Linear programming solution by steps for two-phase method, Operation Research

Assignment Help:

Solve by Steps for Two-Phase Method

Max Z = 5x1 + 8x2

Subject to

3x1 + 2x2 ≥ 3

x1 + 4x2 ≥ 4

x1 + x2 ≤ 5

    &     x1 ≥ 0, x≥ 0

Answer

Standard LPP

 

Max Z = 5x1 + 8x2  

    Subject to

                        3x1 + 2x2 - s1+ a1 = 3

                        x1 + 4x2 - s2+ a2  = 4

                        x1 + x2 + s3 = 5

                        x1 , x2 , s1, s2, s3, a1, a≥ 0

 

Auxiliary LPP

Max Z* = 0x1 + 0x2 + 0s1 + 0s2 + 0s3 -1a1 -1a2

    Subject to

                        3x1 + 2x2 - s1+ a1 = 3

                        x1 + 4x2 - s2+ a2  = 4

                        x1 + x2 + s3 = 5

                        x1 , x2 , s1, s2, s3, a1, a≥ 0

1377_two-steps-method-LPP.png

 

As all Δj ≥ 0, Max Z* = 0 and no artificial vector appears in the basis, we move to phase II. 

Phase II

266_phase-II.png

As all Δj ≥ 0, optimal basic feasible solution is achieved. Thus the solution is Max Z = 40, x1 = 0, x2 = 5


Related Discussions:- Linear programming solution by steps for two-phase method

Linear programming, Q3. Solve the following Linear Programming Problem usi...

Q3. Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Methods of scientific research, Methods is a tool or a techniques used t...

Methods is a tool or a techniques used to collect data. It is procedure for obtaining knowledge based on empirical observation and logical reasoning. Field Study Metho

Multiple objectives- sampling decisions, Multiple  Objective s The sam...

Multiple  Objective s The sample  may vary according  to the  objective of the research. There  may several objectives  of marketing  research so the  sample  size  may vary a

LINEAR PROGRAMMING, A DRUG MANUFACTURER produces 2 products X1 and X2.X1 ne...

A DRUG MANUFACTURER produces 2 products X1 and X2.X1 needs 2 hours on machine A AND 2 HOURS ON MACHINE B.X2 needs 3 hours on machine A and 1 hour on machine B.If machine A can run

Inventory control of any company, give real data & find out the inventory &...

give real data & find out the inventory & give suggestions

Lp model, A company produce three sizes of windows fans small,medium and la...

A company produce three sizes of windows fans small,medium and large. The manager has formulated an LP model for production.

B. A paper mill produces two grades of paper viz., b. A paper mill produces...

b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Distribution methods, 1: explain vogel''s approximation method? 2: explain ...

1: explain vogel''s approximation method? 2: explain optimality test?

Investigate the link between engine wear and mileage, The Association of Ma...

The Association of Malawi Mechanics has commissioned a study to investigate the link between engine wear and mileage. The main focus of the study is to determine whether the mileag

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd