Lubrication of rail joint, Civil Engineering

Assignment Help:

Lubrication of rail joints is one of the important items of permanent way works incidental to systematic track maintenance, the lubrication of joints is done for the following purpose -

i. To allow for free expansion of rails.

ii. To reduce wear and tear on the fishing planes of rails and fish plates.

The lubrication of rail joints also called oiling and greasing of fishplates is done once a year for all the joints during the moderate season which does not have extremes of weather (both hot & cold ). Rainy season is also excluded for this purpose. The lubricant used is a paste of workable consistency made of plumbago Kerosine oil and black oil in the following proportion -

Plumbago ( Dry Graphite ) = 5 kg.

Kerosine oil ( IInd Quality ) = 3.5 Liter.

Black or Reclaimed oil = 2.75 Liter.

For 100 joints of 52 kg / 90R or for 125 joints of 75 R / 60 R

Some items only plumbago and kerosin oil is used in the ratio of 3 : 2 for lubrication of fishplates the black oil is however used for oiling of fish bolts and nuts.


Related Discussions:- Lubrication of rail joint

Show disadvantages of excessive concrete covers, Q. Disadvantages of excess...

Q. Disadvantages of excessive concrete covers? In reinforced concrete structures cover is generally provided to protect steel reinforcement from corrosion and to provide fire r

What do you mean by depth of scour, Q. What do you mean by Depth of Scour? ...

Q. What do you mean by Depth of Scour? The maximum scour depth in a stream can be ascertained when ever possible by actual sounding at or near the site proposed for the bridge

Chain, describe and sketch a survey chain

describe and sketch a survey chain

Packing resources in joint of concrete pipes in pipe jacking, Question ...

Question What is key function of packing resources in joint of concrete pipes in pipe jacking ? Answer Packing resources are about 10 to 20mm broad and are usually mad

Explain the wetted perimeter, Explain the Wetted Perimeter (P) The line...

Explain the Wetted Perimeter (P) The linear length of the interface between the fluid's cross-sectional plane edges in contact with the pipe or channel wall.

Define limitations of radiography - inspection of bridge, Define Limitation...

Define Limitations of Radiography - Underwater Inspection of Bridge? i. Radiography is a costly and time consuming method, which re- quires extensive safety measures to be adop

Stone massonary, what is a 1st sort,2nd sort, 3rd sort stone masonary

what is a 1st sort,2nd sort, 3rd sort stone masonary

High temperature in laying bituminous pavement, High temperature in laying ...

High temperature in laying bituminous pavement Generally bituminous materials are also broadly categorized into two types viz bitumen McAdamsand hot-rolled asphalts. At the ti

Centroid, How to calculate the centroid of parabola?

How to calculate the centroid of parabola?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd