Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Gating system design, Explain the several types of pattern allowances with ...

Explain the several types of pattern allowances with neat sketch. Show the six important - aspects of gating system design. Illustrate briefly their functions.

Stress concentration factor, 1. Write a short note (not more than half A4 p...

1. Write a short note (not more than half A4 page) on your understanding on St. Venant's Principal for your engineering design analysis. 2.  Estimate the " Stress Concentration

What is mock-up testing, Q. What is Mock-up Testing? Tube to all tubesh...

Q. What is Mock-up Testing? Tube to all tubesheet weld tests shall be provided as described below. Mock-up of 10 tubes about 305 mm (12") long are welded to a portion of a t

AOC, The objective of the project is to protect damage of the DC motors. If...

The objective of the project is to protect damage of the DC motors. If the motor is not working it will be shown with red light, if working normally then green and if working at a

Determine maximum internal diameter of hollow shaft, Determine maximum inte...

Determine maximum internal diameter of hollow shaft: A solid shaft of mild steel which is 200 mm in diameter is to be replaced by hollow shaft of alloy steel for which the al

Equipment for resistance welding-protection, EQUIPMENT FOR RESISTANCE WELDI...

EQUIPMENT FOR RESISTANCE WELDING-Protection A circuit breaker can be provided (this equipment can be rated for interrupted capacity) which will cater to a number of resistance

Explain external pressure design, Q. Explain External Pressure Design? ...

Q. Explain External Pressure Design? Determine requirements for external pressure based on the expected operation of the vessel, and add a suitable operating margin to establis

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd