Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Quasistatic loading, • For the ASTM dogbone specimens, the ¾ inch hole spec...

• For the ASTM dogbone specimens, the ¾ inch hole specimens, and the notched specimen tabulate the failure load, in pounds. • Show plots of stress and strain for all specimens w

Diffrence between external diameter and internal diameter, Diffrence betwee...

Diffrence between external diameter and internal diameter: A compound tube is built by shrinking one tube on another, the ultimate dimension being, 80 mm internal diameter, 16

Determine the location of the hydraulic jump, A rectangular channel of widt...

A rectangular channel of width 12ft has an upstream slope of 0.02ft/ft and a downstream slope of 0.0005 ft/ft. Both reaches have lengths of 500 ft. The upstream reach has a Manning

What is tantalum, Q. What is Tantalum? Tantalum is one of the most corr...

Q. What is Tantalum? Tantalum is one of the most corrosion-resistant metals known. However, the high cost of tantalum has limited its commercial use as an all-purpose corrosio

Heat treatment of stainless steels, Heat Treatment of Stainless Steels: ...

Heat Treatment of Stainless Steels: Stainless steels, as other steels, react to heat treatments over broad range. They are subjected to one or more of the given heat treatmen

Two wheeler, how to adjust the motorcycle clutch play

how to adjust the motorcycle clutch play

Cantilevered beam, A cantilevered beam is to be made of 7075-T6 aluminum ...

A cantilevered beam is to be made of 7075-T6 aluminum with a uniaxial yield strength of 469 MPa. The beam is 1m long, and is loaded with the following limit loads: a bending mome

Machine drawing, Sketch neatly two views of a footstep braring for supporti...

Sketch neatly two views of a footstep braring for supporting a 50mm diameter vertical shsft. Give important dimensions

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd