List the process maturity levels in seis cmm, Software Engineering

Assignment Help:

List the process maturity levels in SEIs CMM.

Level 1:Initial - Few processes are explained and individual efforts are taken.

Level 2: Repeatable - To track cost schedule and functionality basic project management processes are established.

Level 3: Defined - The process is standardized, documented and followed.

Level 4: Managed - Both the software process and product are quantitatively understood and controlled using detailed calculated.

Level 5: Optimizing - Establish mechanisms to plan and execute change.

 


Related Discussions:- List the process maturity levels in seis cmm

Explain path testing, Testing to satisfy coverage criteria that every logic...

Testing to satisfy coverage criteria that every logical path by the program be tested. Often paths by the program are grouped into a finite set of classes. Single path from every c

Define design process, Define design process. Design process is a sequ...

Define design process. Design process is a sequence of steps carried through which the requirements are translated into a system or software model.

Explain test plan, Documentation specifying the scope, approach, resources,...

Documentation specifying the scope, approach, resources, and schedule of intended testing activities. It signifies test items, the features to be tested, the testing tasks, respons

What are the functions of data architecture, What are the functions of data...

What are the functions of data architecture? It gives the information needed for a business function. Recognize the data objects and their relationship. Eg: Custome

PSEUDO CODE, You are to create a decision table to help you decide what to ...

You are to create a decision table to help you decide what to do for the day. If it is a weekday and it is not a holiday, then you go to work. However, if it is a weekday and it

What are the problems in comes in SRS, What are the Problems in comes in SR...

What are the Problems in comes in SRS There are numerous features which make requirements analysis difficult. These are explained below: 1. Complete requirements are diffic

How to perform risk analysis during software testing, Describe how to perfo...

Describe how to perform Risk Analysis during software testing. Whereas a test plan is being formed, risks involved in testing the product are to be taken into consideration al

List the guidelines for data design, List the guidelines for data design. ...

List the guidelines for data design. i. Apply systematic analysis on data. ii. Identify data structures and related operations. iii. Establish data dictionary. iv. Use

Explain the different architectures developed during bpe, What are the diff...

What are the different architectures developed during BPE? Data architecture àframework for the information needs of a business. Application architecture à incorporates the

Explain the purpose of an outer join, (a) What is a view? (b) What is ...

(a) What is a view? (b) What is the implication of creating a view with the select * statement in the view definition? (c) Make reference to the relational schema given in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd