Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Thermodynamic process - thermodynamics, Thermodynamic process - Thermodynam...

Thermodynamic process - Thermodynamics: Thermodynamic system undergoes changes because of the energy and mass interactions. Thermodynamic state of system changes because of th

Control surface and flow work - thermodynamics, Control Surface and Flow Wo...

Control Surface and Flow Work - thermodynamics: Cont r o l Surface: A control system has control volume that is separated from its surrounding by real or imaginary contro

Calculate the normal force, Problem You are playing tetherball because ...

Problem You are playing tetherball because you are seven years old and you have nothing better to do.  If the tetherball has a mass of 1 kg and the rope is 1.5 m long and can w

Calculate the kic from the data - thick cylinder, Calculate the KIC from th...

Calculate the KIC from the data - thick cylinder: In a fracture test a 3-point bend specimen of thickness 20 mm and depth 25 mm is supported over a span of 100 mm. The specime

Benefits of cad, Quality Improvement : CAD can improve the quality of eng...

Quality Improvement : CAD can improve the quality of engineering design by increasing the efficiency and effectiveness of the designers. This can be observed with excellent

Bending equation, State and define the bending equation and mention it''s u...

State and define the bending equation and mention it''s units and derive it

Turbine, what do you mean by compounding of turbine?explain pressure-veloci...

what do you mean by compounding of turbine?explain pressure-velocity compounding with neat sketch.

First law of thermodynamics, First law of thermodynamics: The First La...

First law of thermodynamics: The First Law of Thermodynamics states that work and heat are equally convertible. The present tendency is to include all the forms of energy. The

Explain the semi-automatic extension of screw conveyor, Explain the Semi-Au...

Explain the Semi-Automatic Extension of screw conveyor "Semi-Automatic Extension of screw conveyor as per the screed width by telescopic-tube" Procedure: The extension of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd