Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Illustrate clay content test, Q. Illustrate Clay content test? Under th...

Q. Illustrate Clay content test? Under this test, the clay content is measured by washing it off the sand sample. The standard dried sand sample (50 gm) is put in a mixing devi

Motorcycle starts but stops suddenly motorcycle problems, If Motorcycle Sta...

If Motorcycle Starts but Stops Suddenly Causes of Problem Remedy The spark plug gets short-circuited by heating

Determine the brake mean effective pressure, A 4 cylinder petrol engine ope...

A 4 cylinder petrol engine operates on the 4-stroke cycle. The bore of each cylinder is 70mm and stroke 100mm. The clearance volume per cylinder is 60cm3. At a speed of 4000rpm, th

Isothermal compression, The critical Temperature of a gas is the highest te...

The critical Temperature of a gas is the highest temperature for which isothermal compression of the gas results in ? Will an adiabatic ?ash result in more, the same, or less va

What are the conditions where combined footings used, What are the conditio...

What are the conditions where combined footings used? Two conditions in which it is used are as: a. When an exterior column is immediately adjacent to a property or mechanic

Describe crank-pin effort, Describe the following terms:- a) Gyroscope ...

Describe the following terms:- a) Gyroscope b) Crank-pin effort c) Piston Effort d) Crank effort e) Thrust on crank shaft bearings.  f) Brake and Dynamometer g

Minimum design metal temperature, Q. Minimum Design Metal Temperature? ...

Q. Minimum Design Metal Temperature? The MDMT and coincident pressure shall be selected in consideration of the operating phases. Reliable administrative procedures to control

Conceptual engineering phase in project development, Q. Conceptual engineer...

Q. Conceptual engineering phase? During this phase, a conceptual engineering estimate will be prepared by Project Management with input from all disciplines. Activities at t

Welding procedure and performance qualification, WELDING PROCEDURE AND PERF...

WELDING PROCEDURE AND PERFORMANCE QUALIFICATION A total quality assurance scheme, embracing all aspects of manufacture would have necessarily made all attempts to ensure

Torsion , in the torsion equation the term j/r is called

in the torsion equation the term j/r is called

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd