Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Occupational safety acts, Occupational Safety Acts The occupational sa...

Occupational Safety Acts The occupational safety Acts are intended to cover every employees (even if single) and all kinds of employers from manufacturing and construction to

Matlab Question, help write the matlab code desired: The sine function can ...

help write the matlab code desired: The sine function can be evaluated by the following infinite series as (where the angle x is given in radians): xsinx = x-(x^3)/3! + (x^5)/5! -

Working of drum type brake , Working of Drum Type Brake: When we apply br...

Working of Drum Type Brake: When we apply brake to the motorcycle that means we are applying force 'F' to the brake shoes. This force pushes the brake shoes towards the drum surf

Construction and working of locomotive boiler, CONSTRUCTIO N and WORKING: ...

CONSTRUCTIO N and WORKING: The boiler barrel is cylindrical shell and consists of large number of flue tubes. The barrel comprise of a rectangular fire box at one end and a

Three particle system, Three Particle System Suppose we have two partic...

Three Particle System Suppose we have two particles of masses  m 1  and  m 2   already fixed in space at distance  r 12  from each other. Let us bring in a third particle of

What is, what is soundness of casting.

what is soundness of casting.

Cross drainage works, Cross Drainage Works: Culverts A large ...

Cross Drainage Works: Culverts A large number of culverts are needed for taking care of the streams crossing the railway lines. The culverts can be one of the followi

Can you explain the mobile bed model, Q. Can you explain the Mobile bed mod...

Q. Can you explain the Mobile bed model? Mobile bed models can again be either geometrically similar or vertically exaggerated. Models of the former type permit study of proble

DNC, limitations of DNC

limitations of DNC

What do you mean by issued for review, Q. What do you mean by Issued for Re...

Q. What do you mean by Issued for Review? This drawing issue of P&IDs is a draft and is intended for the Colt-internal review process involving affected disciplines. This draw

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd