Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Pressure - thermodynamics, Pressure - Thermodynamics: While working in...

Pressure - Thermodynamics: While working in the system, thermodynamic medium exerts a force on boundaries of vessel in which it is kept. The vessel may be a container, or an e

Inlet and exhaust valves-basic components of engine , Inlet and Exhaust Val...

Inlet and Exhaust Valves : Valves are commonly mushroom shaped poppet type. They are provided on the cylinder for regulation of the charge coming into the cylinder (inlet valve)

Explain the deformation processes, Deformation Processes In these proce...

Deformation Processes In these processes, the material is plastically deformed (hot or cold) under the action of an external force, to produce the required shape. No material i

What are the forces acting on foundations, What are the Forces Acting on Fo...

What are the Forces Acting on Foundations Foundations are normally subjected to vertical loads which are resisted by compressive stress generated in the soil. However, the acti

Mechanical Engineering Careers Incorporating the Outdoors, Are there jobs i...

Are there jobs in the field of Mechanical Engineering that incorporate the outdoors? I am an outdoorsman for one, and a tradesman at heart and am currently a Mechanical engineering

Objectives-computerized scheduling and control manufacturing, Objectives ...

Objectives After studying this section, you should be familiarized about: The typical job shop scheduling problem, Characteristics of computer controlled scheduling,

Determine the magnitude and nature of the stresses, Determine the magnitude...

Determine the magnitude and nature of the stresses: A thin spherical hollow steel shell of 400 mm diameter & 5 mm thickness is immersed into a liquid container pressurized to

Determine the thermal conductivity, A rod of 80mm diameter and 10mm length ...

A rod of 80mm diameter and 10mm length with thermal conductivity 16W/m-deg protrudes from a surface at 160 o C. The rod is exposed to air at 30 o C with convective coefficient of

What do you mean by bunds and dikes, Q. What do you mean by Bunds and Dikes...

Q. What do you mean by Bunds and Dikes ? A bund (or dike) is an embankment or wall of brick, stone, concrete or other impervious material, which surrounds the entire perimeter

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd