

Q. Mechanical Data for Line Designation Tables? Line Designation Tables (LDT's) are initially generated by the Piping designers. Design conditions are inputed by the Process di

Third gear position - shifting of gear, Third Gear Position: When gea...

Third Gear Position: When gear M3 on the main shaft is in mesh with gear C3 on the counter shaft then this is known as third gear position. The fixed gear M3 rotates with mai

# ic engines, what are the di #Minimum 100 words accepted#

what are the di #Minimum 100 words accepted#

Illustrate different methods of merit rating, a) What are essential needs o...

a) What are essential needs of a job evaluation plan. Illustrate the point plan method b) Describe factor comparison method of job evaluation. a) What are basic objectives an

Contrary to the misconception, Contrary to the misconception that the grow...

Contrary to the misconception that the growth in automobile industry has catered only to the higher income-stratum of society by producing mostly passenger cars, the fastest growt

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd