Major considerations in selecting marine plants, Civil Engineering

Assignment Help:

Question

What are major considerations in selecting marine plants and land plants for fitting of band drains?


Answer

For fitting of band drains by marine plants, it has got to sufficient water depth to accommodate marine plants in first place. Though, due to effect of tides and waves, establishment of the position for installation of band drains and subsequent installation works can be affected. In adding together, establishment rate of marine plants is higher than of land plants.

For fitting of band drains by land plants, intricacy may be encountered during installation of band drains through reclaimed layer as C&D material. Land plants can take longer construction time due to above-mentioned difficulty. now and again while bring of public fill is enlarged suddenly, it could be preferable to place these fill at once into position and in this state installation of band drains is delayed so that construction of band drains is transformed to by land plants.

 


Related Discussions:- Major considerations in selecting marine plants

Consideration of hazards in design, • Gas turbines produce noise, heat radi...

• Gas turbines produce noise, heat radiation and exhaust gas emissions that are potentially a danger to health • Fuel is flammable and there are hot surfacesand moving parts

What is a projection line, Projection line is the way, in which the earth i...

Projection line is the way, in which the earth is made known on a flat piece of paper.

Shear stress, Shear stress distribution in circular section

Shear stress distribution in circular section

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Hazard, • A potential source of harm - Mechanical hazard - Electrical...

• A potential source of harm - Mechanical hazard - Electrical hazard - Cutting hazard - Toxic hazard - Fire hazard - Explosion hazard

3-tap to 6-tap increase water pressure, Will going from a 3-tap to 6-tap i...

Will going from a 3-tap to 6-tap increase water pressure? Ans) No, the pressure will be the similar, you will get more volume only if your pumps can handle the GPM, to enhance p

Define factor that is not concerned with schedule control, Schedule control...

Schedule control is concerned with all of the following except: a. Influencing the factors which create schedule changes b. Determining that the schedule has changed c.

Define structural damage - underwater inspection of bridge, Define Structur...

Define Structural Damage - underwater inspection of bridge? Structural damage to the substructure below waterline can be classified as under: i. Construction damage or error

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd