Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Calculate strength coefficient - true stress and true strain, Calculate str...

Calculate strength coefficient: A copper specimen of 64 mm gauge length and 12.80 mm dia. was tested in tension. Following two diameters were recorded in the plastic range of

Determine directions of the wave vectors-double refraction, Double Refracti...

Double Refraction An unpolarized plane wave is incident from free space onto a quartz crystal (n e = 1.553 and n o = 1.544) at an angle of incidence 30°. The optic axis lies i

Define heat for electrical resistance welding, Q. Define Heat for electrica...

Q. Define Heat for electrical resistance welding? The heat, H for electrical resistance welding is generated by passing a large electrical current ( of the order of 3000 to 100

Arc strikes-metallurgical defects, Arc strikes Represent any localised ...

Arc strikes Represent any localised heat affected zone caused by an arc. Arc strike tends to produce hardening particularly in high carbon steels and alloy steels. Grinding of

Steam systems - air-conditioning guidelines, Ensure all low points on steam...

Ensure all low points on steam mains and equipment have drip trap assembly. High pressure condensate to be taken to flash tanks, provide detail of flash tank. Use minimum 24" (610

What do you mean by contractility, Q. What do you mean by Contractility? ...

Q. What do you mean by Contractility? Heart being a muscular pump the ability to eject blood depends on the ability to contract. Another factor is the resistance in the vascula

Design evacuation systems for plant, Q. Design evacuation systems for plant...

Q. Design evacuation systems for plant? The plant will have designated Muster areas where personnel can go during an emergency and be accounted for and from which they can then

Find the stresses by finite method, The stepped bar in Fig Q6 is stretched ...

The stepped bar in Fig Q6 is stretched along the vertical axis and the maximum upward displacement is found to be 0.008 m. The bar has cross-sectional areas of A 1 and A 2 ov

Explain what is meant by the nanocomposite, Choose either a plastic, compos...

Choose either a plastic, composite, titanium alloy or aluminium alloy for the applications below and briefly explain your choice. In explaining your choice, relate the properties t

Motion of two bodies - rough surface and rough pulley, Motion of two bodies...

Motion of two bodies - rough surface and rough pulley: THE HORIZONTAL SURFACE IS ROUGH AND THE STRING IS PASSING OVER ROUGH PULLEY. Figure shows two weights W 1 and W 2 c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd