Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Shear forces and bending moments, Shear Forces and Bending Moments: ...

Shear Forces and Bending Moments: A beam is a structural member, subjected to a system of external forces (involving inclined load) to generate the bending of the member in

What are commercial aircraft mfg key success factors, Conduct an industry &...

Conduct an industry & a 5-Forces analysis for BOEING AND AIRBUS. w/focus on commercial aircraft mfg (Hint: extend POV to travel preferences now & future, & review BOE/Air's POVs on

Mr, I need rewording

I need rewording

Determine the value of the weight, Illustrate with working, construction an...

Illustrate with working, construction and measurement of brake power by Belt transmission type brake dynamometers? The essential features of a transmission dynamometer are show

TTT of effective normalizing of Ductile tiron, At 1500 degrees F, how much ...

At 1500 degrees F, how much time is required to effectively normalize ductile iron

Steam turbine, Stea m Turbine: INTRODUCTIO N:   Steam turbine is ch...

Stea m Turbine: INTRODUCTIO N:   Steam turbine is chief mover in which rotary motion can be obtained by a gradual change of momentum of steam. The force exerted on blade is

Convolution Integral, For a transfer function graph with h(t) on the y-axis...

For a transfer function graph with h(t) on the y-axis and time in seconds on the x-axis, the h(t)=1 from 0 to 2 seconds, while h(t)=0 everywhere else. How do I graph the unit step

Design bulk materials storage, Q. Design Bulk Materials Storage? Consid...

Q. Design Bulk Materials Storage? Consideration shall be given to providing access to safety showers in areas of hazardous bulk material handling and storage. Where bulk handli

First law of thermodynamics, First law of thermodynamics: The First La...

First law of thermodynamics: The First Law of Thermodynamics states that work and heat are equally convertible. The present tendency is to include all the forms of energy. The

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd