Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Explain the bar chart of hydrostatic sensor paver machine, To select the pr...

To select the project, if not already done. Due to above Problem's in Hydrostatic sensor paver machine, now the select the project and solves the problems and also the cost eff

Thermodynamics, The attached figure depicts an indirectly fired gas turbine...

The attached figure depicts an indirectly fired gas turbine engine. In the gas turbine engine, air is compressed to a high pressure and then heat is added. The high pressure, high

Boiler, boiler performance.

boiler performance.

Determine the value of the maximum shear stress, Determine the value of the...

Determine the value of the maximum shear stress: A circular beam of 100 mm diameter is subjected to a shear force of 5 kN. Determine the value of the maximum shear stress & al

Co-efficient of thermal conductivity, State required Features of Fourier La...

State required Features of Fourier Law. What are the factors on which co-efficient of thermal conductivity (K) depends upon ? Write the unit of K.

Moment of inertia.., mathematical expression of moment of inertia

mathematical expression of moment of inertia

Types of stresses, Types of stresses: In general stress is divided in ...

Types of stresses: In general stress is divided in to three group as: various types of stresses may be classified as: 1. Simple or direct stress (Tension, Compressi

Water vortex fountain, hi there there is many way to make the water vortex...

hi there there is many way to make the water vortex but am not sure how can we make the one like > (www.williampye.com/work/charybdis)

Thermodynamics, microscopic and macroscopic view points

microscopic and macroscopic view points

Determine root of equation, Determine root of equation xe x = cosx by Mull...

Determine root of equation xe x = cosx by Muller's method. Solve the following equations by Matrix Inversion method.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd