Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

What is floating foundation, What is floating foundation? Floating Foun...

What is floating foundation? Floating Foundation: Raft or mat is also recommended when the soil mass contains compressible layers or the soil stratum is variable. In such ca

Determine frequency of free oscillations, (a) Illustrate critical damping a...

(a) Illustrate critical damping and its uses. (b) A horizontal spring mass system with coulomb damping has a mass of 5 Kg attached to a spring of stiffness 1KN/m. if the coeffic

What do you mean by filler metals, Q. What do you mean by Filler metals? ...

Q. What do you mean by Filler metals? Use filler metal that is similar in chemistry, corrosion resistance, and mechanical properties of the base metal being welded. Filler m

Define edm machine under varying cutting condition, EDM Machine under varyi...

EDM Machine under varying Cutting Condition a) All the experiments have been conducted on a Z numerically controlled (NC) oil die- sinking EDM Machine. b) The EDM Machine is

Thermodynamic properties , Q= In an investigation of the thermodynamic prop...

Q= In an investigation of the thermodynamic properties of alpha-manganese,the following heat contents determined H 700  - H 298 = 2895 cal/g-atm H 1000 - H 298 = 5450 cal

Induction machine operation, Induction Machine Operation For operation ...

Induction Machine Operation For operation with rated L-L voltage of 230 V and rated frequency of 60 Hz, the performance of a particular 10 hp machine at its rated speed and pow

Composities, example with its properties

example with its properties

Kinetics, Kinetics: Define Kinetics. What is plane motion? Sol: ...

Kinetics: Define Kinetics. What is plane motion? Sol: Kinetics is that branch of mechanics, which deals with force system that produces acceleration and resulting motio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd