Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Nature of shear force and bending moment - load variation, Define the natur...

Define the nature of shear force and bending moment under load variation. Sol.: The nature of SF and BM variation under two-load region is given in the table below

Chemistry, What is a petroleum gas

What is a petroleum gas

Explain straight line mechanism, a) Illustrate with the help of neat sketch...

a) Illustrate with the help of neat sketch any three straight line mechanism. b) Describe Degree of Freedom and prove the relation for Grumbler's equation.

Determine the temperature distribution, The wall shown is 1 m thick. The le...

The wall shown is 1 m thick. The left surface of the wall (x=0) is maintained at a constant temperature 200 degrees Celsius. The right surface (x=L=1 m) is insulated. The thermal c

Derive the expression of torque in closely excited system., Q.   Derive the...

Q.   Derive the expression of torque developed in closely excited magnetic system. Clearly explain then assumption made.   Sol. Double - Excited System   A doubly - ex

Show corrosion loss, Q. Show Corrosion Loss? Additional metal thickness...

Q. Show Corrosion Loss? Additional metal thickness must be added, to compensate for anticipated loss due to metal reacting with the environments to which it is subjected, inclu

#tool life, #tool life formular for diferent n values

#tool life formular for diferent n values

Pultrusion, Pultrusion Structure sections of long length are generated...

Pultrusion Structure sections of long length are generated by putting the fibres via resin bath and heated dies of exact shapes. Unidirectional fibres along with high volume f

Withworth quick return mechanism, its definition, principle, explanation, a...

its definition, principle, explanation, application, and a diagram

Describe dry and wet parting materials, Q. Describe Dry and wet parting mat...

Q. Describe Dry and wet parting materials? Dry parting materials: These are applied by dusting. These include : charcoal, ground bone and limestone, lycopodium(a yellow veget

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd