Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Explain the principle of screw conveyer, Explain the Principle of screw con...

Explain the Principle of screw conveyer When materials are feed into the fixed chutes, due to action of gravity of materials and the friction force between material and chute t

Calculate the depth of water, (Buoyancy of a submerged body; compressibilit...

(Buoyancy of a submerged body; compressibility of air) A grade 4 science student inverts a cup full of air into a water tank. If it takes 1 lb of force to hold the cup down 3

Evaluate piston effect, In a double acting vertical steam engine running at...

In a double acting vertical steam engine running at speed of 360 r.p.m., cylinder diameter is 25 cm, stroke is 30 cm, diameter of piston rod is about 3.75 cm and length of the conn

Pseudo force, why we feel increase in weight when elevator goes up?

why we feel increase in weight when elevator goes up?

Find the twist of a circular hollow shaft, Find the twist of a circular hol...

Find the twist of a circular hollow shaft: Discover the twist per metre length of a circular hollow shaft having 120 mm outer diameter and 90 mm inner diameter, respectively,

Carbon fibers, 3. The tensile modulus of elasticity of a unidirectional car...

3. The tensile modulus of elasticity of a unidirectional carbon-fiber-reinforced-plastic composite material that contains 64 percent by volume of carbon fibers and is stresssed und

Determine a real root of the equation, Determine a real root of the equatio...

Determine a real root of the equation xlog10 x = 1.2 by regula-falsi method correct to four decimal places.

Derive eulers equation of motion, (a) Reduce expression for the net pressur...

(a) Reduce expression for the net pressure and depth of centre of pressure in case of an inclined plan surface submerged in a fluid. (b) Derive Euler's equation of motion along

Sketch merchants force diagram, Merchants force diagram. State the assumpti...

Merchants force diagram. State the assumptions made in development of such diagram.

Find out the modulus of elasticity, Find out the modulus of elasticity: ...

Find out the modulus of elasticity: A unidirectional FRP is produced with fibre volume ratio of 60%. The density of fibre is 1480 kg/m 3 and that of matrix is 1200 kg/m 3 . C

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd