Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Evaluate tension in the string, A smooth sphere of radius 15 cm and weight ...

A smooth sphere of radius 15 cm and weight 2 N is supported in contact with a smooth vertical wall by a string whose length simlar the radius of sphere. The string joins a point on

Fluids, show a schematic circuit diagram of a electric hydraulic gear pump...

show a schematic circuit diagram of a electric hydraulic gear pump with adjustable with one direction flow and explain the operation

Maintenance operations, Maintenance Operations: The maintenance opera...

Maintenance Operations: The maintenance operations cover various activities such as: (a) making good rain cuts in embankment, (b) clearing the side ditches of vegetatio

Force exerted by a jet of water on an inclined fixed plate, (a) Show that t...

(a) Show that the force exerted by a jet of water on an inclined fixed plate in the dissection of jet is provided by fx = .a.v 2 . sin2θ. Where a is area of jet, v is velocity of j

Record keeping, Record Keeping Systematic process for collecting info...

Record Keeping Systematic process for collecting information on employees health, working conditions and any accident requirement be established in a company. Various differe

Operation research, what are the significance and scope of operations resea...

what are the significance and scope of operations research

Can you implement compatibility test, Q. Can you implement Compatibility te...

Q. Can you implement Compatibility test ? This test indicates the decrease in height of a mass of sand in a specimen tube with respect to its original height, under the actio

What do you mean by rigid bed models, Q. What do you mean by Rigid bed mode...

Q. What do you mean by Rigid bed models? Models with rigid boundary and geometrically similar form are used in studies connected with outlet works, stilling basins, spillways

Find out angular displacement of a partical, Find out angular displacement ...

Find out angular displacement of a partical: The angular displacement of a rotating body starting from rest is defined by φ (t ) = 4 t 3   - 3 t 2 . Find out its angular di

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd