Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Stress distribution diagram, why stress distribution diagram is different f...

why stress distribution diagram is different for I section, T section andcircular section?

Determine the stresses in the shell, Determine the stresses in the shell: ...

Determine the stresses in the shell: A thin spherical shell of 1.5 m diameter & 8 mm thickness is filled having a liquid at an internal pressure of 1.5 N/mm 2 . Determine the

FEM, assignment help needed

assignment help needed

Find the minimum weight to keep equilibrium, Find the minimum weight to kee...

Find the minimum weight to keep equilibrium: A belt supports the two weights W 1 an d W 2 over a pulley as shown in the figure given below. If W 1 = 1000N, fi

Determine radial and hoop stress, A hydraulic pipe is 20 cm internal diamet...

A hydraulic pipe is 20 cm internal diameter and 5 cm thick. It is needed to sustain an intensities of radial and hoop stress at several radii and plot their variation.

EM2013KEN2401MECH, Hi. I have made a payment for the above ticket number. W...

Hi. I have made a payment for the above ticket number. Will I get all the workings out too? [email protected]

Shielded metal arc welding (smaw), SHIELDED METAL ARC WELDING (SMAW) It...

SHIELDED METAL ARC WELDING (SMAW) It also known as Manual Metal Arc Welding (MMAW). The heat required for welding is generated by the electric arc formed between metallic elect

Cross belt drive, Cross Belt Drive: When shafts are rotating in the o...

Cross Belt Drive: When shafts are rotating in the opposite direction, cross belt drive can be obtained. Figure In the diagram given to us pulley 'A' is called as

Explain concepty of worktable in radial drilling machine, Explain concepty ...

Explain concepty of Worktable in radial drilling machine The worktable is supported on an arm mounted to the column. The worktable can be adjusted vertically to accommodate dis

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd