Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Thermal Stresses in Tapered Section, A rigidly fixed circular bar 1.75mm lo...

A rigidly fixed circular bar 1.75mm long uniformly tapers from 125mm dia. at 1 end to 100mm dia. at other end. If the max. stress in the bar is not to exceed 108MPa. Find the tempe

Energy balance for a vapor stream, Write down the energy balance for a vapo...

Write down the energy balance for a vapor stream going through a throttling valve (a valve that just reduces the pressure).  State your assumptions. Suppose a nonvolatile materi

Manufacturing systems and automation, This formative assignment seeks to de...

This formative assignment seeks to develop and assess skills associated with basic modern ICT tools and competence in the techniques of Rough-Cut Capacity Planning and F inan

Refrigeration cycle, 1.5kw/ton of refrigeration is required to maintain tem...

1.5kw/ton of refrigeration is required to maintain temp of -40c in the refrigerator.if the cycle works on carnot cycle.determine 1.cop,2.sink temp 3. heat rejejected to the sink/to

Potential deadlock, Suppose an interesting situation represented in followi...

Suppose an interesting situation represented in following figure (b). The Petri net somewhat shows a paradoxical situation. Intuitively we contain in our minds that by raising the

Manufacturing systems and technology, The first successful numerical machin...

The first successful numerical machine tool was developed at MIT in the year:

Forced air cooling - type of cooling system, Forced Air Cooling: A fa...

Forced Air Cooling: A fan makes a difference between natural air cooling and forced air-cooling. The fan supplies the required air to carry away heat from the engine cylinder

Deliberately placing column from centre in footing, Describe method of deli...

Describe method of deliberately placing column from centre in footing. The method of deliberately placing a column away from the centre of the footing so that resulting soil pr

Find out the intensity of the external pressure, Find out the intensity of ...

Find out the intensity of the external pressure: A thick cylinder of 0.5 m external diameter & 0.4 m internal diameter is subjected simultaneously to internal & external press

Study and design of pattern, TO Study And Design Of Pattern A pattern i...

TO Study And Design Of Pattern A pattern is an element used for making cavities in the mould, into which molten metal is poured to produce a casting. It is not an exact replica

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd