Main problems related with prestressed concrete piles, Civil Engineering

Assignment Help:

Question

What are main problems related with prestressed concrete piles?


Answer

Origin of Daido piles comes from Japan where these prestressed actual piles are used as substitute plies. Holes are preformed in position and Daido piles are located inside these preformed holes with subsequent grouting of void gap between piles and neighbouring ground. Though, in Hong Kong Daido piles are constructed by driving into ground by hammers instead of originally designed replacement means. A fitting means of Daido piles is changed, construction troubles like twisting of pile tip shoes, crushing of concrete at pile tip and so on.

 


Related Discussions:- Main problems related with prestressed concrete piles

Force system, show the diagram for non coplanar non concurrent force system...

show the diagram for non coplanar non concurrent force system

Shear and tensile strength, What is the difference between shear and tensil...

What is the difference between shear and tensile strength? Ans) Tensile Strength for a Bolt is explained by applying a Force along it long axis. Shear Strength for a Bolt is exp

Temperature requirements for bituminous material, Question In all-purpo...

Question In all-purpose Specification for Civil Engineering Works, it details temperature requirements for bituminous material all through and after mixing. What is cause beh

Rubber dams – air-filled vs water-filled, Most of the existing rubber dams ...

Most of the existing rubber dams are of air-filled types. Water-filled rubber dams aren't preferred for the below reasons: (i)  By giving same sheet length and dam height, tensi

Pcc, Specific Gravity & Water Absorption of Fine Aggregate

Specific Gravity & Water Absorption of Fine Aggregate

What do you mean by stock verification sheets, Q. What do you mean by Stock...

Q. What do you mean by Stock Verification Sheets? The proper custody and accountal of stores is the prime duty and function of an executive or the stockholder. To ensure this v

Cavities under structures., This is the title for my thesis for masters in ...

This is the title for my thesis for masters in structural engineering. Is it possible to make for me the literature review? I already have my references.

Survey question, Sir morng..i know about WCB AND RB.With diagram..pls help ...

Sir morng..i know about WCB AND RB.With diagram..pls help me sir

State the term - post-tensioned concrete, State the term - Post-tensioned c...

State the term - Post-tensioned concrete In Post-tensioned concrete construction, as shown in Figure,  tendons are placed inside concrete and stretched after concrete has attai

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd