Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Determine the angular-velocity of uniform bar, Determine the angular-veloci...

Determine the angular-velocity of uniform bar: A uniform bar of length l and mass M is hinged at its end B and is released from its horizontal position BA. Determine its angul

Tensile and compressive force - mechanics, Tensile and Compressive Force: ...

Tensile and Compressive Force: T ensil e Forces A force, that pulls the body, is called as tensile force. Here member AB is tension member carrying tensile force P. As

Force exerted by jet on an fixed vertical plate, Show that the force exerte...

Show that the force exerted by jet of water on a fixed semi-circular plate in the direction of jet when the jet strikes at the centre of the semi-circular plate is two times the fo

Effect of individual alloying elements, Effect of Individual Alloying Eleme...

Effect of Individual Alloying Elements: Sulfur Sulfur is not a needed element in steel since in interferes along with hot rolling and forging resulting in hot-shortness

Describe about push-pull welds, Q Describe about Push-pull welds? - A ...

Q Describe about Push-pull welds? - A push-pull system employs transformers with an electrically reversed polarity arrangement wherein two transformers complement each o

What is the maximum load the spring may carry, What is the maximum load the...

What is the maximum load the spring may carry: Any close coiled helical spring has mean diameter of 80 mm, has spring constant of 100 kN/m. It contains 10 coils. The maximum s

Motorcycle servicing , In motorcycle servicing we studied about various ser...

In motorcycle servicing we studied about various service tips for motorcycle servicing. These steps will ensure proper servicing of motorcycle and as a result customers will trust

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd