Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Find out diameter of steel wire, Find out diameter of steel wire: Q: ...

Find out diameter of steel wire: Q: A load of 5 KN is to be raised with help of steel wire. Find out diameter of steel wire, if maximum stress does not to exceed 100 MNm 2

Safety considerations for storage tanks, Q. Safety considerations for stora...

Q. Safety considerations for storage tanks? Large storage tanks are potential fire hazards and should be located at a lower elevation than other occupancies to prevent liquids

Explain macroscopic approach - thermodynamics, Explain Macroscopic Approach...

Explain Macroscopic Approach - Thermodynamics 1. In this method a fixed quantity of matter is considered without taking into account the events taking place at molecular level.

Flow rate, how to calculate flow rate of liquid nitrogen? melting point(-21...

how to calculate flow rate of liquid nitrogen? melting point(-210deg) boiling point(-195.8deg) critical temp(-149.9deg) relative density(0.8) specific gravity(808.5kg/m^3) rel

Classification of cast iron, Classification of Cast Iron: CI having C...

Classification of Cast Iron: CI having C in form of cementite is named as white cast iron. Microstructure of that CI consists of pearlite, cementite and ledeburite. Whether C

Derive the finite element formulation-galerkin method, Derive the finite el...

Derive the finite element formulation  for a tapered bar element using Galerkin's method.                                                 1- Start with. 2- Use and as shap

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd