Loss of camber in steel girders, Civil Engineering

Assignment Help:

Steel triangulated (open web) girders are provided with camber to compensate for deflection under load. Out of the total design camber, the part corresponding to dead load is called dead load camber. The balance is called live load camber which should be available as visible and measurable camber in the girder when not carrying load.

Loss of camber can be mainly attributed to :

a) Overstressing of members beyond the elastic limit

b) Overstressing of joint rivets

c) Loose rivets


Related Discussions:- Loss of camber in steel girders

What is the pre-tensioned concrete, What is the Pre-tensioned concrete ...

What is the Pre-tensioned concrete In Pre-tensioned concrete tendons are kept stretched with suitable mechanisms and concrete is cast into the forms through which stretched ten

Define the cost of shock transmission unit, Define the Cost of shock transm...

Define the Cost of shock transmission unit? There is a keen competition among the few STU manufacturers. For the second Bassein Creek Bridge, the average cost of two STUs of ca

Advantages and disadvantages of water transport, Advantages and Disadvantag...

Advantages and Disadvantages of Water Transport: The following are the advantages of water transport: (a)        Since the vessels travel on water, no investment is needed

M, symbols of electrical layout

symbols of electrical layout

Tests on cement, Tests on Cement: The following tests are conducted o...

Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng

Show the limitations of grillage analysis, Q. Show the Limitations of grill...

Q. Show the Limitations of grillage analysis? In designing the number of cells for concrete box girder bridges, in case depth of a box girder bridge exceeds 1/6 or 1/5 of bridg

Designing lateral resistance of piles, Question While designing later...

Question While designing lateral resistance of piles , have to engineers only use earth pressure against pile caps simply? Answer In case of designing lateral loa

Explain flow measurement with weirs, Explain Flow Measurement with Weirs ...

Explain Flow Measurement with Weirs Fixed plates positioned vertically in an open channel over which flow is directed through an opening. The opening linear distance is termed

.Chemestry, How desalination of water can be acheived by reverse osmosis an...

How desalination of water can be acheived by reverse osmosis and electrodialysis process?

Embankment construction, Embankment Construction: Selection of Soil...

Embankment Construction: Selection of Soil Soil is the material used for embankment construction, though other materials like rock and fly-ash are also used in specia

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd