Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

State the postulates of special theory of relativity, State the postulates ...

State the postulates of special theory of relativity and deduce from them the Lorentz transformations. Define an inertial frame of reference and derive the Lorentz transformatio

Wedge problems, How to solve wedge problems..can anyone just explain the me...

How to solve wedge problems..can anyone just explain the method..

Advantage of electro chemical machining, Advantage of Electro Chemical Mach...

Advantage of Electro Chemical Machining 1. As the tool does not come in contact with the work there for tool wear is practically nil. 2. The metal removal is faster rate.

What are the principles of location of drilling jig, a) Define the degree o...

a) Define the degree of freedom of a work piece in space. What are the basic principles of location of drilling jig.

what do you mean by ignition system?, (a) What do you mean by ignition sys...

(a) What do you mean by ignition system? Write down its functions. (b) Briefly describe the working principle of ignition system. (c) How is energy generated inside the batte

Head loss, calculate the head required

calculate the head required

Evaluate the stresses in the steel and concrete bars, A load of 2MN is appl...

A load of 2MN is applied on a short concrete column 500 mm x 500 mm. The column is reinforced with four steel bars of 10 mm diameter, one in each corner. Evaluate the stresses in t

Flange bevel and lap ring weld, Q. Flange Bevel And Lap Ring Weld? The ...

Q. Flange Bevel And Lap Ring Weld? The fillet weld attaching the lap ring to the shell shall be an equal leg fillet weld, with the leg dimension equal to the nominal shell thic

Determine the length of arc, Data given for gear problem T P = 30 TG = ...

Data given for gear problem T P = 30 TG = 80 φ = 20o m = 12 mm Addendum = 10 mm then determine the length of path of contact, length of Arc of contact and contact Ratio.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd