Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Give expressions for work done and efficiency for otto cycle, Draw neat dia...

Draw neat diagram of aWankel engine and explain its working. Derive expressions for work done and efficiency for an Otto cycle. Illustrate with diagrams the several types of

Concurrent force system - mechanics, Concurrent force system: It state...

Concurrent force system: It state that if force acting at a point on a rigid body, it can be considered to act at any other point on its line of action, given this point is ri

Flow work - thermodynamics , Flow work: Flow work is energy possessed ...

Flow work: Flow work is energy possessed by the fluid by virtue of its pressure. Displacement Work: When piston moves in cylinder from position 1 to 2 with vo

Predict the output of load - curved beam theory, A load cell based on a "pr...

A load cell based on a "proving ring" is shown below.  The circular portion of the load cell has an inner radius of 1.25 in and outer radius of 1.50 in.  The ring has a depth (i.e.

Lifting machine, all information about lifting machine

all information about lifting machine

Determine the stress in the meridional direction, Determine the stress in t...

Determine the stress in the meridional direction: A doubly curved shell of thickness 8 mm is filled through a liquid under an internal pressure of 2.0 N/mm 2 . At a specific p

Effect of the wet and dry curing methods on the strength, Effect of curing ...

Effect of curing conditions on strength, porosity, absorptivity, and shrinkage of concrete in hot and dry climate Abstract This term paper will study the effect of the wet a

Chemistry, What is carbonation.? Discuss its stability s mathod of formatio...

What is carbonation.? Discuss its stability s mathod of formation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd